Hanoi diverts traffic to repair elevated Ring Road 3

Minh Hạnh |

Hanoi - The Department of Construction has just announced the diversion of traffic organization to serve the repair of the elevated Ring Road 3.

Deputy Director of the Hanoi Department of Construction, Mr. Tran Huu Bao, has just signed a document on traffic flow to serve the repair of abutments, piers, bridge bearings, expansion joints and drainage systems on this route.

Specifically, the traffic organization plan on the elevated Ring Road 3 (from Mai Dich to Thang Long Avenue) is implemented as follows:

Daytime (from 6am - 10pm): Barricade 1/2 of the road surface at 09 locations of the expansion joints that need to be repaired. Vehicles move on the remaining half of the road at construction sites.

Night (from 10pm to 6am the next morning): Prohibit all vehicles from traveling on the elevated Ring Road 3, from Mai Dich overpass to Thang Long Avenue.

Vehicles are traveling in the following direction:

From the elevated Ring Road 3 going down: Vehicles will go in the direction of Mai Dich overpass (parallel urban overpass branch) - Pham Van Dong Street - Pham Hung Street (Low Ring Road 3) - through the Pham Hung - Khuat Duy Tien intersection, then take up the elevated Ring Road 3 at the entrance on Khuat Duy Tien Street (opposite Thang Long Number One building) to continue moving towards Phap Van.

From Thang Long Avenue to Mai Dich: Vehicles are moving normally.

The entrance to Mai Dich overpass and the entrance to Pham Hung street to the elevated Ring Road 3 are still operating normally.

Implementation period: 35 days (from March 23, 2025 to April 27, 2025).

The Traffic Infrastructure Maintenance Board and the construction unit are responsible for:

Fully install signs, barriers, traffic lights and night lighting. Specifically, place the sign 200m from the checkpoint location, repeat at 150m, 50m and at the checkpoint location.

For the section of the entrance to Mai Dich overpass, arrange signs of speed gradually decreasing from the checkpoint location by 500m, repeat at 300m, 200m, 100m to ensure traffic safety.

At the daytime barriers on the elevated Ring Road 3, fully install signs of similarly decreasing speed.

Before implementation, it is necessary to work with the Traffic Inspectorate, Traffic Police and local authorities to arrange forces to coordinate in guiding the flow of vehicles at checkpoints. At the same time, remote traffic diversion and installation of a sign system according to regulations. In case of traffic congestion, there needs to be a timely handling plan, coordinating with authorities to ensure smooth traffic.

Minh Hạnh
RELATED NEWS

Multiple car collision on Ring Road 3 in Hanoi

|

Hanoi - A collision between many cars occurred early this morning on the elevated Ring Road 3.

Reorganizing motorbike traffic on Ring Road 3

|

Hanoi - The Department of Construction will pilot traffic organization adjustment on the motorbike lane below the elevated Ring Road 3.

Iran rejects proposal for temporary ceasefire

|

Iran rejects proposal for temporary ceasefire, demands permanent end of conflict.

Case of sick pork entering the kitchen, police continue to verify whether or not there is collusion for consumption

|

Hanoi - Functional agencies are continuing to clarify whether there is collusion between businesses and Cuong Phat Company in the consumption of diseased pork.

Spontaneous landfills reoccur in Hanoi, challenging efforts to preserve the environment

|

Hanoi - Many spontaneous landfills still appear, despite the efforts of the government, local people and environmental workers.

Ambiguous confirmation of whether teachers of Song Hong Intermediate School are civil servants or laborers

|

Phu Tho - According to a report by Phu Tho Vocational College, one of the difficulties in merging Song Hong Intermediate School is the difficulty in identifying whether the 29 officials of this school are civil servants or employees.

How long will the widespread intense heat wave last

|

According to the meteorological agency, from tomorrow, April 7, hot weather will continue to expand in the North and Central regions and last for many days to come.

Factory fire in Ho Chi Minh City leaves 3 people burned

|

Ho Chi Minh City - In Vinh Tan ward, a factory fire occurred, causing 3 people to be burned and hospitalized for emergency treatment.

Multiple car collision on Ring Road 3 in Hanoi

Tô Thế |

Hanoi - A collision between many cars occurred early this morning on the elevated Ring Road 3.

Xe máy đi dưới vành đai 3 lưu ý hướng di chuyển mới

Nhóm PV |

Hà Nội - Thành phố thí điểm điều chỉnh tổ chức giao thông một số tuyến đường. Xe máy đi dưới vành đai 3 cần lưu ý cách di chuyển mới.

Reorganizing motorbike traffic on Ring Road 3

Minh Hạnh |

Hanoi - The Department of Construction will pilot traffic organization adjustment on the motorbike lane below the elevated Ring Road 3.