Hanoi reclaims land from 160 households, prepares to open a 4-lane road

HỮU CHÁNH |

Hanoi - Thanh Xuan District completed the recovery of more than 14,000m2 of land from 160 households and 11 organizations to expand Nguyen Tuan Street to 4 lanes, with a capital of 400 billion VND.

On the morning of October 15, confirming with Lao Dong reporter, the leader of the Thanh Xuan District Construction Investment Project Management Board (Hanoi) said that by 11pm on October 14, the last two households had agreed to hand over the land for the project to upgrade and expand Nguyen Tuan Street.

Households subject to site clearance have an additional month (from now until mid-November 2024) to move their belongings to their new residence.

The leader of Thanh Xuan District People's Committee said that it is expected that by the end of 2024, after completing the dismantling of works and relocation of technical infrastructure, the district will direct the Project Management Board and contractors to implement the project, striving to complete the project and put it into use by mid-2025.

When completed, the project will help reduce traffic congestion in the area, beautify the urban area, and contribute to the socio-economic development of Hanoi in general and Thanh Xuan district in particular.

The project to renovate and expand Nguyen Tuan Street was approved by Thanh Xuan District People's Committee in 2018, with a total investment of about 400 billion VND.

By 2020, Thanh Xuan District People's Committee continued to approve the project's construction drawing design in Decision No. 1928/QD-UBND.

The project is 720m long, starting at the intersection with Nguyen Trai Street, ending at alley 162 Nguyen Tuan, with a cross-section expanded to 21m, including a 15m wide roadway and 3m wide sidewalks on both sides.

To implement the project, Thanh Xuan district will reclaim and clear 14,334 square meters of land, involving 11 organizations and 160 households and individuals.

Initially, Thanh Xuan district set a target to approve all compensation and site clearance plans by the end of 2022. By mid-2023, the project will be implemented and the road expansion will be completed after 1 year.

However, site clearance encountered many difficulties, causing the project to stall.

According to Lao Dong, Nguyen Tuan Street (from Nguyen Trai intersection to lane 162) has a narrow cross-section, with bottlenecks leading to constant traffic jams, greatly affecting people's travel.

In recent days, many residents living on Nguyen Tuan Street have proactively dismantled construction works, moved furniture, and handed over the site to local authorities to implement the project.

a
Many households are dismantling constructions and handing over land for the project to expand Nguyen Tuan Street (Thanh Xuan, Hanoi). Photo: Huu Chanh
a
Nhieu cua hang treo bien thon bao di chuyen den dia diem moi. Anh: Huu Chanh
Many stores have signs announcing their move to a new location. Photo: Huu Chanh
Do dac duoc nguoi dan di chuyen den noi khac. Anh: Huu Chanh
Furniture was moved by people to another place. Photo: Huu Chanh
Mot so cong trinh da duoc thao do. Anh: Huu Chanh
Some constructions on Nguyen Tuan Street have been dismantled. Photo: Huu Chanh
a
Nguyen Tuan Street currently has a narrow cross-section and is often congested, especially during rush hour. Photo: Huu Chanh
Duong Nguyen Tuan sau khi mo rong co mat cat ngang 21m, trong do long duong rong 15m. Anh: Huu Chanh
After being expanded, Nguyen Tuan Street will have a cross-section of 21m, with a 15m wide roadway and 4 lanes, expected to reduce traffic pressure in the area. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

Hanoi reclaims land from more than 2,400 households to build 2 road projects

|

Hanoi - To implement the project to expand Tam Trinh and Linh Nam streets, Hoang Mai district will reclaim about 152,000 square meters of land from more than 2,400 households and 39 organizations.

Nguoi dan o Ha Noi giao dat mo duong truoc ngay cuong che

|

Hanoi - Many more households agreed to hand over land for the construction of the Nguyen Tuan Street expansion project before the forced land acquisition date.

6 months of construction to widen Hanoi central road to 21m

|

Hanoi - It is expected that by the end of 2024, Thanh Xuan district will start construction to expand Nguyen Tuan street, striving to complete the project by June 2025.

New developments in overcoming violations of Muong Thanh Bac Ninh project

|

The investor of Muong Thanh project sent an official dispatch to the People's Committee of Bac Ninh province requesting approval to adjust the investment policy.

HCMC Center is tidier after 5 months of sidewalk fee collection

|

HCMC - The project to collect fees on part of the roadway and sidewalk has come into effect and has created positive changes to the city's appearance after more than 5 months of implementation.

Le Van's stunning beauty in Vietnamese films ranks among Asia's best

|

As a beauty icon of Vietnamese cinema, Meritorious Artist Le Van left her mark through many classic films, including "When Will October Come?"

1.4 million North Korean youths join the army in just one week

|

North Korea claims about 1.4 million young people, including students and youth union officials, joined or re-enlisted in the military last week.

"Declare war" on waste as against "internal invaders"

|

General Secretary and President To Lam has just written an article "Fighting waste", considering this social evil as an "internal invader", affecting our country's goal of "rich people, strong country".

6 months of construction to widen Hanoi central road to 21m

HỮU CHÁNH |

Hanoi - It is expected that by the end of 2024, Thanh Xuan district will start construction to expand Nguyen Tuan street, striving to complete the project by June 2025.

Nguoi dan o Ha Noi giao dat mo duong truoc ngay cuong che

HỮU CHÁNH |

Hanoi - Many more households agreed to hand over land for the construction of the Nguyen Tuan Street expansion project before the forced land acquisition date.

Hanoi reclaims land from more than 2,400 households to build 2 road projects

HỮU CHÁNH |

Hanoi - To implement the project to expand Tam Trinh and Linh Nam streets, Hoang Mai district will reclaim about 152,000 square meters of land from more than 2,400 households and 39 organizations.