Image of the construction of the Tay Ho bridge with Dong Anh, capital of more than 20,000 billion VND

HỮU CHÁNH |

Hanoi - After the groundbreaking ceremony, contractors mobilized machinery and human resources to implement the Tu Lien bridge project through Dong Anh district.

On May 19, the project to build Tu Lien bridge and the road at both ends of the bridge with a total investment of nearly 20,000 billion VND was officially started.

The project is about 5.15km long, starting at Nghi Tam Street (Tay Ho District), ending at Truong Sa Street (Dong Anh District).

s
The access road to Tu Lien bridge on the Dong Anh district side (Hanoi) is under construction. Photo: Huu Chanh

According to the reporter of Lao Dong Newspaper, after more than 20 days of construction, contractors have leveled the ground and constructed on a distance of about 2km of the East England access road.

With the river-crossing bridge component project, it is noted that in both the Red River and Duong River, many barges are "carrying" machinery to conduct geological drilling.

A representative of the Hanoi Traffic Construction Investment Project Management Board (investor) said that contractors are drilling geology to build the main bridge piers across the river, this work is carried out day and night.

Cong truong du an xay dung cau Tu Lien phia huyen Dong Anh (Ha Noi). Anh: Huu Chanh
Construction site of the Tu Lien bridge approach road project in Dong Anh district. Photo: Huu Chanh

For the inner city area, after nearly 1 month of construction, the Tu Lien bridge project in Tay Ho district has not yet been constructed at the site.

The reason is that the project site is about 2km long and the intersection with Nghi Tam Street passing through the residential area has not been cleared.

The Tu Lien Bridge and Road project at both ends of the bridge has been approved, including 4 component projects, including 3 component projects for site clearance and 1 investment project to build Tu Lien Bridge and access roads.

Component projects for site clearance in 3 districts: Tay Ho, Long Bien, Dong Anh (in the wards of Quang An, Yen Phu, Tu Lien, Ngoc Thuy, Xuan Canh, Dong Hoi) have a total investment of about 4,332 billion VND.

The total area of land acquisition and clearance is about 62.53 hectares with a total expected of about 701 cases of land acquisition (412 cases of residential land, 280 cases of agricultural land and land of organizations, public land), of which about 257 cases of residential land are expected to be resettled.

May moc tap ket phuc vu thi cong du an. Anh: Huu Chanh
Machinery is gathered to serve the project construction. Photo: Huu Chanh

Assessing the volume of land cleared by districts for the project, a representative of the Hanoi Traffic Construction Investment Project Management Board said that the land within the construction scope of the Dong Anh district project has been implemented by the Dong Anh district People's Committee at about 90%, basically with land for overall construction.

With the site in Tay Ho and Long Bien districts, the two districts have completed the survey and counting plan.

Regarding the relocation and resettlement of households affected by the project, the Hanoi Traffic Construction Investment Project Management Board said that Tay Ho District has the largest number of people having to relocate and resettle.

"Currently, the city has agreed to arrange a resettlement housing fund in Dong Anh district to serve households that have to relocate to serve the project. The investor is coordinating with the People's Committee of Long Bien District, Tay Ho to carry out support for the implementation of the resettlement area, and will then relocate households subject to site clearance to live there" - said the investor's representative.

HỮU CHÁNH
TIN LIÊN QUAN

The bridge connecting Long Bien with Gia Lam has built 3 bridge piers, at risk of having to stop construction

|

Hanoi - The road bridge over the Duong River is at risk of stopping construction when it has only completed 3 bridge piers. The delay in site allocation is the reason for the project's progress.

Hanoi officially starts construction of the bridge connecting Tay Ho with Dong Anh

|

Hanoi - On the morning of May 19, the City People's Committee organized the groundbreaking ceremony for the Tu Lien Bridge and the road at both ends of the bridge.

The bridge connecting Long Bien with Gia Lam is behind schedule, no completion date has been set

|

Hanoi - The slow handover of the site has caused the road bridge project across the Duong River to not be completed in 2025 as planned and the completion date has not been set.

A major road in Hanoi is under repair, vehicles are banned from circulating from night to morning

|

Hanoi - From 10pm - 6am, vehicles are prohibited from traveling on Ring Road 3 from Nguyen Trai - Thang Long Avenue to repair the expansion joints and bridge deck.

Landslide on National Highway 15D, road to La Lay International Border Gate cut off

|

Quang Tri - The landslide occurred while the construction unit was expanding the curve on National Highway 15D to the La Lay international border gate, causing traffic disruption.

Russian general arrested on corruption charge

|

Russia arrested Senior Lieutenant General Viktor Strigunov, former Deputy Commander of the National Guard, on serious corruption charges.

Millions of cars and motorbikes in Vietnam are about to undergo emission inspection

|

According to the Director of the Department of Environment, in July, emission standards will be issued for motorbikes and mopeds.

Accidents lurk but many people still ignore them, determined to ride motorbikes onto the highway

|

Hanoi - Just because they want to get to work quickly, many people still ignore the danger of riding motorbikes on Thang Long Avenue Expressway.

The bridge connecting Long Bien with Gia Lam has built 3 bridge piers, at risk of having to stop construction

HỮU CHÁNH |

Hanoi - The road bridge over the Duong River is at risk of stopping construction when it has only completed 3 bridge piers. The delay in site allocation is the reason for the project's progress.

Hanoi officially starts construction of the bridge connecting Tay Ho with Dong Anh

KHÁNH AN |

Hanoi - On the morning of May 19, the City People's Committee organized the groundbreaking ceremony for the Tu Lien Bridge and the road at both ends of the bridge.

The bridge connecting Long Bien with Gia Lam is behind schedule, no completion date has been set

HỮU CHÁNH - ĐẶNG TIẾN |

Hanoi - The slow handover of the site has caused the road bridge project across the Duong River to not be completed in 2025 as planned and the completion date has not been set.