The bridge connecting Long Bien with Gia Lam has built 3 bridge piers, at risk of having to stop construction

HỮU CHÁNH |

Hanoi - The road bridge over the Duong River is at risk of stopping construction when it has only completed 3 bridge piers. The delay in site allocation is the reason for the project's progress.

In July 2023, the road bridge under the Duong River waterway upgrade project started construction. By September, the contractor began construction on site.

The project starts at the old Duong bridge intersection on Ngo Gia Tu street, Long Bien district; the end point is at the intersection between Ha Huy Tap street and Phan Dang Luu street, Gia Lam district, about 100m downstream from the old Duong bridge.

d
The road bridge over the Duong River started construction in July 2023. Photo: Huu Chanh

According to the report of the Railway Project Management Board, Ministry of Transport (now Ministry of Construction - investor), the XL02 package (Duong Road Bridge) has completed pillars T3; for the two towers T4 and T5, the pillar body construction has been completed and the tower sections are under construction; the output reached 43.7% of the contract value (230.2/526.5 billion VND).

Currently, both overpasses and access roads at both ends of Long Bien and Gia Lam are still unable to be constructed due to lack of land.

"Currently, the road bridge project is only constructing the T4 and T5 pillars on the riverbed, and will be completed in the second quarter of 2025. If we do not switch to the construction of the bridge girder canopy, from July 2025, the project will have to stop construction of the road bridge due to lack of land" - Mr. Mai Xuan Tan - Director of Duong Railway Bridge Project Management (Reline Project Management Board) said.

s
The two piers of the T3 and T4 bridges in the middle of the Duong River are being constructed by the contractor. Photo: Huu Chanh

Mr. Pham Van Nam, Commander of the contractor of Dat Phuong Group Joint Stock Company, said that because the bridge girder is constructed using cantilever technology, to construct the girder over the river, it is necessary to complete the overpass girder on both banks to create symmetry.

However, the site in both Long Bien and Gia Lam districts is not yet available, so the bridge piers built in the riverbed are standing still, unable to construct the girder casting symmetrical with piers T4 and T5.

According to the investor's representative, if the locality does not hand over the site by the end of July, the contractor will also run out of site, forced to temporarily suspend construction, relocate all machinery, equipment and human resources to other projects.

In case of timely site clearance in June 2025, the investor will urge and direct the contractor to increase human resources and construction equipment, try to complete the project and put it into use in the second quarter of 2026.

d
The Gia Lam site has not been handed over. Photo: Huu Chanh
s
Long Bien is also facing many households with land clearance problems. Photo: Huu Chanh

According to the Railway Project Management Board, the project has a total land area requiring site clearance of about 4.96ha/141 households (Long Bien district about 3.33ha/55 households; Gia Lam district about 1.63ha/86 households). The cost of site clearance is 650 billion VND.

Currently, the project has only handed over about 8%, mainly public land, land managed by agencies and units, and 16/141 households on the dike road (on the side of Long Bien district) are affected.

Currently, Long Bien district is conducting a counting and determining the origin of land of households within the clearance area, and has not yet conducted procedures to move the power measuring station at the T2 pillar construction site.

Gia Lam District is appraising the draft compensation, support and resettlement plan to publicize the draft plan, and has not yet relocated technical infrastructure works. The implementation is still very slow (the drawing of resettlement locations has not been completed, the appraisal of the draft plan has not been completed).

Thus, the site clearance work did not meet the handover schedule on May 30, 2025 as directed by the City People's Committee.

The Railway Project Management Board requested Gia Lam district and Long Bien district to urgently deploy site clearance and relocation of technical infrastructure works to hand over the site in month 6; in which priority is given to temporary accommodation in advance for about 27 households and the Long Bien Power Company's electric measuring station to hand over part of the site to serve the construction of items including abutments M1, piers T1, T2 and piers T6 to construct the balanced cantilever beam of the road bridge.

HỮU CHÁNH
TIN LIÊN QUAN

Hanoi Chairman finalizes the time to start construction of 2 bridges across the Red River

|

Hanoi - Chairman of Hanoi People's Committee Tran Sy Thanh assigned specific progress units to ensure the start of construction of Tran Hung Dao Bridge and Ngoc Hoi Bridge according to plan.

Hanoi announces traffic reorganization on 2 central streets from June 11

|

Hanoi - 2 streets in Hoan Kiem district will be reorganized for traffic from tomorrow (June 11).

New road nearly 1km long in Thuong Tin district

|

Hanoi - The new route in Thuong Tin district is nearly 1km long, starting at the intersection with Provincial Road 427B and ending at Tu Ba Co Street.

The case of 900 teachers in Lao Cai who failed to receive awards, the district said "due to awareness"

|

Lao Cai - More than 900 teachers in Bac Ha district are not considered for year-end rewards for not paying compulsory charity funds.

The Ministry of Public Security proposes to resolve the case of 705,000 people who have not been tested for driving licenses

|

The Ministry of Public Security spoke out about removing difficulties and bottlenecks, urgently resolving them in the testing work to issue driving licenses.

Germany plans to provide more weapons to Ukraine despite security risks

|

German Defense Minister Boris Pistorius visited Ukraine on June 12 to discuss the next military aid packages that Berlin will provide to Kiev.

Many cadres in Hanoi are paid more than 2 billion VND when retiring early

|

Hanoi - Among the cases that have just received the regime from the city, many officials have received more than 2 billion VND when retiring early.

Latest forecast of the affected area of storm No. 1

|

According to the meteorological agency, storm No. 1 will strengthen to level 10 in the next 24 hours; then change direction to the southwest of Guangdong province (China).

Hanoi Chairman finalizes the time to start construction of 2 bridges across the Red River

KHÁNH AN |

Hanoi - Chairman of Hanoi People's Committee Tran Sy Thanh assigned specific progress units to ensure the start of construction of Tran Hung Dao Bridge and Ngoc Hoi Bridge according to plan.

Hanoi announces traffic reorganization on 2 central streets from June 11

HỮU CHÁNH |

Hanoi - 2 streets in Hoan Kiem district will be reorganized for traffic from tomorrow (June 11).

New road nearly 1km long in Thuong Tin district

KHÁNH AN |

Hanoi - The new route in Thuong Tin district is nearly 1km long, starting at the intersection with Provincial Road 427B and ending at Tu Ba Co Street.