Progress of land acquisition and site clearance for Tu Lien bridge project

KHÁNH AN |

Hanoi - Tay Ho District, Long Bien and Dong Anh District are speeding up site clearance to start the Tu Lien Bridge project on the occasion of May 19.

It is expected that on May 19, Hanoi will start construction of Tu Lien Bridge and the approach roads at both ends of the bridge.

Regarding site clearance to implement the Tu Lien bridge construction project, speaking with Lao Dong on May 5, a representative of the Tay Ho District Investment and Construction Project Management Board (DTXD) said that the boundary for site clearance projects in the district is in 3 wards of Yen Phu, Quang An, and Tu Lien.

The total area of recovered land and cleared land is expected to be about 266,524.1m2. The total number of cases of land acquisition is 558 cases (322 cases of residential land; 230 cases of agricultural land; 3 cases are organizations and 3 cases are public land).

In Tay Ho district, there are 194 cases in need of resettlement (of which Quang An ward has 84 cases; Yen Phu ward has 56 cases and Tu Lien ward has 54 cases). The total cost of site clearance is more than VND 2,884 billion.

"On April 29, the District People's Committee issued a notice of land recovery for project implementation. Regarding the submission of specific land price decisions as a basis for calculating compensation, support, and resettlement, the specific land appraisal council of the project held a land price appraisal meeting, expected to issue a specific land price decision before May 9" - a representative of the Tay Ho District Construction Investment Project Management Board informed.

Tay Ho District is also focusing on coordinating with relevant departments and branches to determine housing funds and resettlement land funds. The completion time is expected to be in May 2025.

Phuong an phan chia du an thanh phan Du an Dau tu xay dung cau Tu Lien va duong hai dau cau. Anh:
The plan divides the project into the Tu Lien Bridge Construction Investment Project and the road at both ends of the bridge.

In Long Bien district, Head of the Propaganda and Mass Mobilization Department of Long Bien District Party Committee Dinh Thi Thu Huong said that up to now, the work of reviewing the total area of land to be recovered has been basically completed. Accordingly, the total land area within the boundary is 73,794.05m2. Regarding residential land related to 63 households with an area of about 7,700m2. Agricultural land related to 15 households with an area of about 4,175m2.

The District People's Committee directs specialized departments to coordinate with the city's departments, branches and sectors to carefully review the work to be carried out when implementing the project, compile total area within boundaries, classify land groups to prepare plans to effectively implement site clearance and compensation and resettlement support policies to ensure compliance with legal regulations.

Currently, the District People's Committee is coordinating and proposing to the Departments, branches and sectors of the City People's Committee to implement the following contents such as: Approving resettlement locations as a basis for people to meet to implement site clearance; working with the Ministry of National Defense on land acquisition for national defense land and proposing specific instructions for religious land areas...

Along with Tay Ho and Long Bien districts, the work of site clearance and preparation of resettlement land funds is also being resolutely implemented by Dong Anh district. In Dong Anh district, the total area of land recovered and cleared is expected to be about 261,100m2.

On April 11, Dong Anh District People's Committee sent a report to the City People's Committee and the Department of Finance for evaluating the pre -feasibility study report. Expected to approve the project investment policy in the second quarter of 2025; approving the estimates of investment preparation for the second quarter/2025; approving plans, routes, 1/500 ratio in the second quarter/2025; Evaluation, evaluation and approval of environmental impact assessment reports in the third quarter of 2025; Make, evaluate and approve the project feasibility study report in the third quarter of 2025 and organize compensation, support and implementation of ground clearance will be in the fourth quarter of 2025.

The investment project to build Tu Lien Bridge and the two ends of the bridge (from the intersection with Nghi Tam road to the intersection with Truong Sa street) has a total length of about 5.15km. Preliminary total investment of the project 20,171 billion dong. The project was implemented in the period 2025 - 2027.

KHÁNH AN
TIN LIÊN QUAN

In 2 weeks, Hanoi will start construction of a bridge over the Red River worth more than 20,000 billion VND

|

Hanoi - 3 bridges across the Red River and 2 urban railway lines will be started by the city in 2025.

Hanoi spends more than VND5,000 billion to build a road connecting Tu Lien bridge

|

Hanoi - The road connecting Tu Lien bridge (from the intersection of Tu Lien bridge approach road with Truong Sa road to Hanoi - Thai Nguyen expressway) has a total investment of VND 5,076 billion.

Latest update on the construction of Tu Lien bridge

|

Hanoi - The Tu Lien Bridge and the approach roads at both ends of the bridge project has a total estimated investment of over VND15,000 billion, implemented in 2025 - 2027.

employee of Nam Dinh General Hospital assaulted

|

Nam Dinh - An employee of Nam Dinh General Hospital was suddenly assaulted by a young man while working at the Resuscitation Department.

People in the Nam Son landfill area have lived in pollution for 20 years, now they see a ray of hope

|

After 2 decades of living in the stench from the largest landfill in the capital, hundreds of households in Nam Son commune are about to move to new places with more satisfactory compensation plans.

4 Vietnamese people found dead in Taiwan (China)

|

The death of 4 Vietnamese people in Taiwan (China) is likely due to poisoning.

List of collectives and individuals expected to be honored in the Vinh Quang Vietnam 2025 Program

|

On the afternoon of April 28, 2025, the Council for selecting collectives and individuals to be honored in the Vinh Quang Vietnam 2025 Program met and reviewed the nominated characters from central departments, ministries and branches. It is expected to select the following collectives and individuals to consider and honor in the Vinh Quang Vietnam 2025 Program.

In 2 weeks, Hanoi will start construction of a bridge over the Red River worth more than 20,000 billion VND

KHÁNH AN |

Hanoi - 3 bridges across the Red River and 2 urban railway lines will be started by the city in 2025.

Hanoi spends more than VND5,000 billion to build a road connecting Tu Lien bridge

KHÁNH AN |

Hanoi - The road connecting Tu Lien bridge (from the intersection of Tu Lien bridge approach road with Truong Sa road to Hanoi - Thai Nguyen expressway) has a total investment of VND 5,076 billion.

Latest update on the construction of Tu Lien bridge

KHÁNH AN |

Hanoi - The Tu Lien Bridge and the approach roads at both ends of the bridge project has a total estimated investment of over VND15,000 billion, implemented in 2025 - 2027.