Completed expansion of chronically congested road in Hanoi

HỮU CHÁNH |

Hanoi - The Xuan Dieu Street upgrade project, with an investment capital of nearly 400 billion VND, has reached its completion after many years of sluggish construction.

For many years, Xuan Dieu Street has been a traffic jam in Tay Ho district (Hanoi).

The narrow road surface while receiving a large number of vehicles every day causes frequent traffic jams, making it difficult for people to travel.

To solve the above situation, in 2020, Tay Ho district invested in expanding Xuan Dieu street 1.1 km long, with an investment capital of nearly 400 billion VND.

The starting point of the project intersects with To Ngoc Van Street, the end point intersects with Au Co Street, expanded on the basis of the existing road, in which the roadway is 10.5 m wide, the sidewalk is 5 m wide.

According to the original plan, the expansion was expected to be completed after 1 year, but the project was delayed due to problems in site clearance.

In fact, the Xuan Dieu road upgrade project has been basically completed and nearly 1 km of technical route has been opened.

Only the first section of the route, which is more than 100m long (near the Tu Hoa intersection), has not been able to be constructed for many years due to land acquisition problems in 11 cases, with a total area of ​​712.02m2.

After many times of propaganda and mobilization, some households agreed to hand over the land to the project. Others did not comply, forcing the Tay Ho district government to organize compulsory land recovery according to regulations.

By June 2024, the locality had handed over the entire remaining site to the contractor to complete the project after many years of delay.

According to Lao Dong's records on the afternoon of September 28, more than 100m of Xuan Dieu Street (first section of the route) has been completed by the contractor, and the items are also basically completed.

Lighting systems, railings, and sidewalks have been installed here. A group of workers are finishing planting flowers and grass on the embankment area.

Mr. Le Xuan Hai (32 years old, Quang An ward, Tay Ho) said that the completion of the first section of Xuan Dieu road helps to remove the bottleneck that has existed for many years at the Xuan Dieu - Au Co intersection.

"During rush hour, traffic flows smoothly, there is no longer local congestion like before" - Mr. Hai excitedly said.

According to the Tay Ho District Construction Investment Project Management Board, the completion of the expansion of Xuan Dieu Street in sync with the technical opening of Au Co - Nghi Tam route will help resolve traffic congestion in the area.

Some images recorded by reporters:

Sau 4 nam thi cong, Du an nang cap duong Xuan Dieu (quan Tay Ho, Ha Noi) da hoan thanh mo rong doan tuyen dai hon 1km.
The Xuan Dieu Street upgrade project (Tay Ho district, Hanoi) has been completed after 4 years of construction. Photo: Huu Chanh
a
The first section of the route (intersection with Tu Hoa Street) has been expanded after the land acquisition issue was resolved. Photo: Huu Chanh
a
The railing, sidewalk, and lighting systems have been completed by the contractor. Photo: Huu Chanh
a
The expanded route eliminates the bottleneck that has been there for many years at the Xuan Dieu - Au Co intersection. Photo: Huu Chanh
a
Workers are laying grass and planting flowers on the embankment. Photo: Huu Chanh
Sau 4 nam thi cong, Du an nang cap duong Xuan Dieu (quan Tay Ho, Ha Noi) da hoan thanh mo rong doan tuyen dai hon 1km.
The anti-erosion embankment system along Xuan Dieu Street has been completed. Photo: Huu Chanh
a
The expanded road has a cross-section of more than 15 m, 2 lanes, sidewalk system, lighting, trees... Photo: Huu Chanh
a
The completion of the expansion of Xuan Dieu Street in sync with the technical opening of Au Co - Nghi Tam Street will help resolve traffic congestion in the area. Photo: Huu Chanh
HỮU CHÁNH
RELATED NEWS

Securities welcomes real estate stock waves

|

Although not maintaining the 1,900 point mark, the stock market recorded quite positive signals with the return of the real estate stock group.

Zalo fined 810 million VND by the Ministry of Industry and Trade, requesting termination of violations

|

The National Competition Commission (Ministry of Industry and Trade) issued a decision to fine VNG Group Joint Stock Company (Zalo) 810 million VND.

Tet Sum vay - Spring Sharing and spreading love to people in difficult circumstances

|

Vinh Long - The Provincial Fatherland Front coordinates with Tra Con commune to organize Tet Sum vay - Xuan Chia, giving more than 400 gifts to people in difficult circumstances during the Binh Ngo spring 2026.

Gasoline prices simultaneously decreased from 3 pm today, January 22

|

Gasoline and oil prices fluctuate in opposite directions from 3 pm today, January 22, after the adjustment of the inter-Ministry of Industry and Trade - Finance.

Da Nang ornamental kumquat capital is guaranteed a clean garden by traders

|

Da Nang - Thanh Ha ornamental kumquat capital (Hoi An Tay ward, Da Nang city) is being ordered by traders to whiten the garden.

Coach Kim Sang-sik is praised by Korean newspapers

|

Coach Kim Sang-sik and U23 Vietnam received attention from Korean media before the 3rd place match of the 2026 AFC U23 Championship.

Hanoi builds 45m wide road, to be completed in 2026

HỮU CHÁNH |

Hanoi has begun construction of a 2.2km long road with a 45m cross-section, expected to be completed after 1.5 years.

Hundreds of trees were moved to open a 40m wide road in Hanoi

HỮU CHÁNH |

Hanoi - Authorities have basically completed the relocation of hundreds of trees to widen Tam Trinh Street to 40m, with an investment of more than 3,300 billion VND.

Hanoi gateway road to be expanded 6 times, capital of nearly 1,500 billion VND

HỮU CHÁNH |

The main gateway road to Hanoi is about to be widened from 7-8m to 52m to help reduce traffic congestion and contribute to the socio-economic development of the capital.