The Ministry of Construction has just decided to announce the termination of the emergency situation of natural disasters issued earlier to overcome damage to traffic infrastructure on Truong Son Dong road, under the management of Road Management Zone III.
According to the decision, the termination of the emergency situation applies to damaged locations at Km19+600 (T), Km22+137 (sewer), Km22+800 (T), Km23+600 (T), Km80+530 (P), Km112+350 (T), Km126+350 (T), Km177+643 (T) and Km180+100 (P) on the Truong Son Dong route.
These are locations that were previously announced by the Ministry of Construction as emergency situations for natural disasters according to Decision No. 2002/QD-BXD dated November 12, 2025 to implement remediation, ensure traffic safety and restore road infrastructure due to the impact of rain and floods.
The announcement of the termination of the emergency situation shows that the disaster recovery work at the above locations has been completed, meeting the requirements to put the project into management and exploitation according to regulations.