Metro No. 2 HCMC: 15 years still no start date

MINH QUÂN |

HCMC - After 15 years of approval, Metro Line 2 (Ben Thanh - Tham Luong) with a capital of nearly VND47,900 billion has not yet set a start date after transferring from ODA capital to the budget.

still stuck with a site clearance

According to the Ho Chi Minh City Urban Railway Management Board (MAUR), the site clearance work for Metro Line 2 project has reached 99.83%, with 584/585 cases handed over.

There is also a case of public land, which is the headquarters of District 3 Police, still stuck in legal procedures for handover between the Ministry of Public Security and Ho Chi Minh City Police. It is expected that the handover will be completed in the first quarter of 2025.

MAUR has proposed that the People's Committee of District 3 and the District Compensation and Site Clearance Board continue to support the acceleration of land acquisition, compensation and site handover procedures to ensure project progress.

Di doi ha tang ky thuat tuyen Metro so 2.  Anh: Anh Tu
Relocating the technical infrastructure of Metro Line 2 (HCMC). Photo: Anh Tu

The relocation of technical infrastructure at 12/12 station locations and open excavation sections has been implemented simultaneously, including electricity, telecommunications, water supply and drainage, lighting, trees and traffic items.

However, MAUR said that the progress outside the construction site is still slower than planned due to many factors: Construction in urban areas is cramped, causing many underground works outside the design; some households have works within the project area that have not been completely resolved; mobilizing human resources and equipment from contractors that have not met requirements despite commitments.

MAUR said that it will focus on speeding up the construction progress to complete the relocation of infrastructure in the third quarter of 2025.

Major packages are suspended due to changes in capital sources

Regarding bidding, MAUR has signed a contract with the project management support consultancy (PMSC) to implement the contractor selection for the project control and construction supervision consultancy package (CS2B package). The bidding documents have been issued and extended until August 30, 2024.

However, up to now, all major packages of the project have had to be temporarily suspended due to changes in capital sources. Previously, the project was funded by the Asian Development Bank (ADB), the German reconstruction Bank (KfW) and the European Investment Bank (EIB).

The arrangement of ODA loans for the project has changed compared to the original plan due to sponsors adjusting the conditions and funding process. After the working session with the Ho Chi Minh City People's Committee, sponsors (ADB, KfW, EIB) agreed not to continue sponsoring the CS2B package and the entire Metro No. 2 project.

At the end of 2024, Ho Chi Minh City agreed on the policy of using the city budget to implement the next tasks of Metro Line 2 project, instead of using ODA capital.

The Ho Chi Minh City People's Committee has reported to the Prime Minister about stopping the use of ODA capital and preferential loans for Metro Line 2 project.

MAUR said that it will cancel the CS2B package according to regulations after having an official decision on the financial plan.

Cong nhan di doi, dau noi he thong dien de lam tuyen Metro so 2 . Anh: Anh Tu
Workers relocate and connect the power system to build Metro Line 2. Photo: Anh Tu

Metro Line 2 was approved in 2010 with an initial total investment of VND26,000 billion. By 2019, the project capital was adjusted to increase to nearly VND47,900 billion.

The entire route is more than 11 km long, of which 9.2 km is underground, the rest is elevated and the road leading to Tham Luong depot (District 12). The project has 9 underground stations and 1 elevated station.

According to the previous plan, Metro Line 2 was expected to be operational in 2026. However, due to a series of problems, in October 2023, the Ho Chi Minh City People's Committee adjusted the completion time to 2030.

With the current situation, the exact start date of the main package has not been determined.

MINH QUÂN
TIN LIÊN QUAN

Metro Line 2 speeds up construction in the last days of the year

|

HCMC - At the end of the year, workers are busy relocating the underground power system, clearing the ground to serve the construction of metro line 2 in 2025.

After 14 years of waiting, Metro Line 2 in Ho Chi Minh City is facing a major turning point

|

HCMC - After 14 years of approval, Metro Line 2 (Ben Thanh - Tham Luong) is facing a major turning point when switching from using ODA capital to local budget sources.

Metro Line 2 in Ho Chi Minh City unexpectedly switches from ODA capital to budget

|

Metro Line 2 (Ben Thanh - Tham Luong) was approved by the Party Committee of the Ho Chi Minh City People's Committee to be implemented using budget capital, instead of using ODA loans.

The square of the coastal tourism area is deteriorating after 1 year of use

|

Ha Tinh - Ky Ninh Sea Tourism Area Square (Ky Anh town) with a total investment of 55 billion VND, just put into use for a year, has deteriorated.

Doan Hai My: I am beautiful because I am pampered by Doan Van Hau

|

In the program Saturday Afternoon Coffee, beauty Doan Hai My shared about her current married life with player Doan Van Hau.

Workers dredging sludge under To Lich River

|

On February 22, dozens of workers dredged the sludge under the To Lich River to prepare to receive additional water from the Red River.

Passenger bus caught fire fiercely on National Highway 1 through Binh Dinh

|

traveling on National Highway 1 through Tuy Phuoc District (Binh Dinh), a Ninh Binh-plate passenger car suddenly caught fire.

Warning about the habit of bacteria causing rain, humidity, and pollution

|

Doctors recommend that people should not wear fabric masks during days of air pollution accompanied by humid rain to avoid accumulating disease-causing bacteria.

Metro Line 2 speeds up construction in the last days of the year

Tú Tâm |

HCMC - At the end of the year, workers are busy relocating the underground power system, clearing the ground to serve the construction of metro line 2 in 2025.

After 14 years of waiting, Metro Line 2 in Ho Chi Minh City is facing a major turning point

MINH QUÂN |

HCMC - After 14 years of approval, Metro Line 2 (Ben Thanh - Tham Luong) is facing a major turning point when switching from using ODA capital to local budget sources.

Metro Line 2 in Ho Chi Minh City unexpectedly switches from ODA capital to budget

MINH QUÂN |

Metro Line 2 (Ben Thanh - Tham Luong) was approved by the Party Committee of the Ho Chi Minh City People's Committee to be implemented using budget capital, instead of using ODA loans.