Messy key road in the South of Lam Dong

Phúc Khánh |

Lam Dong - The DT. 721 road upgrade project is under construction slowly, the construction site is messy, seriously affecting people's travel, business and daily life.

Traffic unsafety risk

The project to upgrade DT. 721 section from Da Huoai commune to Da Teh commune has a total investment of about 650 billion VND, a length of more than 16.6km, a scale of 3 lanes, and a roadbed width of 14.5m.

Dự án DT 721 thi công dang dở, ngổn ngang khắp tuyến. Ảnh: Phúc Khánh
Project DT. 721 is under construction, messy all over the route. Photo: Phuc Khanh

The project started in August 2024, undertaken by a joint venture of Khanh Hoa Road Construction Management Joint Stock Company and Tan Khanh Hoa Co., Ltd.

When completed, the road is expected to become an important trade connecting axis of the southern region of Lam Dong province. Thereby, contributing to promoting socio-economic development and expanding regional linkage space.

However, after nearly 2 years of implementation, the construction site is still in a messy state. Many road sections are dug unfinished, piles of soil and rocks, machinery operates intermittently, and construction personnel are sparse.

Mr. Duong Van Oanh (resident of Da Huoai commune) said that his family is doing small business, but for many months now it has been blocked by construction right on the front, so business has been almost stalled.

Mặt đường dự án thi công dang dở, đào đắp ngổn ngang kéo dài gây ảnh hưởng nghiêm trọng đến việc đi lại, sinh hoạt của người dân xung quanh. Ảnh: Phúc Khánh
The road surface of the project is under construction, dug and patched messily for a long time, seriously affecting the travel and daily life of surrounding people. Photo: Phuc Khanh

“Previously, people were very excited because the road was upgraded. But the more construction, the more messy it became, it was difficult to travel, and life was disrupted. We just hope the project will be completed soon to stabilize our lives,” Mr. Oanh said.

According to records, although most of the site has been handed over, many sections of horizontal culverts and roadbeds are still under construction. Some locations have appeared mud, potholes, posing a potential risk of traffic unsafety.

Mr. Dinh Trong Dai (resident in Da Huoai commune) reflected that in the past time, many motorbike falls have occurred when people travel through the construction area.

The DT. 721 route project in the South of Lam Dong is under construction slowly and messy. Video: Phuc Khanh

People have repeatedly complained to the local authorities, but the remediation is still slow," Mr. Dai said.

After a period of difficulties in site clearance and lack of embankment land, local authorities and related units have focused on removing them. Up to now, about 15.6/6.6km of site has been handed over, reaching more than 90% of the volume.

However, the construction progress has not improved significantly. Along the route, many locations are almost stalled, greatly affecting people's travel and transportation of goods.

Slow construction, alarming disbursement

According to assessments by relevant agencies, in addition to the land area still stuck at 37 households, the major difficulty currently is the high increase in construction material prices and scarce supply.

The price of soil, sand, and rock continuously fluctuates, causing many contractors to fall into a state of slow construction...

Hầu hết cống thoát nước dọc tuyến đường đều thi công dang dở, tiềm ẩn nguy cơ xảy ra tại nạn giao thông. Ảnh: Phúc Khánh
Most drains along the route are under construction, posing a risk of traffic accidents. Photo: Phuc Khanh

Notably, this is not the first time contractors have been reminded for slow progress. Since 2025, many construction units have been continuously criticized, but the sluggish situation still persists.

It is worth mentioning that in 2026, Lam Dong province allocated more than 353 billion VND of public investment capital for the project. However, by mid-May, the project had only disbursed about 7.3 billion VND, equivalent to about 2% of the annual capital plan.

This figure clearly reflects the paradox of "having money but not being able to spend it". In the context of public investment being seen as a driving force for economic growth, the fact that large capital sources are waiting while construction projects are slow causes huge waste.

Dự án đang trong tình trạng thi công ì ạch, cầm chừng. Ảnh: Phúc Khánh
The project is in a state of slow construction, holding back. Photo: Phuc Khanh

Faced with the risk that DT. 721 route will continue to become a "bottleneck" pulling back the province's overall disbursement rate, the Construction Investment Project Management Board No. 1 of Lam Dong province has requested contractors to urgently rectify the apparatus and accelerate construction.

The goal is to complete the roadbed in May and deploy asphalt concrete paving in June 2026. If progress continues to be violated, the investor will fine and recover the volume to transfer to another capable unit.

Provincial leaders also requested strict handling of weak contractors, not allowing prolonged delays on key traffic projects.

Phúc Khánh
RELATED NEWS

Key road construction is slow, people suffer from muddy rain and dusty sun

|

Lao Cai - Started in 2023, the project to upgrade Provincial Road 160, a key road through Xuan Hoa commune, is still unfinished, disrupting people's lives.

Lam Dong promotes the progress of site clearance for Tan Phu - Bao Loc expressway

|

Lam Dong - Provincial leaders requested relevant units to accelerate compensation and site clearance, ensuring the progress of the Tan Phu - Bao Loc Expressway Project.

Ring Road 1 project behind schedule, construction site road in disarray

|

Hanoi - The project's slow progress has caused De La Thanh street to be flooded with dirt, rocks and construction materials, disrupting daily life and polluting the environment.

Musician with billion-view song Nguyen Van Chung: I am too used to being stolen of intellectual property

|

Musician Nguyen Van Chung once had a hit song that brought the network operator 1.7 billion VND, but he only received 30 million VND in "consolation" money.

Money flow from music copyright exploitation seen from BH Media, May Lang Thang cases

|

Protecting copyright and authors' rights is protecting property, making transparent the flow of money exploiting music in the digital space.

Warning for thunderstorm areas today, with very heavy rain in some places over 100mm

|

The meteorological agency continues to warn of rain in the Northeast, Northwest, North Central, provinces from Quang Tri to Lam Dong and the South.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Key road construction is slow, people suffer from muddy rain and dusty sun

Đinh Đại |

Lao Cai - Started in 2023, the project to upgrade Provincial Road 160, a key road through Xuan Hoa commune, is still unfinished, disrupting people's lives.

Lam Dong promotes the progress of site clearance for Tan Phu - Bao Loc expressway

Phúc Khánh |

Lam Dong - Provincial leaders requested relevant units to accelerate compensation and site clearance, ensuring the progress of the Tan Phu - Bao Loc Expressway Project.

Ring Road 1 project behind schedule, construction site road in disarray

Minh Hạnh |

Hanoi - The project's slow progress has caused De La Thanh street to be flooded with dirt, rocks and construction materials, disrupting daily life and polluting the environment.