Causes of flooding when building a bypass in Quang Tri

HƯNG THƠ |

Quang Tri - The investor has clarified the cause of flooding in residential areas during the construction of the eastern bypass of Dong Ha City and will proceed to fix it.

On November 15, the Department of Transport of Quang Tri province confirmed that it had set up a team to inspect flooding at the construction site of the Eastern bypass project of Dong Ha city in Truc Lam village (Gio Quang commune, Gio Linh district, Quang Tri province).

Inspection showed that the construction of the bypass had obstructed drainage. However, measuring the water level upstream and downstream showed only a 5cm difference, the drainage opening of the bypass was still too large and not fully flooded. Inspection downstream found that the section of the canal junction with the bypass (80m away) at the siphon location was heavily flooded, with stagnant water unable to drain quickly.

Based on the inspection results, the Department of Transport of Quang Tri province confirmed that there were two causes of flooding.

Xi phong hep o doan kenh phia ha luu khien nuoc bi u, khong thoat duoc. Anh: Hung Tho.
Narrow siphon in the downstream canal section causes water to stagnate and not drain. Photo: Hung Tho

To overcome this problem, the provincial Department of Transport will add more culverts and expand the culvert apertures on the bypass to improve drainage. In particular, the provincial People's Committee will be asked to expand the siphon in the canal section so that water does not stagnate. When the downstream drains all the water and the bypass has increased the culverts, the flooding will be resolved.

“We have worked with the local authorities to clarify the cause and find a solution. We will report to the Quang Tri Provincial People's Committee on measures to avoid flooding affecting people's lives and production,” said Mr. Tran Huu Hung, Director of the Provincial Department of Transport.

Previously, as Lao Dong Newspaper reported, after heavy rains caused by storm No. 6 in late October and early November, Bau Na field behind residential area of ​​Team 4 (Truc Lam village) was flooded. The road leading to the residential area was flooded more than 1 meter in some places, disrupting people's lives.

After the rain stopped, flooding still occurred because the water receded slowly. Believing that the construction of the bypass project had become a dam, causing flooding, the people wrote a collective petition, asking the authorities to find a solution.

HƯNG THƠ
RELATED NEWS

Construction of bypass road in Quang Tri causes flooding in residential areas

|

Quang Tri - The Eastern bypass project of Dong Ha city is being constructed through a field, causing the water to not drain in time, causing flooding.

Please extend the implementation of the bypass project in Quang Tri

|

QUANG TRI - The Eastern bypass project of Dong Ha city is at risk of falling behind schedule, so the locality has requested an extension of the implementation time and capital disbursement.

Quang Tri urges contractors to speed up progress of 400 billion VND bypass road

|

The nearly 400 billion VND bypass road in Quang Tri province is under construction. From now until the end of the year, the weather is forecast to be unfavorable, so disbursement will be difficult.

Mr. Putin assesses the price of the US purchase of Greenland

|

Mr. Putin said that the Greenland issue is not related to Moscow's interests, and gave an assessment of this deal.

Comrade Tran Cam Tu re-elected to the 14th Central Executive Committee

|

Comrade Tran Cam Tu - Member of the Politburo of the XIII term, Standing Secretary of the Secretariat of the XIII term - re-elected to the Party Central Committee of the XIV term.

National and international trade union organizations congratulate the 14th Party Congress

|

On the occasion of the 14th National Congress of the Communist Party of Vietnam, 16 international trade union organizations and national trade unions sent congratulatory messages to the Congress. The messages all expressed respect and appreciation for the leadership role of the Communist Party of Vietnam in bringing the country through many difficulties and challenges, achieving important achievements in the fields of economy, society and politics, improving life, bringing prosperity and happiness to the people and workers.

Electric motorbike battery exchange cabinets in Ho Chi Minh City must be used for many brands

|

Ho Chi Minh City - Electric motorbike battery exchange cabinets installed on sidewalks must have a flexible design, support common batteries for many types of vehicles or commit to applying an open connection protocol.

14th Party Congress: International friends admire Vietnam's comprehensive achievements

|

Letters and telegrams congratulating the 14th Party Congress believe that the strategic decisions at the Congress will bring Vietnam to prosperous and happy development.

Construction of bypass road in Quang Tri causes flooding in residential areas

HƯNG THƠ |

Quang Tri - The Eastern bypass project of Dong Ha city is being constructed through a field, causing the water to not drain in time, causing flooding.

Please extend the implementation of the bypass project in Quang Tri

HƯNG THƠ |

QUANG TRI - The Eastern bypass project of Dong Ha city is at risk of falling behind schedule, so the locality has requested an extension of the implementation time and capital disbursement.

Quang Tri urges contractors to speed up progress of 400 billion VND bypass road

HƯNG THƠ |

The nearly 400 billion VND bypass road in Quang Tri province is under construction. From now until the end of the year, the weather is forecast to be unfavorable, so disbursement will be difficult.