Causes of flooding when building a bypass in Quang Tri

HƯNG THƠ |

Quang Tri - The investor has clarified the cause of flooding in residential areas during the construction of the eastern bypass of Dong Ha City and will proceed to fix it.

On November 15, the Department of Transport of Quang Tri province confirmed that it had set up a team to inspect flooding at the construction site of the Eastern bypass project of Dong Ha city in Truc Lam village (Gio Quang commune, Gio Linh district, Quang Tri province).

Inspection showed that the construction of the bypass had obstructed drainage. However, measuring the water level upstream and downstream showed only a 5cm difference, the drainage opening of the bypass was still too large and not fully flooded. Inspection downstream found that the section of the canal junction with the bypass (80m away) at the siphon location was heavily flooded, with stagnant water unable to drain quickly.

Based on the inspection results, the Department of Transport of Quang Tri province confirmed that there were two causes of flooding.

Xi phong hep o doan kenh phia ha luu khien nuoc bi u, khong thoat duoc. Anh: Hung Tho.
Narrow siphon in the downstream canal section causes water to stagnate and not drain. Photo: Hung Tho

To overcome this problem, the provincial Department of Transport will add more culverts and expand the culvert apertures on the bypass to improve drainage. In particular, the provincial People's Committee will be asked to expand the siphon in the canal section so that water does not stagnate. When the downstream drains all the water and the bypass has increased the culverts, the flooding will be resolved.

“We have worked with the local authorities to clarify the cause and find a solution. We will report to the Quang Tri Provincial People's Committee on measures to avoid flooding affecting people's lives and production,” said Mr. Tran Huu Hung, Director of the Provincial Department of Transport.

Previously, as Lao Dong Newspaper reported, after heavy rains caused by storm No. 6 in late October and early November, Bau Na field behind residential area of ​​Team 4 (Truc Lam village) was flooded. The road leading to the residential area was flooded more than 1 meter in some places, disrupting people's lives.

After the rain stopped, flooding still occurred because the water receded slowly. Believing that the construction of the bypass project had become a dam, causing flooding, the people wrote a collective petition, asking the authorities to find a solution.

HƯNG THƠ
TIN LIÊN QUAN

Construction of bypass road in Quang Tri causes flooding in residential areas

|

Quang Tri - The Eastern bypass project of Dong Ha city is being constructed through a field, causing the water to not drain in time, causing flooding.

Please extend the implementation of the bypass project in Quang Tri

|

QUANG TRI - The Eastern bypass project of Dong Ha city is at risk of falling behind schedule, so the locality has requested an extension of the implementation time and capital disbursement.

Quang Tri urges contractors to speed up progress of 400 billion VND bypass road

|

The nearly 400 billion VND bypass road in Quang Tri province is under construction. From now until the end of the year, the weather is forecast to be unfavorable, so disbursement will be difficult.

Land tax debt, the largest private school in Quang Tri is at risk of closing

|

Not being given timely guidance to switch to land lease to complete procedures for land rent exemption, the largest private school in Quang Tri is at risk of being forced to close due to huge land rent debt.

On the construction site of the 6-lane road worth nearly 500 billion at the Northwest gateway

|

The project to renovate and upgrade National Highway 6 at the Northwest gateway with a total investment of nearly 500 billion VND and a scale of 6 lanes is being accelerated.

Russia attacks Ukraine with latest hypersonic missile

|

Russia attacked Ukraine with its latest Oreshnik hypersonic missile in response to Kiev's use of Western long-range missiles.

Gold price update morning of November 22: Many supporting factors, high increase

|

Gold price update on the morning of November 22 increased simultaneously in both domestic and world markets.

There will be 3 new routes in Quoc Oai, Hanoi

|

Hanoi - There will be 3 new routes located near the Central Maternity Hospital, Branch 2, Central Children's Hospital, Branch 2, Quoc Oai district.

Construction of bypass road in Quang Tri causes flooding in residential areas

HƯNG THƠ |

Quang Tri - The Eastern bypass project of Dong Ha city is being constructed through a field, causing the water to not drain in time, causing flooding.

Please extend the implementation of the bypass project in Quang Tri

HƯNG THƠ |

QUANG TRI - The Eastern bypass project of Dong Ha city is at risk of falling behind schedule, so the locality has requested an extension of the implementation time and capital disbursement.

Quang Tri urges contractors to speed up progress of 400 billion VND bypass road

HƯNG THƠ |

The nearly 400 billion VND bypass road in Quang Tri province is under construction. From now until the end of the year, the weather is forecast to be unfavorable, so disbursement will be difficult.