Criticizing investors for delaying key expressway projects in Lam Dong

Phúc Khánh |

Lam Dong - Provincial leaders criticize investors for slow progress of key expressway projects, requesting to accelerate construction and ensure completion of procedures.

On June 28, Lam Dong Provincial People's Committee said that the Bao Loc - Lien Khuong expressway project (phase 1) is more than 73.6km long, with a total investment of 17,718 billion VND, passing through 10 communes and wards with 2,464 affected cases, with a recovered area of more than 681ha.

In 2026, the project was allocated nearly 2,940 billion VND of public investment capital. However, so far only more than 331 billion VND has been disbursed, mainly for compensation, support and land valuation consulting.

Chủ tịch UBND tỉnh Lâm Đồng Hồ Văn Mười phê bình nhà đầu tư để dự án cao tốc Bảo Lộc - Liên Khương chậm tiến độ. Ảnh: Phúc Khánh
Chairman of Lam Dong Provincial People's Committee Ho Van Muoi criticized the investor for delaying the Bao Loc - Lien Khuong expressway project. Photo: Phuc Khanh

Up to now, the locality has handed over about 421ha of land, reaching about 68%.

However, the construction progress is still very slow due to the technical design documents and estimates of many sections of the route not being completed, not meeting the conditions for simultaneous construction.

Representative of the investor consortium, Mr. Nguyen Ngoc Nghi - Deputy General Director of T&T Group - admitted the slow progress of the project, took responsibility to the local authorities and committed to completing the credit contracts before July 15.

At the same time, the investor will complete the technical design dossier in July to focus on deploying construction.

However, Director of Lam Dong Department of Construction Le Ngoc Tien affirmed that the reason for the slow progress belongs to the investor.

Ông Nguyễn Ngọc Nghị, Phó Tổng Giám đốc Tập đoàn T&T, liên doanh nhà đầu tư Dự án Cao tốc Bảo Lộc - Liên Khương giải trình tại buổi làm việc. Ảnh: Phước Lê
Mr. Nguyen Ngoc Nghi, Deputy General Director of T&T Group, joint venture of investors of Bao Loc - Lien Khuong expressway project, explained at the working session. Photo: Phuoc Le

According to Mr. Tien, the investor once committed to completing the design dossier from the end of May but has not yet implemented it.

Vice Chairman of Lam Dong Provincial People's Committee Nguyen Hong Hai requested the investor to urgently complete the commitments, soon complete procedures and credit contracts; and at the same time mobilize sufficient manpower and equipment to deploy construction immediately on the sections that have been handed over the site.

At the working session on June 26, Mr. Ho Van Muoi, Member of the Party Central Committee, Chairman of Lam Dong Provincial People's Committee, severely criticized the investor for allowing the project to be delayed, affecting the province's public investment capital disbursement plan.

Dự án cao đốc Bảo Lộc - Liên Khương đang chậm tiến độ so với kế hoạch. Ảnh: Phúc Khánh
The Bao Loc - Lien Khuong expressway project is behind schedule compared to plan. Photo: Phuc Khanh

The Chairman of Lam Dong Provincial People's Committee requested that all dossiers, procedures, and capital mobilization work must be completed before July 15; and at the same time implement the motto "where there is land, there is construction".

Mr. Ho Van Muoi also requested departments and branches to arrange standing forces to monitor and urge progress; and said that the province will organize online meetings periodically every 2 weeks to review the project implementation progress.

Lam Dong does not accept the situation of irresponsible investors affecting the disbursement progress of public investment capital," Chairman of Lam Dong Provincial People's Committee Ho Van Muoi emphasized.

Phúc Khánh
RELATED NEWS

Bao Loc - Lien Khuong expressway is slow to construct due to incomplete design documents

|

Lam Dong - Although more than 67% of the site has been handed over, the Bao Loc - Lien Khuong expressway project cannot be implemented due to incomplete technical design documents.

Gia Lai criticizes investor for being absent without reason when meeting to remove project obstacles

|

Gia Lai requests criticism of investors who are absent without reason at the project difficulty removal meeting; warns of strict handling of cases of lack of cooperation.

Bao Loc - Lien Khuong expressway is behind schedule

|

Lam Dong - Leaders of Lam Dong Provincial People's Committee criticized the investor of the Bao Loc - Lien Khuong Expressway Project for delays in project preparation and implementation.

Breaking down a door to rescue a driver trapped after an accident in Quang Ninh

|

Quang Ninh - Amidst the messy scene of the accident, people and functional forces broke down the door and took the victim out for emergency treatment.

Clicking on TikTok ads, users fall into sophisticated scam traps

|

Users are upset when shopping through the TikTok platform but are redirected to a link designed to be "fake but real".

From July 1st, new law tightens livestream sales and linked marketing activities

|

From July 1, 2026, the 2025 Law on E-commerce adds many regulations for online sellers, livestream sales and linked marketing.

Forecast of the area with the heaviest rain from tonight, risk of extreme rain 100mm/3 hours

|

Warning from tonight, June 28, the focus of heavy rain is the mountainous and midland areas of the Northern region; risk of heavy rain intensity over 100mm within 3 hours.

Double earthquake in Venezuela kills 1,430 people

|

Two strong earthquakes with hundreds of aftershocks in Venezuela caused a terrible disaster, with thousands of casualties.

Bao Loc - Lien Khuong expressway is slow to construct due to incomplete design documents

Phúc Khánh |

Lam Dong - Although more than 67% of the site has been handed over, the Bao Loc - Lien Khuong expressway project cannot be implemented due to incomplete technical design documents.

Gia Lai criticizes investor for being absent without reason when meeting to remove project obstacles

Hoài Phương |

Gia Lai requests criticism of investors who are absent without reason at the project difficulty removal meeting; warns of strict handling of cases of lack of cooperation.

Bao Loc - Lien Khuong expressway is behind schedule

Phúc Khánh |

Lam Dong - Leaders of Lam Dong Provincial People's Committee criticized the investor of the Bao Loc - Lien Khuong Expressway Project for delays in project preparation and implementation.