After 3 years, the expressway worth more than 5,200 billion VND connecting Thang Long - Hoa Binh Avenue is still facing site clearance issues

Minh Nguyễn - Thanh Bình |

Hanoi - Investing more than 5,200 billion VND, the road project connecting Thang Long Avenue to Hoa Lac - Hoa Binh expressway still has "remaining" land that has not been cleared.

In the afternoon of April 7, Lao Dong's records at the construction site of the Thang Long Avenue expressway project (the section connecting National Highway 21 to the Hanoi - Hoa Binh expressway) showed that the construction atmosphere was quite quiet. At the construction site, there were only a few workers and machinery and equipment operating.

Chỉ có số ít công nhân, máy móc thi công, thậm chí máy xúc không có người vận hành. Ảnh: Minh Nguyễn
There are only a few workers, construction machinery, even excavators without operators. Photo: Minh Nguyen

The project has a length of 6.7 km and is identified as one of the key infrastructure projects in western Hanoi today. The road plays a role in completing the strategic traffic axis, connecting from the capital center to Hoa Binh (old) and the northwestern provinces.

Notably, this route also plays a linkage role with Hanoi National University - a university urban area with a scale of more than 11.13 km2, the largest in the country. The surrounding area also concentrates many important training institutions such as the Political Officer School, the University of Culture and Arts of the Army, and the Electricity University. When completed, the project is expected to shorten travel time from the Northwest provinces to Hoa Lac, while promoting regional linkages.

According to Hoa Lac Commune People's Committee, by April 1, site clearance work had achieved many positive results. The locality has handed over more than 564,000 m2 out of a total of 676 land plots, equivalent to 93.21% of the area to be recovered.

However, there are still some "remaining" areas that have not been cleared, affecting the construction progress. Currently, about 6.79% of the area (equivalent to more than 41,000 m2, including 7 land plots) has not been handed over, mainly due to problems with land origin and compensation procedures.

Meanwhile, the existing road next to the construction area is under great traffic pressure. The density of vehicles increases during peak hours and weekends, posing a potential risk of unsafety. Therefore, the early completion of the project and reorganizing traffic is considered very necessary to reduce the load on the area.

Mật độ phương tiện lưu thông tại khu vực bên cạnh tuyến đường đang thi công. Ảnh: Minh Nguyễn
Vehicle density in the area next to the road under construction. Photo: Minh Nguyen

According to the plan, the project aims to be completed in 2026. When put into operation, the road will not only contribute to completing the transportation network but also help reduce pressure on existing axes, while expanding Hanoi's development space to the West and Southwest.

Some images at the construction site, April 6th:

Sau 3 năm khởi công, dự án đường nối Đại lộ Thăng Long đến cao tốc Hòa Lạc - Hòa Bình đã có nhiều chuyển biến. Ảnh: Minh Nguyễn
After 3 years of construction, the road project connecting Thang Long Avenue to Hoa Lac - Hoa Binh expressway has had many changes. In areas with clean ground, lanes have gradually appeared. Photo: Minh Nguyen
Những mặt bằng đã hoàn tất quá trình làm sạch, . Ảnh: Minh Nguyễn
The land has been handed over, completing the site clearance and cleaning process. Photo: Minh Nguyen
6 làn xe cao tốc ở trung tâm, hai bên là hệ thống đường song hành cùng các hạ tầng kỹ thuật được đầu tư đồng bộ, dự án có mặt cắt ngang rộng từ 120 - 180 m. Đây cũng sẽ là tuyến đường có mặt cắt rộng nhất Việt Nam hiện nay, vượt xa so với đại lộ Thăng Long với mặt cắt trung bình khoảng 140 m. Ảnh: Minh Nguyễn
6 highway lanes in the center, on both sides is a parallel road system and synchronously invested technical infrastructure, the project has a cross-section width of 120 - 180 m. This will also be the road with the widest cross-section in Vietnam today, far exceeding Thang Long Avenue with an average cross-section of about 140 m. Photo: Minh Nguyen
Dự án sẽ là nhịp cầu kết nối với Đại học Quốc gia Hà Nội. Bên cạnh đó là các cơ sở đào tạo trọng điểm như Trường Sĩ quan Chính trị, Đại học Văn hóa Nghệ thuật Quân đội và Đại học Điện lực. Khi hoàn thành, tuyến đường sẽ tăng cường kết nối từ các tỉnh Tây Bắc về Hòa Lạc, rút ngắn thời gian di chuyển và thúc đẩy liên kết vùng. Ảnh: Minh Nguyễn
The project will be a bridge connecting to Hanoi National University. Besides, there are key training institutions such as the Political Officer School, the University of Culture and Arts of the Army and the Electricity University. When completed, the route will strengthen connectivity from the Northwest provinces to Hoa Lac, shorten travel time and promote regional linkages. Photo: Minh Nguyen
Những trụ bê tông dần vươn cao giữa công trường, đánh dấu tiến độ thi công tuyến đường đang được đẩy nhanh. Ảnh: Minh Nguyễn
Concrete pillars gradually reach high in the middle of the construction site, marking the progress of road construction being accelerated. Photo: Minh Nguyen
Một số phần mặt bằng chưa được bàn giao, gây ảnh hưởng tới tiến độ thi công dự án. Ảnh: Minh Chuyên
Some parts of the site have not been handed over, affecting the project construction progress. Photo: Minh Nguyen
Ban chỉ huy công trình . Ảnh: Minh Nguyễn
Project Steering Committee. Photo: Minh Nguyen

The road project connecting Thang Long Avenue to Hoa Lac - Hoa Binh expressway was started in October 2023, with the starting point at the Thang Long Avenue - National Highway 21 intersection and the ending point directly connecting to the Hanoi - Hoa Binh expressway. When completed, the route will replace the existing narrow road, contributing to reducing traffic pressure, shortening travel time and improving connectivity capacity throughout the western Hanoi area.

Minh Nguyễn - Thanh Bình
RELATED NEWS

Trailer truck collision on Cau Gie - Ninh Binh expressway, 1 person died

|

Ninh Binh - A serious traffic accident occurred on the Cau Gie - Ninh Binh expressway, killing 1 motorcyclist on the spot.

Busy before the rainy season at the Noi Bai - Lao Cai expressway expansion site

|

Lao Cai - Thousands of engineers and workers are busy constructing the Noi Bai - Lao Cai expressway expansion project.

Non-stop construction on the Noi Bai - Lao Cai expressway construction site

|

In the context of difficult construction, thousands of engineers and workers on the Noi Bai - Lao Cai expressway expansion project still maintain the construction pace to ensure progress.

First heat of the season, outdoor workers proactively adapt to make a living

|

Hanoi - The hot sun at the beginning of April has forced many outdoor workers to proactively adjust their working habits and apply sun protection measures to make a living.

Domestic silver prices surge, stores are bustling with traders

|

Although silver prices increased compared to before, on April 8, many silver shops in Hanoi still recorded a large number of customers coming to transact.

Abolishing some articles in Circular 29 on tutoring and extra classes from May 15, 2026

|

The Ministry of Education and Training has just issued new regulations amending and supplementing Circular 29/2024/TT-BGDĐT on tutoring and extra classes.

Temporarily suspending the principal in the case of infected pork leaking into kindergarten

|

Thai Nguyen - The test results of pork samples at Hoa Binh Kindergarten tested positive for African cholera, E. coli, causing many parents to be upset.

10th grade enrollment in Ho Chi Minh City, no required level 2 identification

|

The 10th grade entrance exam in Ho Chi Minh City promotes online registration, not requiring students to have level 2 identification accounts.

Trailer truck collision on Cau Gie - Ninh Binh expressway, 1 person died

Minh Nguyễn |

Ninh Binh - A serious traffic accident occurred on the Cau Gie - Ninh Binh expressway, killing 1 motorcyclist on the spot.

Busy before the rainy season at the Noi Bai - Lao Cai expressway expansion site

Tân Văn |

Lao Cai - Thousands of engineers and workers are busy constructing the Noi Bai - Lao Cai expressway expansion project.

Non-stop construction on the Noi Bai - Lao Cai expressway construction site

Nhóm PV |

In the context of difficult construction, thousands of engineers and workers on the Noi Bai - Lao Cai expressway expansion project still maintain the construction pace to ensure progress.