Completion time of the trillion-dollar bridge connecting Bac Ninh - Hai Duong

Trần Tuấn |

The Golden Canal Bridge connecting Bac Ninh - Hai Duong is expected to be completed on the occasion of the 30th anniversary of the re-establishment of Bac Ninh province (1997 - 2027).

On the morning of September 24, information from the People's Committee of Bac Ninh province said that Mr. Vuong Quoc Tuan - Chairman of the People's Committee of Bac Ninh province - had just directly visited the construction site, encouraged, presented gifts and assigned tasks to the investor and contractor of the Kenh Vang bridge project in Trung Kenh commune, Luong Tai district.

The investment project to build the Golden Canal Bridge and the approach roads at both ends of the bridge, connecting the two provinces of Bac Ninh and Hai Duong, has a route length of about 13.4km, invested by the Traffic Construction Project Management Board (Bac Ninh Department of Transport).

With a total cost of over VND2,182 billion, the construction project includes the 740m long, 23.5m wide Kenh Vang bridge, designed with a permanent scale, prestressed reinforced concrete structure; the approach roads at both ends of the bridge are 12.6km long, with a 15m wide road surface.

Construction location in Gia Binh district, Luong Tai (Bac Ninh province) and Nam Sach district (Hai Duong province).

Visiting the construction site directly, Chairman of Bac Ninh Provincial People's Committee Vuong Quoc Tuan acknowledged and commended the efforts and initiative of the investor and contractor.

Mr. Vuong Quoc Tuan said that Prime Minister Pham Minh Chinh highly praised Bac Ninh province for organizing the Conference to announce the Planning and Investment Promotion combined with the groundbreaking of the Golden Canal Bridge project - this is not only a meaningful project for the two provinces of Bac Ninh and Hai Duong but also has the meaning of inter-regional connectivity, something that the Government is very interested in.

The Chairman of the Provincial People's Committee affirmed that Kenh Vang Bridge is a project with many meaningful points when it started construction on the occasion of the 25th anniversary of the re-establishment of Luong Tai district (September 1999 - September 2024), was completed on the occasion of the 21st Provincial Party Congress, term 2025 - 2030 and was completed on the occasion of the 30th anniversary of the re-establishment of Bac Ninh province (1997 - 2027).

Thu tuong va cac dai bieu bam nut khoi cong du an cau Kenh Vang, chieu 22.9. Anh: Den Phu
The Prime Minister and delegates pressed the button to start the construction of the Golden Canal Bridge project on the afternoon of September 22. Photo: Tran Tuan

Previously, on September 22, Bac Ninh province held a conference to announce the Planning and Investment Promotion combined with the groundbreaking ceremony of the Golden Canal Bridge project, with the participation of Prime Minister Pham Minh Chinh.

The groundbreaking ceremony was changed from in-person to online, which was highly appreciated by the Prime Minister. The entire estimated budget for the groundbreaking ceremony arranged by the investor and enterprise to start construction directly at the project site was used to support the people affected by storm No. 3.

Trần Tuấn
RELATED NEWS

Fearing high gasoline prices, many people queue for 30 minutes to fill up their tanks

|

Before the information that gasoline and oil prices may increase due to the impact of the Middle East conflict, many Hanoi residents took the opportunity to queue to fill up their tanks.

Ho Chi Minh City expects the 10th grade entrance exam schedule on the 1st and 2nd of June

|

The Ho Chi Minh City Department of Education and Training submitted to the Ho Chi Minh City People's Committee a plan to organize the 10th grade exam in 2026 on June 1st and 2nd.

Forecast for tomorrow's gasoline and oil prices to increase sharply, increasing to a maximum of 3,220 VND/liter

|

It is predicted that gasoline and oil prices may increase sharply from 1,207 - 3,220 VND/liter in this week's price adjustment session.

The State Bank continues to request credit institutions to publicly disclose lending interest rates

|

Deputy Governor Pham Thanh Ha said that the State Bank will continue to require credit institutions to publicize lending interest rates.

Iranian ship attacked by submarine, at least 101 people missing

|

At least 101 people are missing after a submarine attacked an Iranian ship, the Sri Lankan navy reported.

Live football match between Vietnam women's team and India at the 2026 Women's Asian Cup

|

Live match between Vietnam women's team and India at the 2026 Women's Asian Cup, taking place at 6:00 PM today (March 4).

Real estate identification codes will lose the speculative environment

|

From March 2026, each real estate will be issued a separate electronic identification code, attached to a unified database.

Da Nang voters trust in the qualifications and bravery of National Assembly Deputy candidates

|

Da Nang - Voters highly appreciate the qualifications and capacity of National Assembly candidates and expect elected delegates to pursue issues of concern to the people to the end.

32 words from the Prime Minister to the Party Committee, government and people of Bac Ninh

Trần Tuấn |

On the afternoon of September 22, Prime Minister Pham Minh Chinh attended the Conference to announce the Planning and Investment Promotion of Bac Ninh province in 2024.

Beltway 4 through Bac Ninh must be completed by the end of 2025

Trần Tuấn |

Inspecting the progress at the construction site, Prime Minister Pham Minh Chinh requested that the section of Ring Road 4 passing through Bac Ninh be completed by the end of 2025.

Giới thiệu địa điểm di dời làng nghề ô nhiễm nhất Bắc Ninh

Vân Trường |

Ngày 21.9, UBND TP Bắc Ninh tổ chức giới thiệu Cụm Công nghiệp Quảng Chu đến với hàng trăm hộ sản xuất giấy làng nghề Phong Khê.