7,352 billion VND tourism project in the coldest place in Vietnam adjusts progress

Khánh Linh |

Lang Son - The Mau Son eco-tourism and cable car complex project has its investment policy adjusted for the third time, with a total capital of more than 7,352 billion VND.

According to the decision approving the adjustment of investment policy and also approving the investor of Lang Son Provincial People's Committee, the Mau Son eco-tourism and cable car complex project is implemented by Mau Son Sun Co., Ltd.

The scale of land use and construction investment is divided into two phases.

Phase I has an area of 121.8 ha in Loc Binh and Mau Son communes, including departure and arrival stations, cable car routes, resort hotels, event centers, commercial service areas, indoor and outdoor entertainment, food, shopping, culture, spiritual areas, squares, parking lots, internal traffic and ecological landscape forest land.

Phase II has an area of about 570.46 ha in Mau Son commune. The expected items include commercial service, entertainment, culinary, shopping, accommodation, resort hotels, sports, culture, spiritual, semi-wild animal rescue area, medical and rescue center, parking lot, internal traffic and other items according to the plan.

The total investment capital after adjustment is 7,352 billion VND. Of which, phase I is allocated 4,898 billion VND, phase II is 2,454 billion VND.

Hiện nay, công tác giải phóng mặt bằng đang có nhiều chuyển biến. Ảnh: Khánh Linh
Currently, site clearance work is undergoing many changes. Photo: Khanh Linh

Regarding progress, phase I is implemented from the second quarter of 2026 to the second quarter of 2031. In 2026, the project must complete site clearance.

From the second quarter of 2026 to the end of the second quarter of 2028, the investor will complete legal procedures, construct the departure station, arrival station, cable car route and some items according to the approved detailed plan.

The remaining items of phase I such as resort hotels, event centers, commercial service areas, entertainment areas, food - shopping areas, squares, parking lots and internal traffic are expected to be completed by the second quarter of 2031.

Phase II is implemented from the second quarter of 2026 to the fourth quarter of 2032, including site clearance, preparation for construction investment, deployment of items according to planning and put into operation.

The Provincial People's Committee assigns the Department of Finance to state management of investment for the project, and at the same time requests investors to deposit or provide bank guarantees to ensure implementation obligations. The Department of Agriculture and Environment and the Department of Construction coordinate to guide investors to complete procedures on land, forestry, environment, minerals, construction, planning and transport infrastructure.

The People's Committees of Mau Son and Loc Binh communes are responsible for carrying out site clearance and resettlement work, coordinating to develop compensation and support plans when the State recovers land; and at the same time strengthen land management in the project area and surrounding areas.

Investors are required to contribute sufficient equity, mobilize capital on schedule, complete investment procedures, construction, planning, environment, and land before deployment.

Mau Son is a famous tourist area of Lang Son, located at an altitude of over 1,000 m above sea level, with a cool climate, mountain scenery and unique indigenous culture.

The adjustment of the cable car project is expected to create more motivation for tourism and service development in the northeastern area of the province.

Khánh Linh
RELATED NEWS

Tourism project worth over 7,000 billion VND in the coldest place in Vietnam has new changes

|

Lang Son - Site clearance work for the Mau Son eco-tourism and cable car complex project recorded new changes.

Lang Son establishes working group to remove obstacles for Mau Son cable car project 7. 352 billion VND

|

Lang Son - The Provincial People's Committee established an inter-sectoral working group to remove obstacles and promote the progress of the Mau Son eco-tourism and cable car complex project.

7,000 billion VND cable car project in Mau Son may be operational by the end of 2027

|

Lang Son - The Provincial National Assembly Delegation proposed that Sun Group soon construct phase 1 of the Mau Son eco-tourism and cable car complex project, and put it into operation at the end of 2027.

Tropical depression may strengthen into a major storm, direction is still uncertain

|

The tropical depression operating in the southwest of the Mariana Islands is forecast to strengthen into a major storm by the end of this week.

Ho Chi Minh City 10th grade exam scores available, instructions on how to look up

|

Candidates in Ho Chi Minh City can start looking up 10th grade entrance exam scores for the 2026-2027 school year.

Journalist soldier of the Southwest region: Leaving the war with many wounds

|

Many wounded journalists in the Southwest region entered peacetime with silent wounds.

Tourism project worth over 7,000 billion VND in the coldest place in Vietnam has new changes

Khánh Linh |

Lang Son - Site clearance work for the Mau Son eco-tourism and cable car complex project recorded new changes.

Lang Son establishes working group to remove obstacles for Mau Son cable car project 7. 352 billion VND

Khánh Linh |

Lang Son - The Provincial People's Committee established an inter-sectoral working group to remove obstacles and promote the progress of the Mau Son eco-tourism and cable car complex project.

7,000 billion VND cable car project in Mau Son may be operational by the end of 2027

Khánh Linh |

Lang Son - The Provincial National Assembly Delegation proposed that Sun Group soon construct phase 1 of the Mau Son eco-tourism and cable car complex project, and put it into operation at the end of 2027.