Gia Lai identifies factors causing slow disbursement of public investment capital

THANH TUẤN |

Gia Lai - Despite many obstacles, the province is still in the group of localities with the highest disbursement rate of public investment capital in the country.

On July 8, Gia Lai Provincial People's Committee said that in the first 6 months of the year, the disbursement rate reached 32.74% of the capital plan assigned by the Prime Minister, ranking in the group of localities with high disbursement rates and leading in the South Central Coast and Central Highlands regions.

However, the province also acknowledges that there are still many obstacles and limitations that slow down the disbursement progress of public investment capital, and it is necessary to soon overcome them to complete the target of disbursing 100% of the capital plan by the end of 2026.

The main difficulties include the progress of land use fee collection not reaching the plan, affecting the ability to balance capital sources to pay for completed volumes and disburse projects using this source of revenue.

In addition, some projects face difficulties in the construction process due to insufficient supply of construction materials, increased transportation costs, and strong fluctuations in raw material and fuel prices.

Some other projects face obstacles in terms of site clearance, terrain and existing technical infrastructure that are still complex.

According to Gia Lai Provincial People's Committee, some projects have design dossiers that are not suitable for actual conditions, so in the process of implementation, they must be adjusted and supplemented to ensure investment efficiency.

Compensation and site clearance work at some projects is still slow. Determining the origin of land, determining land prices, and developing compensation, support, and resettlement plans still takes a lot of time.

In some cases, people do not agree with the compensation plan, affecting the progress of site handover and construction organization.

The provincial government requests departments, branches, and localities to focus on removing difficulties in compensation and site clearance; accelerate the completion of investment procedures, contractor selection and construction organization.

In particular, the province focuses on promoting the progress of key projects such as Nguyen Van Linh road, Quy Nhon - Pleiku expressway, Ia Prát reservoir (Ia Khuol commune), the Inter-level School project in 7 border communes, Cat Tien - Diem Van coastal road project and Nguyen Van Linh residential area...

THANH TUẤN
RELATED NEWS

Lam Dong breaks through in disbursing public capital investment thanks to management innovation

|

Lam Dong - After more than a month of removing bottlenecks, promoting digital transformation and tightening responsibility, the disbursement rate of public investment capital has made a strong breakthrough.

Vinh Long disburses 2 billion VND to support 40 farming households to develop production

|

Vinh Long - The Farmers' Support Fund disbursed 2 billion VND for 40 households to borrow, along with many outstanding activities of socio-political organizations.

Gia Lai requests acceleration of disbursement of public investment capital

|

Gia Lai - The provincial government requests to accelerate the disbursement of public investment capital for infrastructure, technical, and key projects.

9th Hour No. 205: Life's turning point - Part 1

|

Hour 9 - Losing her job after divorce, the single mother fell into a deadlock. Will the "lifebuoy" from the Trade Union official help her rebuild her life?

Vietnam national team wins Yongin FC, coach Kim Sang-sik continues to test the squad

|

The Vietnamese team won Yongin FC 2-1 in the second practice match in Korea to prepare for the ASEAN Cup 2026.

Ho Chi Minh City transfers and appoints 11 leading officials

|

Ho Chi Minh City transfers and appoints 11 leading officials in many departments, agencies, branches and state-owned enterprises to consolidate the apparatus after arrangement.

Forecast of heavy rain in the area from this evening, in some places exceeding 300mm

|

The meteorological agency forecasts that from the evening of July 8 to July 10, the mountainous and midland areas of the Northern region and Quang Ninh are likely to experience widespread heavy rain.

Decentralization and delegation of power to create conditions, not to push work and risks down to the grassroots level

|

The Prime Minister emphasized the policy and law of decentralization, delegation of power, allocation of resources, and more conditions, not pushing work and risks to the grassroots level.

Lam Dong breaks through in disbursing public capital investment thanks to management innovation

Phan Tuấn |

Lam Dong - After more than a month of removing bottlenecks, promoting digital transformation and tightening responsibility, the disbursement rate of public investment capital has made a strong breakthrough.

Vinh Long disburses 2 billion VND to support 40 farming households to develop production

HOÀNG LỘC |

Vinh Long - The Farmers' Support Fund disbursed 2 billion VND for 40 households to borrow, along with many outstanding activities of socio-political organizations.

Gia Lai requests acceleration of disbursement of public investment capital

THANH TUẤN |

Gia Lai - The provincial government requests to accelerate the disbursement of public investment capital for infrastructure, technical, and key projects.