Removing obstacles for an industrial cluster project worth over 500 billion VND in Phu Tho

Tô Công |

Phu Tho - The Phu Ho industrial cluster project (Phong Chau ward) is being removed from obstacles to start construction in August 2026 according to the direction of the Chairman of the Provincial People's Committee.

Investor reflects to Chairman of Provincial People's Committee

The Phu Ho Industrial Cluster Infrastructure Construction and Business Investment Project has a total estimated investment of 532 billion VND; an area of 75ha in Phong Chau ward; the investor is Nam Hoang Viet Joint Stock Company.

Recently, Phu Tho Provincial People's Committee organized the third "Business Coffee" program. Nam Hoang Viet Joint Stock Company has reflected on the obstacles and difficulties in the project implementation process.

According to the above enterprise, so far the compensation and site clearance (GPMB) work of the project has only reached 30.6/75ha (about 40%); the area of land allocation and land lease in phase 1 has reached about 10.4ha.

The reasons for the delay are that land management records over many periods are incorrect; many land plots are difficult to verify their origin, have not been granted or have been granted inappropriate land use right certificates.

In addition, a part of the population does not agree with the compensation plan and the construction progress of the resettlement area is still slow.

The business proposed that the Provincial People's Committee direct the removal of obstacles, accelerate the progress of the resettlement area and carry out procedures for land allocation in the 2nd phase (for the 30.6ha area that has been compensated) so that construction can be deployed.

Tuyến đường nối cụm công nghiệp Phú Hộ với Quốc lộ 2 đang thi công. Ảnh: Tô Công
The road connecting Phu Ho industrial cluster with National Highway 2 is under construction. Photo: To Cong.

After listening to the opinions of businesses, Chairman of Phu Tho Provincial People's Committee Tran Duy Dong requested Phong Chau Ward People's Committee to closely coordinate with the investor to focus on accelerating compensation and site clearance.

Strive to complete the handover of land phase 2 in July 2026. At the same time, urgently deploy the construction of the resettlement area, ensuring complete completion in December 2026.

The Chairman of the Provincial People's Committee noted that the province has prioritized allocating resettlement capital from the beginning of 2026, so the locality must act decisively and not delay.

On the business side, it is necessary to prepare resources to start the project right in August 2026 on the handed over area.

Investor delays payment to households

After grasping the direction of the Chairman of the Provincial People's Committee, Phong Chau Ward People's Committee organized a conference on the implementation of the Phu Ho industrial cluster construction project and related infrastructure projects.

Bản đồ quy hoạch tổng thể mặt bằng sử dụng đất của cụm công nghiệp Phú Hộ. Ảnh: Quy hoạch
Master plan map of land use of Phu Ho industrial cluster. Photo: Planning.

According to the meeting conclusion notice, the area that has been approved for compensation and site clearance plans is 30.7/75ha (the area that has received compensation and handed over land is 24.1ha).

Project implementation still has some shortcomings and limitations such as: The progress of site clearance has basically not ensured the roadmap and plan set out; the coordination between departments, agencies, units and investors is not really effective.

In which, mainly stemming from the investor's delay in allocating funds to pay compensation and site clearance for households that have been approved.

Therefore, Phong Chau Ward People's Committee requests the investor to ensure the implementation of compensation funds and late payment funds to households before June 25, 2026.

At the same time, commit to ensuring continuous capital sources when implementing the project, not allowing interruptions or shortages of capital during the implementation process. This is an important basis for the Ward People's Committee to report the results and progress of project implementation to the Provincial People's Committee and relevant departments and agencies.

Nhà đầu tư chậm trễ chi trả tiền bồi thường cho các hộ dân. Ảnh: Tô Công
Investors are slow to pay compensation to households. Photo: To Cong.

Phong Chau Ward People's Committee also requested the Phu Tho area branch of the land fund development center to coordinate with the investor to implement the payment of compensation and support money to ensure compliance with regulations.

At the same time, preside over and coordinate with departments and divisions of the Ward People's Committee to organize inventory, count, prepare and submit for approval compensation, support, and resettlement plans for the unimplemented area.

Focus on removing cases of slow inventory, not receiving compensation money, and not handing over land. Accelerate compensation, support, and site clearance work, and regularly report progress to the Ward People's Committee.

The Ward People's Committee also assigned the Economic - Infrastructure and Urban Department to proactively coordinate with the Phu Tho Regional Land Fund Development Center branch and the investor in compensation, support, and resettlement work.

Review and complete the dossier requesting the Provincial People's Committee to carry out procedures to hand over land to the investor for the clean site before July 31, 2026, to start the project in August 2026.

Tô Công
RELATED NEWS

Phu Tho enters Ho Chi Minh City to call for investment, opening up many opportunities for businesses

|

Phu Tho - In the afternoon of May 29, in Ho Chi Minh City, the Provincial People's Committee organized the 2026 Investment Promotion Conference with the theme "Joining hands to create - Together to develop".

Investing nearly 40 billion VND to build a school complex in Phu Tho

|

Phu Tho - Thinh Minh commune invests nearly 40 billion VND to build a school complex including Yen Quang primary and secondary schools.

Lao Cai starts construction of 860 billion VND industrial cluster

|

Lao Cai - Thong Nhat 1 Industrial Cluster in Gia Phu commune is oriented to develop according to the green industrial model, creating more jobs for workers.

Live football match Hoang Anh Gia Lai vs Hanoi FC in V.League

|

Live match between Hoang Anh Gia Lai and Hanoi FC in round 25 of V.League 2025-2026, taking place at 6:00 PM today (May 31).

Buddha's Birthday, Buddhists line up to perform the Buddha bathing ritual at Quan Su Pagoda

|

A large number of monks, nuns, Buddhists and people came to Quan Su Pagoda (Hanoi) to attend the Buddha's Birthday ceremony in the 2570s Buddhist calendar.

Hanoi youth brave the sun to clean up polluted canals

|

Hanoi - Despite the hot weather, many young people are still actively participating in cleaning, collecting waste and clearing the flow at polluted canals in Hanoi.

Math exam questions and answers for the 10th grade entrance exam in Hanoi in 2026

|

Official exam questions, reference answers for the Math subject for the 10th grade entrance exam in Hanoi in 2026 are updated most quickly by Lao Dong.

Phu Tho enters Ho Chi Minh City to call for investment, opening up many opportunities for businesses

Tô Công |

Phu Tho - In the afternoon of May 29, in Ho Chi Minh City, the Provincial People's Committee organized the 2026 Investment Promotion Conference with the theme "Joining hands to create - Together to develop".

Investing nearly 40 billion VND to build a school complex in Phu Tho

Tô Công |

Phu Tho - Thinh Minh commune invests nearly 40 billion VND to build a school complex including Yen Quang primary and secondary schools.

Lao Cai starts construction of 860 billion VND industrial cluster

Đinh Đại |

Lao Cai - Thong Nhat 1 Industrial Cluster in Gia Phu commune is oriented to develop according to the green industrial model, creating more jobs for workers.