Thinh Minh commune was established on the basis of merging the entire natural area and population of the communes: Hop Thanh, Quang Tien and Thinh Minh of the former Hoa Binh province.
Currently, Thinh Minh commune has an area of 89.21km2, a population of more than 19 thousand people and is aiming to become a ward by 2030.
The Yen Quang school cluster construction project, Thinh Minh commune (phase 01) was approved from April 28, 2026, according to Decision No. 524/QD-UBND of the People's Committee of Thinh Minh commune.
This project has a total investment of nearly 40 billion VND invested by the Project Management Board of Thinh Minh commune.
According to the reporter's investigation, on May 27, the project investor issued a bidding invitation notice for the "Construction of works" package.
The above bidding package was widely bid online, with a value of more than 28.4 billion VND from the site clearance capital of the project: Investment in construction and business of Yen Quang Industrial Park infrastructure and other legal capital sources.
In the near future, after completing the contractor selection work, the construction unit will build the project with the main items including:
Ground leveling item: Total area 5,161.6m2; ground leveling volume 12,906.41m3, excavation volume 2,532.85 m3.
Grade building item: 2 floors, construction area 744.84m2, total floor area 1489.68m2 including 10 classrooms, each room is arranged with a separate adjacent functional area: Nursing and childcare area, group classroom warehouse, teacher room, toilet area, playyard; 17-compartment house.
Headquarters building item: 2 floors, construction area 232.2m2, total floor area 464.4m2; 7-compartment building; arranging functional rooms for administrative and management blocks.
Subject classroom building item: 2 floors, construction area 232.2m2, total floor area 464.4m2; 7-compartment building; arranging functional rooms: Physical education room, art education room, multi-purpose room, information technology room.
Along with that are items: 1-story semi-boarding kitchen, construction area of 265.1m2; security house with an area of 17.6m2; auxiliary items (internal yard, embankment); fire prevention and fighting...
The completion time of the bidding package is 450 days.