Accelerate completion of apatite plant worth over 800 billion VND in Lao Cai

Đinh Đại |

Lao Cai - Lang Phung apatite ore processing plant is being accelerated in construction, aiming for commercial operation in the third quarter of 2026.

In mid-April, the construction site of Lang Phung Grade III Apatite Ore Preparation Plant (Van Ban commune, Lao Cai province) maintained a state of urgent construction.

Hundreds of workers and machinery systems operate continuously, and items are deployed synchronously to shorten progress and bring the project to completion on schedule.

The project is invested by Tam Dinh Apatite Investment Joint Stock Company, with a total investment of more than 800 billion VND, a designed capacity of 250,000 tons of concentrated ore per year, and an expected operating time of 16 years.

Dự án hiện đang được tập trung triển khai. Ảnh: Viết Vinh
The project is currently being accelerated. Photo: Viet Vinh

This is one of the large-scale deep mineral processing projects of Lao Cai province, aiming to improve resource value and gradually reduce crude exports.

Through research, the project once experienced a period of stagnation due to the impact of the COVID-19 epidemic, material price fluctuations and difficulties in the equipment supply chain. However, from 2024, the project has been restarted and quickly regained construction momentum.

Stepping into 2025, the investor and contractors simultaneously accelerated, mobilizing maximum resources to compensate for progress. To date, the total volume of construction and equipment installation has reached about 95%, and many important items have been completed.

Công nhân thi công các hạng mục tại công trường dự án. Ảnh: Viết Vinh
Workers constructing items at the project site. Photo: Viet Vinh

According to Mr. Nguyen Manh Hai - Head of the Project Management Board of Lang Phung Apatite Ore Preparation Plant, the main items have been basically completed.

The crushing house, floating screening house, concentrating system, tail ore filter tank... have been completed. Currently, we are focusing on checking and technical adjustment to prepare for the trial run phase of the entire production line," Mr. Hai said.

Also according to Mr. Hai, it is expected that in June 2026, the project will conduct single-dynamic trial runs, followed by unloaded and loaded runs if it fully meets technical, safety and legal conditions.

The goal is to put the factory into commercial operation in the third quarter of 2026," Mr. Hai said.

Dự án sẽ sớm vận hành vào quý III/2026. Ảnh: Viết Vinh
The project will soon be put into operation in Q3/2026. Photo: Viet Vinh

During the implementation process, the project is under pressure from fluctuations in raw material prices, especially gasoline and oil, causing costs to incur about 20 billion VND. However, the investor has proactively balanced finances and supported the contractor to maintain progress.

In parallel with the construction progress, quality control and labor safety are tightened. After completion, all items are thoroughly inspected and accepted to ensure stable operation of the production line and limit risks.

Currently, there are about 150 workers and many large-scale construction equipment operating continuously at the construction site. The progress of installation of basic equipment closely follows the overall plan.

Mr. Tan Hung Vu - Director of construction site and equipment installation - said that the current progress is being well controlled.

Items such as floating mills, grinders, and concentrated tanks have been completed and installed. If major problems do not arise, we plan to test run them unloaded by the end of June 2026," Mr. Vu informed.

Khi đi vào hoạt động, dự án sẽ tạo thêm nhiều việc làm cho lao động địa phương. Ảnh: Viết Vinh
When put into operation, the project will create more jobs for local workers. Photo: Viet Vinh

To serve the adjustment and operation work, the project also plans to add more than 30 experts, bringing the total number to more than 60 people.

It is known that when put into operation, the factory is expected to reach a capacity of 250,000 tons of apatite concentrate per year, contributing more than 200 billion VND to the state budget.

The project also creates stable jobs for about 120 - 150 local workers, of which about 50% are ethnic minorities.

Businesses have now implemented on-site vocational training to improve the quality of human resources and meet production requirements.

Đinh Đại
RELATED NEWS

Lao Cai sets a target of 75% of workers receiving vocational training by 2030

|

Lao Cai - Not only increasing the rate of trained workers, the province also sets a target for the majority of learners to have jobs, tightening training with market demand.

Current status of the 860 billion VND industrial cluster site about to be formed in Lao Cai

|

Lao Cai - The current status of the 860 billion VND industrial cluster is being accelerated for site clearance to create a premise for the project to be formed soon and attract investment.

Lao Cai accelerates comprehensively, firmly aim for double-digit growth

|

Lao Cai - Maintaining double-digit growth in the context of much pressure, the whole province is entering the second quarter with the spirit of "speeding up without waiting".

New regulations on civil servant positions

|

The Government assigned the Ministry of Home Affairs to advise on the promulgation of the Government's Decree regulating the position of civil servants.

Ministry of National Defense proposes to the Central Government to adjust the salary scale of the armed forces

|

The Ministry of National Defense proposes that the Central Government review, adjust, and complete the salary scale of the armed forces and cryptography.

US - Iran may restart negotiations this week

|

Negotiations to end the conflict with Iran may resume in Pakistan in the next few days, US President Donald Trump said on April 14.

Russian ship returns to port after 220 days, refuels 10,000 tons of oil for warships

|

Russian ship Kama of the Northern Fleet completed a 220-day voyage, refueling 10,000 tons of oil for Russian warships operating offshore.

Lao Cai sets a target of 75% of workers receiving vocational training by 2030

Đinh Đại |

Lao Cai - Not only increasing the rate of trained workers, the province also sets a target for the majority of learners to have jobs, tightening training with market demand.

Current status of the 860 billion VND industrial cluster site about to be formed in Lao Cai

Đinh Đại |

Lao Cai - The current status of the 860 billion VND industrial cluster is being accelerated for site clearance to create a premise for the project to be formed soon and attract investment.

Lao Cai accelerates comprehensively, firmly aim for double-digit growth

Bảo Nguyên |

Lao Cai - Maintaining double-digit growth in the context of much pressure, the whole province is entering the second quarter with the spirit of "speeding up without waiting".