On May 29, Lao Dong Newspaper reporters recorded that many vehicles and machines are focusing on the construction of the VSIP Ha Tinh Industrial Park Project in Viet Tien and Thach Lien communes.
Through observation, dozens of vehicles and machines have been mobilized by 2 contractors, Dai Hiep Company Limited and Dong Anh General Trading Company Limited, to participate in construction activities at the construction site.
Mr. Nguyen Van Sau - Vice Chairman of Thach Ha District People's Committee - said that after a period of slow construction due to lack of filling materials, the contractor has been granted a filling mine, so he is focusing on speeding up the construction of the VSIP Project in Thach Ha district.
According to Mr. Sau, the project has basically completed the digging of the fertilized soil, and is focusing on leveling the ground and constructing the road system in the project.
The project to invest in the construction and business of infrastructure of Bac Thach Ha Industrial Park, also known as VSIP Ha Tinh (Phase 1), was approved by the Prime Minister in Decision 1003 dated August 29, 2023 with an area of 190.41 hectares in Thach Lien and Viet Tien communes.
The project affects 696 households (Thach Lien 201 households, Viet Tien 495 households), of which 11 households have residential land (Viet Tien 10 households, Thach Lien 1 household), more than 300 graves must be relocated, the rest is mainly rice land allocated to households and land managed by the People's Committee of the commune.
According to Mr. Nguyen Van Sau, up to now, the project has completed the clearance of 99.9%. The area that has not been completed in the site clearance is 2,318.6 m2. In particular, in Viet Tien commune is 2,189.3 m2 (including 622.6m2 of grave land; 1,539.7m2 of residential land of 10 households with 11 land plots); In Thach Lien commune: 156.3 m2 of residential land of 1 household. In addition, it is also necessary to relocate medium and low voltage lines.
The plan is to complete site clearance for the residential land of 11 households before December 30, 2025, while the completion of relocation of medium and low voltage power lines will be slower due to procedures that take more time.

The VSIP Ha Tinh project is invested by Vietnam Singapore Urban and Industrial Park Development Joint Stock Company. The total investment of the project is 1,555 billion VND. The project started construction in June 2024.
VSIP Ha Tinh is expected to attract domestic and foreign investors in fields such as: Electricity and electronics, semiconductors, precision mechanics, energy, electric vehicle batteries, metals, auto parts, food processing, logistics services, factories for rent...
The project is expected to create more than 30,000 jobs, creating momentum for the development and economic restructuring of Ha Tinh province.