Lam Dong develops contingency plans when Da Lat waste treatment plant temporarily stops

Phúc Khánh |

Lam Dong - Da Lat Waste Treatment Plant is expected to temporarily suspend from October 1, 2026. Lam Dong province is surveying a temporary waste storage plan at Cam Ly landfill.

Survey of temporary waste storage plan

On September 11, the Department of Agriculture and Environment of Lam Dong province said that the unit will chair a working session with the Department of Finance, Department of Construction, People's Committee of Cam Ly - Da Lat Ward and Da Lat Urban Services Joint Stock Company to discuss a temporary waste storage plan at Cam Ly landfill.

Nhà máy xử lý rác Đà Lạt sẽ tạm ngừng tiếp nhận rác từ ngày 1.10 tới đây. Ảnh chụp ngày 14.6.2026 (Ảnh: Phúc Khánh)
Da Lat Waste Treatment Plant will temporarily stop receiving waste from October 1st. Photo taken on June 14th, 2026 (Photo: Phuc Khanh)

Previously, Mr. Nguyen Ngoc Phuc - Vice Chairman of Lam Dong Provincial People's Committee and leaders of departments, branches, and units inspected the reality at Cam Ly landfill and the planned location for the Solid Waste Treatment Plant project in Lac Duong commune area.

At the inspection, Mr. Nguyen Ngoc Phuc assigned Da Lat Urban Services Joint Stock Company to select a consulting unit according to regulations to survey, determine the scale, scope and total investment to serve the temporary storage of garbage at Cam Ly landfill.

Leaders of the Provincial People's Committee requested not to expand the existing Cam Ly landfill, and at the same time determine the storage capacity and items to be invested in, ensuring environmental protection requirements during the temporary waste storage period.

Factory requests temporary suspension from October 1st.

On September 10, Green Energy Environment Co., Ltd. - the investor of Da Lat Waste Treatment Plant - sent a document to the Department of Agriculture and Environment of Lam Dong province requesting temporary suspension of factory operation from 0:00 on October 1, 2026.

Lâm Đồng đang lên phương án xử lý rác cho khu vực Đà Lạt khi nhà máy xử lý rác Đà Lạt tạm ngưng nhận rác. Ảnh chụp ngày 14.6.2026 (Ảnh: Phúc Khánh)
Lam Dong is developing a waste treatment plan for the Da Lat area when the Da Lat waste treatment plant temporarily stops receiving waste. Photo taken on June 14, 2026 (Photo: Phuc Khanh)

According to the business, the unit is facing financial difficulties and does not have enough resources to continue to maintain factory operations.

The business said that from January 2026 to now, the payment of waste treatment costs has been difficult and not guaranteed according to regulations. At the same time, the company is under pressure from the judgment enforcement agency.

Previously, Green Energy Environment Co., Ltd. had repeatedly notified the local authorities about the temporary suspension of receiving and treating waste.

Most recently, in mid-June 2026, the enterprise temporarily stopped receiving and treating waste due to financial difficulties.

In 2 days, June 13-14, hundreds of tons of garbage accumulated on the streets of Da Lat area, affecting people's lives, urban aesthetics and local tourism image.

By the afternoon of June 14, Da Lat Urban Services Joint Stock Company had to mobilize about 200 workers and 30 specialized vehicles to collect and treat the amount of accumulated garbage in 5 wards in Da Lat area.

Phúc Khánh
RELATED NEWS

Lam Dong requests clarification of the basis for waste treatment prices

|

Lam Dong - The Provincial Department of Agriculture and Environment has just issued a document guiding the settlement of the petition of Green Friendly Environment Joint Stock Company regarding domestic waste treatment.

Waste treatment plant stops operating, wards in Da Lat flooded with domestic waste

|

Lam Dong - After 3 days of collection interruption due to the treatment plant stopping operation, waste in the center of Da Lat is congested, smelly, causing serious pollution.

Directing to clarify responsibilities in waste treatment in Bao Loc area

|

Lam Dong - The Provincial People's Committee directed to clarify the responsibilities of collectives, individuals and heads related to the treatment of domestic solid waste in the Bao Loc area.

Thousands of tons of clams raised by people die after storms

|

Thanh Hoa - Mass clam deaths at about 60ha of farming ground of 50 households in Ngoc Son ward, estimated damage output from 2,000-2,400 tons.

Houthi forces completely control the strategic Bab al Mandab strait

|

Houthi forces in Yemen have just seized control of Mayyun Island and taken over the Bab al Mandab Strait, a vital shipping route for global oil exports.

Ministry of Industry and Trade requests Grab to clarify fares, fees, and discounts

|

The National Competition Committee (Ministry of Industry and Trade) is conducting a review and verification of reflections related to Grab's price and fee policies.

Case of former principal collecting 15,000 VND/sidetime tutoring: Parents say students benefit

|

Parents affirmed that their children benefited and there was no damage in the case of the former Principal of Ba Dinh Secondary School collecting 15,000 VND/sidetime tutoring.

Lam Dong requests clarification of the basis for waste treatment prices

Phúc Khánh |

Lam Dong - The Provincial Department of Agriculture and Environment has just issued a document guiding the settlement of the petition of Green Friendly Environment Joint Stock Company regarding domestic waste treatment.

Waste treatment plant stops operating, wards in Da Lat flooded with domestic waste

Hải Đường |

Lam Dong - After 3 days of collection interruption due to the treatment plant stopping operation, waste in the center of Da Lat is congested, smelly, causing serious pollution.

Directing to clarify responsibilities in waste treatment in Bao Loc area

Phúc Khánh |

Lam Dong - The Provincial People's Committee directed to clarify the responsibilities of collectives, individuals and heads related to the treatment of domestic solid waste in the Bao Loc area.