Crossing mountains and rivers to build a 6,800 billion VND highway through Tuyen Quang

Việt Bắc |

Tuyen Quang - Ha Giang Expressway with route crossing mountainous terrain, crossing Lo River, construction progress is being accelerated.

Ghi nhan thoi diem giua thang 11.2024, tren doan Km 23 du an Cao toc Tuyen Quang - Ha Giang, mot vung nui doi rong lon da duoc san gat tao mat bang thi cong. Anh: Viet Bac.
Recorded in mid-November 2024, on Km 23 of the Tuyen Quang - Ha Giang Expressway project, a large mountainous area was leveled to create a construction site. Photo: Viet Bac.
Chieu dai toan tuyen gan 105 km, trong do 77 km qua tinh Tuyen Quang, 27,5 km qua Ha Giang. Dia hinh chu yeu doi nui dat, khoi luong san gat, dao dap lon.
The construction terrain is mainly hills and mountains, with a large volume of leveling, excavation and filling. Photo: Viet Bac.
Hien tai, cac nha thau dang tap trung thi cong nen duong, ha taluy duong. Anh: Viet Bac.
Currently, contractors are focusing on constructing the roadbed and lowering the slope. Photo: Viet Bac.
Tren toan tuyen, nhu cau cau dat dap khoang 10,7 trieu m3, trong do hon 8 trieu m3 khai thac tai du an. Anh: Viet Bac.
Along the entire route, the demand for earth fill is about 10.7 million m3, of which more than 8 million m3 is exploited at the project. Photo: Viet Bac.
Tuy nhien, theo don vi thi cong, hien nay tren toan tuyen dang thieu dat dap do vuong cac thu tuc nen chua the khai thac dat. Viec nay co the anh huong toi tien do cua du an. Anh: Viet Bac.
However, according to the construction unit, there is currently a shortage of fill soil along the entire route due to procedural issues, so the soil cannot be exploited. This may affect the progress of the project. Photo: Viet Bac.
Du an duong cao toc Ha Giang - Tuyen Quang doan qua tinh Tuyen Quang dai 77km, co tong muc dau tu 6.800 ti dong do Ban QLDA Dau tu xay dung cac cong trinh giao thong tinh Tuyen Quang lam chu dau tu. Anh: Viet Bac.
The Ha Giang - Tuyen Quang expressway project, the 77 km long section through Tuyen Quang province, has a total investment of VND6,800 billion and is invested by the Tuyen Quang Province Traffic Construction Investment Project Management Board. Photo: Viet Bac.
 Dien tich su dung dat doan qua tinh Tuyen Quang khoang 643ha, chu yeu dat rung san xuat, dat trong lua. Anh: Viet Bac.
The land use area in Tuyen Quang province is about 643 hectares, mainly production forest land and rice land. Photo: Viet Bac.
Mot hang muc cong ngam tren tuyen dang duoc thi cong. Anh: Viet Bac.
An underground sewer project on the route is under construction. Photo: Viet Bac.
Cau song Lo tai xa Tan Quang (huyen Bac Quang, Ha Giang), cay cau vuot song lon nhat tren tuyen cao toc Tuyen Quang - Ha Giang. Anh: Viet Bac.
Lo River Bridge in Tan Quang Commune (Bac Quang District, Ha Giang), the largest river-crossing bridge on the Tuyen Quang - Ha Giang Expressway. Photo: Viet Bac.
Theo bao cao cua chu dau tu, hien tai toan bo 6/6 goi thau xay lap phan duong va cau tren tuyen da duoc dong loat trien khai voi 90 mui thi cong. Anh: Viet Bac.
Informing reporters, the investor representative said that currently all 6/6 construction packages for the road and bridge sections on the route have been simultaneously deployed with 90 construction teams. The implementation value reached about 14.55%. Photo: Viet Bac.
Việt Bắc
TIN LIÊN QUAN

Expressway project through Soc Trang province is 9.3% behind schedule

|

Soc Trang - Component 4 project of Chau Doc - Can Tho - Soc Trang expressway section through Soc Trang province reached 14.2% of contract value.

Urgently repair highway worth more than 10 trillion before collecting tolls

|

After 10 years of operation, the Hanoi - Thai Nguyen expressway is expected to collect tolls in early 2025, and repairs are being urgently implemented.

After road repair and toll increase, Noi Bai - Lao Cai highway is still bad

|

Although it was repaired before the toll increase, the Noi Bai - Lao Cai highway still makes many drivers worried because of the degraded and damaged road surface.

Ho Chi Minh City requests review of Cambridge International certificates

|

Ho Chi Minh City People's Committee requires units to inspect and review officials who have declared the use of foreign language certificates named "Cambridge International".

SPT Company must pay nearly 500 million VND after tax inspection

|

Thanh Hoa Provincial Tax Department has requested SPT Architecture Joint Stock Company to pay nearly 500 million VND due to incorrect tax declaration.

Tens of thousands of people flock to watch the Ngo boat racing festival in Soc Trang

|

Mekong Delta - From November 14-15, 60 boat teams from provinces and cities in the Mekong Delta will compete in the Ngo Boat Race with fierce and exciting matches.

My Boss Expressed His Love Even Though He Knew I Was Getting Married (Part 1)

|

Hour 9 - The female employee is expressed her feelings by her manager when she is about to get married. What will this girl decide?

8pm News: Merging many wards in 6 central districts of Hanoi

|

News at 8pm on November 14: Hanoi merged many wards in 6 central districts; Arrested and took statements from singer Chi Dan, model An Tay...

Expressway project through Soc Trang province is 9.3% behind schedule

PHƯƠNG ANH |

Soc Trang - Component 4 project of Chau Doc - Can Tho - Soc Trang expressway section through Soc Trang province reached 14.2% of contract value.

Urgently repair highway worth more than 10 trillion before collecting tolls

Việt Bắc |

After 10 years of operation, the Hanoi - Thai Nguyen expressway is expected to collect tolls in early 2025, and repairs are being urgently implemented.

After road repair and toll increase, Noi Bai - Lao Cai highway is still bad

Nguyễn Tùng |

Although it was repaired before the toll increase, the Noi Bai - Lao Cai highway still makes many drivers worried because of the degraded and damaged road surface.