86 billion VND waste treatment project in Hue "shelved" for 7 years

PHÚC ĐẠT - NGUYỄN LUÂN |

HUE - Implemented since 2018, the waste treatment project in Binh Dien commune is still unfinished, the construction site is deserted of workers, and many items are degraded even though they have not been used.

Du an xu ly triet de o nhiem moi truong do rac thai sinh hoat tai xa Binh Dien (TP Hue) duoc trien khai tu nam 2018, du kien hoan thanh nam 2022, den nay van dang do.
The project to thoroughly treat environmental pollution caused by domestic waste in Binh Dien commune (Hue City) was implemented from 2018, expected to be completed in 2022, but is still unfinished.
Ghi nhan cua phong vien Bao Lao Dong chieu 29.12, tai cong truong khong co cong nhan, may moc thi cong, nhieu hang muc dung lai trong thoi gian dai.
According to reporters of Lao Dong Newspaper on the afternoon of December 29, there were no workers or construction machinery at the construction site, and many items were stopped for a long time.
Ho chon lap, ho dieu hoa, thap nuoc, nha dieu hanh da thi cong co ban nhung bi bo hoang, xuong cap giua mua nang.
The burial pit, regulating lake, water tower, and operating house have been basically constructed but are abandoned and degraded in the rain and sun.
Mot so tuyen duong noi bo, ho chon lap, he thong thoat nuoc bi sat lo, boi lap do mua lu va ngung thi cong keo dai.
Some internal roads, burial pits, and drainage systems were landslides and silted up due to rain and prolonged construction suspension.
Theo Chu dau tu la Ban Quan ly du an (Ban QLDA) Dau tu xay dung va Phat trien do thi TP Hue, du da nhieu lan gia han tien do va xu phat nha thau, khoi luong xay dung moi dat khoang 80%.
According to the Investor, the Project Management Board (PMB) for Investment, Construction and Urban Development of Hue City, although it has repeatedly extended the progress and fined contractors, the construction volume has only reached about 80%.
Thap nuoc da hoan thien nhung chua the su dung.
The water tower is completed but cannot be used yet.
Ban QLDA da xu ly tam thoi mot so vi tri sat lo, bo sung he thong thu nuoc ngam va gia co cuc bo nham on dinh cong trinh. Du da gia co, trong mua mua lu nam nay, cong trinh van xuat hien them cac diem hu hong, tiem an rui ro.
The Project Management Board has temporarily handled some landslide locations, supplemented groundwater intake systems and localized reinforcements to stabilize the project. Although reinforcements have been made, in this year's rainy and flood season, the project still has more damage points, potential risks.
Nhieu hang muc xay len dang do roi bo khong dan den viec chua dung da xuong cap.
Many items are built unfinished and then abandoned, exposed to sun and rain.
 May moc, vat lieu ngon ngang, hoen ri.
Machinery and materials are scattered, rusty.
Ban QLDA cho biet, do chua xac dinh duoc nguon cung cap, khoi luong, thoi diem co rac de van hanh nen cac don vi lien quan chua lap dat thiet bi vi lo ngai se de hu hong, mat trom.
The Project Management Board said that because the source of supply, volume, and time of garbage for operation have not been determined, relevant units have not installed equipment because they are worried that it will be easily damaged and stolen.
Cung theo Ban QLDA, hien don vi da thuc hien dieu chuyen mot so hang muc tu giai doan 1 sang giai doan 2. Dong thoi, dieu chinh thoi gian thuc hien du an doi voi giai doan 1 keo dai den het quy II.2026. Giai doan 2 se tap trung xay dung cac hang muc va mua sam thiet bi cho cac hang muc nhu lo dot rac, may ui, may xuc... de dua toan bo cong trinh vao hoat dong.
Also according to the Project Management Board, the unit has transferred some items from phase 1 to phase 2. At the same time, adjusting the project implementation time for phase 1 to last until the end of the second quarter of 2026. Phase 2 will focus on building items and purchasing equipment for items such as incinerators, bulldozers, excavators... to put the entire project into operation.

The project to thoroughly treat environmental pollution caused by domestic waste in Binh Dien commune (Hue City) has a total investment of nearly 86 billion VND for 2 phases; of which phase 1 is more than 68 billion VND, phase 2 is more than 17 billion VND.

To date, the project has disbursed about 50 billion VND, invested by the Hue City Urban Development and Construction Investment Project Management Board.

The project aims to treat domestic waste for the northern area of Hue City, phase 1 capacity reaches 150 tons/day.

PHÚC ĐẠT - NGUYỄN LUÂN
RELATED NEWS

Da Nang does not allow site clearance to slow down project

|

Da Nang - As of December 26, the disbursement rate of public investment capital of the city has only reached 67.8% of the Government's assigned plan.

Lao Dong Newspaper warns of capital increase for coastal road project before inspection conclusion

|

Quang Tri - Before the Government Inspectorate pointed out violations, Lao Dong Newspaper reported abnormalities in the proposal to adjust and increase capital in the coastal road project.

Dak Lak criticizes Director of Department of Finance for slow reporting on investment projects

|

Dak Lak - Director of the Department of Finance has just been criticized for delaying reporting and advising the Provincial People's Committee on investment projects in the area.

Teacher suspected of molesting 8th grade female student temporarily suspended from work

|

Ha Tinh - A teacher suspected of molesting an 8th grade female student at Chu Van An Secondary School (in Huong Khe commune) has just been temporarily suspended from work.

Panko Vina suspends operations before Tet, workers look forward to 13th month salary

|

Ho Chi Minh City - Panko Vina Co., Ltd. announced the cessation of operations, workers hope the company will pay the 13th month salary to have money to cover Tet expenses.

Warehouse fire in Da Lat at night, many items burned down

|

Lam Dong - A warehouse fire occurred in the dark night on Le Van Tam street. Functional forces promptly extinguished the fire, preventing the fire from spreading.

Decades-delayed projects in Thanh Hoa

|

Thanh Hoa - Currently, there are hundreds of backlog projects, slow progress, and even some projects have been "stuck in place" for decades.

Gia Lai pilots night economy to avoid mistakes, creates new breakthrough

|

Gia Lai is piloting night economy models, both experimenting and evaluating to avoid mistakes, with the goal of exploring the potential of night tourism - services.

Da Nang does not allow site clearance to slow down project

Nguyễn Linh |

Da Nang - As of December 26, the disbursement rate of public investment capital of the city has only reached 67.8% of the Government's assigned plan.

Lao Dong Newspaper warns of capital increase for coastal road project before inspection conclusion

HƯNG THƠ |

Quang Tri - Before the Government Inspectorate pointed out violations, Lao Dong Newspaper reported abnormalities in the proposal to adjust and increase capital in the coastal road project.

Dak Lak criticizes Director of Department of Finance for slow reporting on investment projects

BẢO TRUNG |

Dak Lak - Director of the Department of Finance has just been criticized for delaying reporting and advising the Provincial People's Committee on investment projects in the area.