Current status of a transport project worth more than 1,100 billion VND in Hue before changing investors

PHÚC ĐẠT - NGUYỄN LUÂN |

HUE will replace the investor and terminate the contract with the weak contractor, causing the key traffic project of To Huu extended road to Phu Bai airport to be delayed.

Dự án đường Tố Hữu nối dài đi sân bay Phú Bài đang thi công chậm tiến độ. Chủ đầu tư đã nhiều lần xử phạt nhà thầu do không đảm bảo tiến độ theo hợp đồng.
The To Huu extended road project to Phu Bai airport (Hue City) is under slow construction progress. The investor has repeatedly fined the contractor for not ensuring the progress according to the contract.
Ghi nhận của PV Báo Lao Động chiều 5.7, trên toàn tuyến vẫn còn nhiều đoạn thi công dang dở, chưa được triển khai đồng bộ.
Recorded by Lao Dong Newspaper reporters on the afternoon of July 5, there are still many unfinished construction sections on the entire route that have not been deployed synchronously.
Tại gói thầu số 21, nhiều đoạn nền đường mới chỉ đắp cát, đắp đất một phần rồi dừng thi công, chưa thể kết nối liên tục. Phần việc do Công ty CP Tập đoàn Đồng Tâm đảm nhận là khu vực chậm nhất, nhiều vị trí vẫn ngổn ngang, xuất hiện hố nước và nền đất nhão.
At package No. 21, many sections of the roadbed have only been filled with sand and soil for a part and then construction has stopped, and continuous connection is not possible. The work undertaken by Dong Tam Group Joint Stock Company is the slowest area, many locations are still messy, with water holes and soft soil appearing.
Một số cầu vượt kênh trên tuyến đang được các nhà thầu triển khai thi công, hình hài công trình dần hiện rõ.
Some overpasses on the route are being implemented by contractors, and the shape of the project is gradually becoming clear.
Máy móc được tập kết tại công trường nhưng số lượng công nhân trực tiếp thi công còn khá ít.
Machinery is gathered at the construction site, but the number of workers directly constructing is still quite small.
Các trụ cầu đang được thi công tại nhiều vị trí trên tuyến, phục vụ kết nối các đoạn đường qua khu vực đồng ruộng.
Bridge pillars are being constructed at many locations on the route, serving the connection of road sections through the field area.
Điều kiện địa chất nhiều bùn, nước khiến việc xử lý nền đất và thi công gặp không ít khó khăn.
The geological conditions with a lot of mud and water make the treatment of the soil foundation and construction encounter many difficulties.
Nhiều đoạn tuyến được phủ bạt kỹ thuật để phục vụ xử lý nền đất yếu trước khi triển khai các hạng mục tiếp theo.
Many sections of the route are covered with technical tarpaulins to serve weak soil treatment before deploying subsequent items.
Tăng cường triển khai thi công tại các khu vực có nền đất yếu.
Strengthen the implementation of construction in areas with weak soil foundations.
Nhiều vị trí trên tuyến vẫn chưa được kết nối giữa các đoạn thi công, khiến mặt bằng còn rời rạc.
Many locations on the route are still not connected between construction sections, causing the ground to be still disjointed.
Điểm đầu của dự án tại khu E - Khu đô thị mới An Vân Dương hiện vẫn chưa triển khai thi công.
The starting point of the project in Zone E - An Van Duong New Urban Area has not yet been implemented.
Toàn dự án vẫn còn nhiều hạng mục phải đẩy nhanh tiến độ để đảm bảo mục tiêu hoàn thành theo kế hoạch.
The entire project still has many items to accelerate progress to ensure the goal of completion according to plan.

The To Huu extended road to Phu Bai airport project was approved by Hue City People's Committee in 2023 with a total investment of 1,143 billion VND, a length of about 9.59km, starting point at Zone E - An Van Duong new urban area and ending point connecting Thuan Hoa road intersection with National Highway 1 (Phu Bai ward). The project was started on January 20, 2025, with a implementation time of 4 years.

For package No. 21, the work undertaken by Dong Tam Group Joint Stock Company is worth about 196 billion VND. During the construction process, this contractor was fined twice by the investor with a total amount of 411 million VND for violating the contract progress. After many urging but failing to rectify, the Hue City Urban Development and Construction Investment Project Management Board issued a decision to terminate the contract, and at the same time carried out procedures to confiscate more than 10 billion VND of contract performance guarantee money and recover more than 38 billion VND of unpaid advance money.

To remove obstacles and accelerate the project progress, Hue City People's Committee has agreed on the policy of transferring the project investor from the Project Management Board for Construction Investment and Urban Development to the Project Management Board for Construction Investment Area 3, and at the same time requested to complete the handling of existing problems related to contractors before July 10, 2026.

PHÚC ĐẠT - NGUYỄN LUÂN
RELATED NEWS

Sluggish 650 billion VND provincial road project in Lam Dong

|

Lam Dong - The DT. 721 road project has a total investment of about 650 billion VND, started in August 2024, but so far construction is still slow and behind schedule.

Dong Nai publicly announces key traffic project with an area of 37ha

|

Dong Nai - Road 768B project with an area of 37ha expanded from 30m to 60m, with a length of more than 6km.

Trillions of VND to implement a series of social housing projects in Thai Nguyen

|

Thai Nguyen sets a target to complete 60,000 social housing units by 2030, 2.4 times higher than the target assigned by the Central Government.

Current status of a transport project worth more than 1,100 billion VND in Hue before changing investors

|

HUE will replace the investor and terminate the contract with the weak contractor, causing the key traffic project of To Huu extended road to Phu Bai airport to be delayed.

Vietnam national team wins big in first friendly match in Korea

|

The Vietnamese team had a favorable start in the training trip in Korea when they defeated Siheung FC with a score of 6-0 in the first practice match.

Strategy to register aspirations to increase chances of university admission in 2026

|

Choosing and arranging aspirations reasonably will help candidates increase their chances of being admitted to the desired university.

Sluggish 650 billion VND provincial road project in Lam Dong

Phúc Khánh |

Lam Dong - The DT. 721 road project has a total investment of about 650 billion VND, started in August 2024, but so far construction is still slow and behind schedule.

Dong Nai publicly announces key traffic project with an area of 37ha

HÀ ANH CHIẾN |

Dong Nai - Road 768B project with an area of 37ha expanded from 30m to 60m, with a length of more than 6km.

Trillions of VND to implement a series of social housing projects in Thai Nguyen

Việt Bắc |

Thai Nguyen sets a target to complete 60,000 social housing units by 2030, 2.4 times higher than the target assigned by the Central Government.