Machinery rumbles at Phong Chau bridge construction site on 29th of Tet

Bài và Ảnh: Tô Công - Quốc Huy |

Phu Tho - On the 29th of Tet, the construction site of the new Phong Chau bridge and the dismantling and clearing of the old bridge were still under construction, the sound of machinery resounded throughout the area.

Theo ghi nhan cua phong vien Bao Lao Dong chieu 28.1 (tuc ngay 29 thang Chap), cac ky su, cong nhan cua Tong Cong ty xay dung Truong Son van dang miet mai thi cong xay dung cau Phong Chau moi va thao do, thu don cac phan cau cu.
According to Lao Dong Newspaper reporters on the afternoon of January 28 (December 29), from the shore to the Red River, engineers and workers of Truong Son Construction Corporation are still working hard to build the new Phong Chau bridge and dismantle and clean up parts of the old bridge.
Co the thay, phia xa Phung Nguyen, huyen Lam Thao, Mo, tru T2, tru T3, tru T4 cua phan cau cu da duoc xu ly xong.
It can be seen that, in Phung Nguyen commune, Lam Thao district, pier 1, pillar T2, pillar T3, pillar T4 of the old bridge section have been completed.
han dam tu tru T5 den tru T6 voi khoi luong sat thep rat lon da duoc dua sang ben canh.
The beam section from column T5 to column T6 with a huge amount of steel and concrete has been moved to the side.
Cac dam cau duoc dua ve vi tri tap ket.
The bridge girders are brought to the assembly location.
Phia xa Van Xuan, huyen Tam Nong, Tu T8 va Mo 9 cua phan cau cu cung da co ban duoc xu ly xong.
In Van Xuan commune, Tam Nong district, pillar T8 and pier 9 of the old bridge section are also being processed.
Hien, cong truong dang thi cong cac coc khoan nhoi. Tieng may cau, may xuc, may khoan, tau thuyen... ca tren bo va duoi song ren vang ca mot vung, tao nen mot khong khi thi cong day hang say trong ngay cuoi cung cua nam.
Regarding the construction of the new Phong Chau bridge, large machinery at the construction site is constructing a series of bored piles...
Tieng may cau, may xuc, may khoan, tau thuyen... ca tren bo va duoi song ren vang ca mot vung, tao nen mot khong khi thi cong day hang say trong ngay cuoi cung cua nam.
The sound of cranes, excavators, drills, boats... both on the shore and under the river echoed throughout the area, creating an enthusiastic construction atmosphere on the last day of the year.
Voi cau phao Phong Chau, Binh chung Cong binh (Bo Quoc phong) da co thong bao duy tri hoat dong cau phao Phong Chau tu 21h ngay 28.1 (tuc ngay 29 thang Chap nam Giap Thin) den 5h ngay 29.1 (tuc mung 1 Tet At Ty 2025), nguoi dan co the qua cau phao to chuc hoat dong vui xuan, don Tet dem giao thua.
Regarding Phong Chau pontoon bridge, the Engineering Corps (Ministry of National Defense) has announced that the pontoon bridge will be maintained from 9:00 p.m. on January 28 (ie December 29, Giap Thin year) to 5:00 a.m. on January 29 (ie the first day of Tet At Ty 2025), people can cross the pontoon bridge to organize spring activities and celebrate Tet on New Year's Eve.
Bài và Ảnh: Tô Công - Quốc Huy
TIN LIÊN QUAN

Phong Chau Bridge and other major projects to be completed in 2025 in Phu Tho

|

In 2025, along with the new Phong Chau bridge, Phu Tho province has many projects worth hundreds of billions of VND expected to be completed and put into use.

Phong Chau Bridge inauguration on December 22, 2025

|

Minister of Transport Tran Hong Minh said that Phong Chau Bridge, Phu Tho will be inaugurated on the occasion of the founding day of the Vietnam People's Army (December 22, 2025).

Road Department provides documents to police on Phong Chau bridge case

|

Responding to voters recently, the Ministry of Transport said it had assigned the Roads Department to provide investigation documents to the police on the Phong Chau bridge collapse.

Vietnamese tourists are required to declare online when traveling to Thailand

|

From May 1, all international tourists traveling to Thailand must fill in their digital entry cards before entering the country. This is something Vietnamese tourists need to pay attention to.

The Ministry of Construction has many violations when adjusting the planning of the capital area

|

The Government Inspectorate has just pointed out many violations in adjusting the Construction Planning of the Capital Region.

The Inspection Committee proposes to discipline the former Vice Chairman of the Dong Nai Provincial People's Committee

|

The Provincial Party Committee's Inspection Committee proposed to discipline former Vice Chairman of Dong Nai Provincial People's Committee Vo Van Chanh for related land violations.

Ho Chi Minh City sidewalks "transformed", people are excited about clean and beautiful walking paths

|

HCMC - After the renovation process, many sidewalks in the city center have taken on a new look, people are excited because they have a clean and beautiful walking space.

Hanoi Police lost the first leg of the Southeast Asian Cup C1 semi-final

|

Hanoi Police lost 0-1 to PSM Makassar in the first leg of the 2024-2025 Southeast Asian Cup C1 semi-final on the evening of April 2.

Phong Chau Bridge and other major projects to be completed in 2025 in Phu Tho

Tô Công |

In 2025, along with the new Phong Chau bridge, Phu Tho province has many projects worth hundreds of billions of VND expected to be completed and put into use.

Phong Chau Bridge inauguration on December 22, 2025

Hiếu Anh |

Minister of Transport Tran Hong Minh said that Phong Chau Bridge, Phu Tho will be inaugurated on the occasion of the founding day of the Vietnam People's Army (December 22, 2025).

Road Department provides documents to police on Phong Chau bridge case

Xuyên Đông |

Responding to voters recently, the Ministry of Transport said it had assigned the Roads Department to provide investigation documents to the police on the Phong Chau bridge collapse.