1 year of Phong Chau bridge collapse disaster

TÔ CÔNG |

Phu Tho - Over the past year, many works have been deployed to fix the Phong Chau bridge collapse incident.

Tu Do anh huong cua hoan luu Bao so 3 Yagi, mua lon khien lu cac song, suoi tai mien Bac len nhanh. Tren song Hong (song Thao) tai Phu Tho, bat dau tu ngay 8.9.2024, lu da co lap nhieu ho dan xa Hien Luong, huyen Ha Hoa cu (nay la xa Hien Luong).
Due to the influence of the circulation of Storm No. 3 Yagi, heavy rain caused floods in rivers and streams in the North to rise rapidly. On the Red River (Thao River) in Phu Tho, starting from September 8, 2024, floods have isolated many households in Hien Luong commune, the old Ha Hoa district (now Hien Luong commune).
Den khoang 10h2' ngay 9.9.2024, cau Phong Chau tren Quoc lo 32 noi 2 huyen Tam Nong va Lam Thao (2 huyen cua tinh Phu Tho cu) bi sap nhip, cuon troi tru T7 va 2 nhip dan chinh.
At about 10:02 a.m. on September 9, 2024, Phong Chau bridge on National Highway 32 connecting Tam Nong and Lam Thao districts (2 districts of the old Phu Tho province) collapsed, sweeping away pillar T7 and 2 main spans.
Theo thong tin ban dau, thai thoi diem xay ra su co co 10 phuong tien dang di chuyen tren cau (1 xe oto tai, 2 xe oto dau keo, 6 xe mo to, 1 xe may dien), khien cho 8 nguoi mat tich, 3 nguoi bi thuong.
At the time of the incident, there were 10 vehicles moving on the bridge (1 truck, 2 tractor-trailers, 6 motorbikes, 1 electric motorbike), leaving 8 people missing and 3 injured.
Ngay sau khi xay ra su co, cac co quan chuc nang tinh da khan truong trien khai cong tac cuu ho, cuu nan. Cong tac tim kiem, truc vot nguoi, phuong tien, phan cau bi sap duoi song da duoc thuc hien xuyen suot nhieu tuan sau do.
Immediately after the incident, the provincial authorities promptly deployed rescue work. The search and salvage of people, vehicles, and the collapsed bridge section under the river was carried out for many weeks afterwards.
Bo Quoc phong cung nhanh chong huy dong nhan luc, phuong tien, khi tai chuan bi lap cau phao qua song phuc vu viec di lai cua nguoi dan.
The Ministry of National Defense also quickly mobilizes human resources, vehicles, and equipment, ready to install pontoon bridges across the river when weather and hydrological conditions allow.
Den ngay 30.9, cau phao Phong Chau chinh thuc thong xe. Cac xe oto con, xe ban tai duoc phep luu thong 1 chieu, cac xe tho so, xe may, xe gan may, mo to 3 banh duoc phep luu thong 2 chieu, van toc khong qua 5km/h.
On September 30, Phong Chau pontoon bridge officially opened to traffic, serving people's travel until now.
Den ngay 29.10.2024, Phu Tho ket thuc tim kiem nan nhan mat tich trong vu sap cau Phong Chau, tap trung thao do phan con lai cua cau, dong thoi duy tri cau phao va pha de phuc vu nhu cau di lai cua nguoi dan.
On October 29, 2024, Phu Tho completed the search for missing victims in the Phong Chau bridge collapse, focusing on dismantling the remaining part of the bridge, while maintaining a pontoon bridge and ferry to serve the travel needs of the people.
Den thang 10.2024, ngay sau khi duoc giao nhiem vu xay dung cau Phong Chau moi, Ban Quan ly du an Thang Long (Chu dau tu) cung Tong Cong ty Xay dung Truong Son (don vi thi cong) da khan truong huy dong nhan luc, phuong tien de trien khai cac cong viec.
Also in October 2024, immediately after being assigned the task of building the new Phong Chau bridge, the Thang Long Project Management Board (Investor) and Truong Son Construction Corporation (construction unit) urgently mobilized human resources and means to carry out the work.
Thang 11.2024, cong tac thao do phan cau Phong Chau cu ca duoi song va tren bo da duoc trien khai.
In November 2024, the demolition of the old Phong Chau bridge both under the river and on the shore was carried out. Previously, a large area on the left bank of the Red River (Phung Nguyen commune) was prepared.
Den ngay 21.12.2024, sau khi Du an dau tu xay dung cau Phong Chau moi - Quoc lo 32C, tinh Phu Tho duoc phat lenh khoi cong, nhan luc va phuong tien duoc huy dong toi da den cong truong.
On December 21, 2024, after the investment project to build the new Phong Chau bridge - National Highway 32C, Phu Tho province was given a start date, human resources and vehicles were mobilized to the maximum to the construction site.
Tong Cong ty Xay dung Truong Son da to chuc thi cong 3 ca, 4 kip, khong ke ngay dem, le tet, phan dau hoan thanh cong trinh som nhat co the
Truong Son Construction Corporation has organized construction in 3 shifts, 4 teams, regardless of day or night, holidays, striving to complete the project as soon as possible.
Den thang 2.2025, hang muc coc khoan nhoi - mot trong nhung hang muc quan trong nhat cua cong trinh, gom 74 mui khoan coc nhoi ca tren bo va duoi song da hoan thanh vuot tien do, dap ung yeu cau ky thuat nghiem ngat.
By February 2025, the bored pile item - one of the most important items of the project, including 74 bored pile drilling points both on the banks and under the river, had been completed ahead of schedule, meeting strict technical requirements.
Thang 3.2025, sau khi hoan thanh trien khai cong tac do betong bit day tru, cac be mong va than tru da dan thanh hinh.
In March 2025, after completing the implementation of concrete pouring to cover the base of the pillars, the foundations and body of the pillars have gradually taken shape.
Trong thang 4, 5, 6, 7.2025, don vi thi cong da do betong 6 tru cau, do betong xa mu tru, trien khai cac hang muc lao lap dam va do betong ban mat cau.
In April, June, and July 2025, the construction unit poured concrete for 6 bridge piers, poured concrete for the pillar and helmet bar, deployed items to install girders and pour concrete for the bridge deck.
Sau hon 8 thang thi cong, ngay 27.8, Bo Xay dung, Bo Quoc phong va tinh Phu Tho to chuc le hop long cau Phong Chau moi.
After more than 8 months of construction, on August 27, the Ministry of Construction, the Ministry of National Defense and Phu Tho province held a ceremony to close the new Phong Chau bridge.
Den nay, don vi thi cong dang tham nhua mat cau, ngay cong trinh cau Phong Chau moi dua vao khai thac su dung da khong con xa.
Up to now, the construction unit is paving the bridge surface, the date the new Phong Chau bridge project was put into operation and use is not far away.
TÔ CÔNG
RELATED NEWS

Officially closing Phong Chau bridge on the Red River

|

Phu Tho - The Phong Chau bridge project on National Highway 32 across the Red River has been officially closed.

Prime Minister directs to close the new Phong Chau bridge on August 28

|

The Prime Minister requested the units to make efforts to construct the new Phong Chau bridge on August 28, completing on schedule in early October.

Tu Lap wins inter-regional road package extending near Phong Chau bridge

|

Phu Tho - The investor has approved the results of the selection of contractors to construct the extended road from Km0 of the inter-regional road to near Phong Chau bridge.

The Ministry of Industry and Trade responds to the proposal to calculate household electricity prices according to operating hours

|

The Ministry of Industry and Trade has responded to the petition of voters in Dong Nai province sent before the 9th Session of the 15th National Assembly regarding the issue of electricity prices.

Clarifying the case of a dump truck reversing 3 motorbikes in the red light waiting area in Ho Chi Minh City

|

HCMC - On DT 741 road, a dump truck reversed 3 motorbikes in the waiting area for red lights at Ben Tram intersection, Phuoc Hoa commune.

"Mass fish died in Hon Bac" due to falling into a net while fishing

|

Khanh Hoa - The provincial Department of Agriculture and Environment has reported the results of verifying the mass death of sea fish in the Hon Bac area, Dong Ninh Hoa ward.

2 miracles of the deceased computer god were declared by the Vatican

|

Carlo Acutis became the new Saint of the Catholic Church on September 7, and is considered by many to be "the first Saint to wear jeans".

Officially closing Phong Chau bridge on the Red River

Tô Công |

Phu Tho - The Phong Chau bridge project on National Highway 32 across the Red River has been officially closed.

Prime Minister directs to close the new Phong Chau bridge on August 28

PHẠM ĐÔNG |

The Prime Minister requested the units to make efforts to construct the new Phong Chau bridge on August 28, completing on schedule in early October.

Tu Lap wins inter-regional road package extending near Phong Chau bridge

Tô Công |

Phu Tho - The investor has approved the results of the selection of contractors to construct the extended road from Km0 of the inter-regional road to near Phong Chau bridge.