Removing obstacles to Tan Duc Industrial Park site for construction and inauguration

Duy Tuấn |

Binh Thuan - Departments, branches, districts and investors are making efforts to remove obstacles in the Tan Duc Industrial Park (IP) site for construction and inauguration of infrastructure.

The Tan Duc Industrial Park Infrastructure Investment, Construction and Business Project in Tan Duc Commune, Ham Tan District, Binh Thuan Province was approved by the Prime Minister in 2021 with a scale of 300 hectares and a total investment of 1,360 billion VND.

Phoi canh KCN Tan Duc. Anh: Sonadezi
Perspective of Tan Duc Industrial Park. Photo: Sonadezi

The Management Board of Binh Thuan Industrial Parks has issued an Investment Registration Certificate to Sonadezi Binh Thuan Joint Stock Company (investor). According to the investor's representative, so far 275 hectares have completed compensation and site clearance. On March 11, 2 more households handed over 2.6 hectares of land after being mobilized. The rest are being campaigned for compensation.

Currently, Tan Duc Industrial Park still has problems with residential land and agricultural land in residential areas (7.3 ha). Even the entrance to the industrial park is still stuck with unapproved land prices.

In the past, with the motto of having a site, the unit has focused on constructing there to keep up with the progress. The construction process is also slower due to the geological factors, so there must be blasting and time to complete the procedures. To date, the total cost that the investor has spent on site clearance compensation and construction is about 800 billion VND.

Diem ket noi duong vao KCN Tan Duc va Quoc lo 1. Anh: Duy Tuan
The connection point of the road to Tan Duc Industrial Park and National Highway 1. Photo: Duy Tuan

Other items such as water supply for the industrial park have completed the water supply pipeline from Xuan Loc to the Tan Duc Industrial Park boundary, ready to supply water. To supply electricity to the industrial park, the Southern Power Corporation has committed to investing, including the 110 KV line and the Tan Duc Industrial Park transformer station, which are implementing investment procedures. It is expected to be completed by the end of 2027. The 22KV line in the industrial park is preparing investment procedures and is expected to be completed in 2025, ensuring the electricity load according to the industrial park's investment and construction progress.

The telecommunications system serving the industrial park has been agreed upon by Viettel Binh Thuan to invest. The construction drawing design documents for the Tan Duc Industrial Park connection with National Highway 1A have been approved and the Ham Tan District Project Management Board is implementing procedures to select a construction contractor. Construction is expected to start at the end of March 2025.

Loi vao KCN Tan Duc. Anh: Duy Tuan
Entrance to Tan Duc Industrial Park. Photo: Duy Tuan

Faced with the remaining problems, the investor recommended that the locality consolidate the records and make a list of households that need to carry out further enforcement to promptly clear the site and hand over clean land to the Construction Company. At the same time, support the resolution of problems and speed up the Company's land lease procedures in installments.

Regarding residential land and agricultural land in residential areas, it is necessary to approve specific land prices and complete compensation procedures for residential land and agricultural land in residential areas.

Binh Thuan provincial leaders affirmed the province's general spirit of making a strong determination to complete the infrastructure of Tan Duc Industrial Park Phase 1 as soon as possible.

May moc thi cong mat bang trong KCN Tan Duc, hoi thang 10.2024. Anh: Duy Tuan
Construction machinery in Tan Duc Industrial Park, in October 2024. Photo: Duy Tuan

Mr. Ha Le Thanh Chung - Chairman of Ham Tan District People's Committee - said that up to now, 93% of the project site has been basically handed over. The district has established 4 groups to mobilize people to hand over the site. Currently, 11 households have agreed to hand over 10 hectares, so the company needs to coordinate immediately with the locality to immediately implement compensation work. Specific land price work is also being urgently implemented. At the same time, the locality requested the company to mobilize more machinery to speed up the construction of the site.

It is expected that the Tan Duc Industrial Park Infrastructure Investment, Construction and Business Project will be inaugurated on April 19, 2025, on the occasion of the 50th Anniversary of the Liberation of Binh Thuan Province. Therefore, there is not much time left, departments, branches, localities and investors are trying to speed up the removal of obstacles for construction, ensuring progress according to plan.

Duy Tuấn
TIN LIÊN QUAN

Are clearing land to open a 50m wide central road in Hanoi

|

Hanoi - Some sections are being cleared to construct the Ring Road 1 project, Hoang Cau - Voi Phuc section, with an investment capital of more than VND 7,200 billion after many years of delay.

2 major investors propose to invest in projects in Binh Thuan

|

Binh Thuan - 2 major investors in the field of investment in construction and business of industrial park infrastructure want to cooperate in investment, proposing new projects in the province.

Land clearance problems slow down the progress of Van Thanh bridge in Phan Thiet

|

Binh Thuan - After more than 2 years of construction, the progress of the Van Thanh bridge project has only reached about 51% of the contract volume due to land clearance problems.

The death anniversary of Hung Vuong's great monk in Phu Tho is a grand festival

|

Phu Tho - The Hung Temple historical relic site is being decorated with many colors from the cultural funds of 13 districts, cities and towns in the area.

Prime Minister directs Vinh Phuc to focus on arranging administrative boundaries

|

The Prime Minister requested Vinh Phuc province to focus on implementation, ensuring progress in streamlining the apparatus and arranging administrative boundaries according to the direction of the Central Government.

HCMC reviews criteria for rearranging 273 wards, communes and towns

|

HCMC - The Ho Chi Minh City Department of Home Affairs is coordinating with districts, towns and Thu Duc City to review the criteria to develop a draft to reorganize 273 commune-level administrative units.

The Ministry of Finance talks about the 46% tax rate

|

The representative of the Ministry of Finance assessed that the US imposing a 46% tax on Vietnamese goods will negatively affect exports, requiring appropriate policy responses.

Dry port project in Hoai Duc abandoned for many years

|

The ICD My Dinh dry port project in Hoai Duc, Hanoi has been approved for nearly 10 years but has not been completed. However, the project's land has shown signs of lease.

Are clearing land to open a 50m wide central road in Hanoi

HỮU CHÁNH |

Hanoi - Some sections are being cleared to construct the Ring Road 1 project, Hoang Cau - Voi Phuc section, with an investment capital of more than VND 7,200 billion after many years of delay.

2 major investors propose to invest in projects in Binh Thuan

Duy Tuấn |

Binh Thuan - 2 major investors in the field of investment in construction and business of industrial park infrastructure want to cooperate in investment, proposing new projects in the province.

Land clearance problems slow down the progress of Van Thanh bridge in Phan Thiet

Duy Tuấn |

Binh Thuan - After more than 2 years of construction, the progress of the Van Thanh bridge project has only reached about 51% of the contract volume due to land clearance problems.