Speeding up the progress of the Phan Thiet Airport project

Duy Tuấn |

Binh Thuan speeds up the implementation of the Phan Thiet Airport project, a civil aviation project, striving to start construction in October 2025.

On March 11, Chairman of the Provincial People's Committee Do Huu Huy chaired a meeting to review the progress of the Phan Thiet Airport project.

According to the approved Planning, Phan Thiet airport includes military airport and civil airport. Up to now, the military airport project in Phan Thiet has been basically completed by the Ministry of National Defense. Including common items: Runway, taxiway, waiting yard; accurate landing equipment system; approach road; traffic lights, signs, etc. have been completed and put into use.

Duong vao du an san bay Phan Thiet. Anh: Duy Tuan
Road to Phan Thiet airport project. Photo: Duy Tuan

In particular, the Phan Thiet Airport project, the civil aviation item under the form of a BOT contract is carrying out procedures to adjust the investment policy (increasing the scale from level 4C to 4E). Up to now, the adjusted Pre-Feasibility Study Report dossier has been appraised by the Interdisciplinary Appraisal Council.

Regarding compensation and site clearance, localities have basically completed the approach points, air defense targets, connecting roads and relocating 220 kV lines affected by the clearance. Currently, there are 2 records in Ham Thuan Bac district affected by the power line corridor and the construction at a religious facility affected by the clearance. Ham Thuan Bac District People's Committee is continuing to mobilize the above-mentioned relevant units to hand over the site. At the same time, develop a construction protection plan when the construction unit plans to pull the ropes.

Mot khu vuc ben trong du an. Anh: Duy Tuan
An area inside the project. Photo: Duy Tuan

Chairman of Binh Thuan Provincial People's Committee Do Huu Huy requested the Department of Construction to coordinate with relevant units to prepare the Pre-feasibility Study Report for the Phan Thiet Airport project, civil aviation item under a BOT contract to advise the Provincial People's Committee to submit to the Prime Minister for consideration and approval of the project investment policy adjustment.

At the same time, continue to implement related work to speed up the project implementation progress, striving to start construction in October 2025. The Chairman of the Provincial People's Committee also requested relevant localities to focus on compensation and site clearance for the remaining items, to be completed in March 2025.

Duy Tuấn
TIN LIÊN QUAN

Preventing encroachment and illegal construction in an urban area project of nearly 220 hectares

|

Binh Thuan - Many notice boards have been posted to prevent encroachment and illegal construction in the area of the new Ham Tien - Mui Ne commercial and service urban area project.

Appearance of the 118 billion VND road to Phan Thiet airport just opened to traffic

|

Binh Thuan - The Phan Thiet airport access road project (phase 2) has been opened to traffic; vehicles are moving smoothly after nearly 1 year of construction.

Phan Thiet airport civil works expected to start in 2025

|

Binh Thuan - The progress of the Phan Thiet Airport project, civil project under BOT contract form, is waiting for the Prime Minister to review and approve the investment policy.

Strong earthquake in Tonga just a few days after Myanmar earthquake

|

A 7.1-magnitude earthquake near Tonga prompted an initial Tsunami warning but was later lifted.

The Cong Viettel beat Hoang Anh Gia Lai to advance to the semi-finals of the National Cup

|

On the evening of March 30, The Cong Viettel defeated Hoang Anh Gia Lai with a score of 2-0 to win a ticket to the semi-finals of the 2024-2025 National Cup.

Updated gold price at the end of session 30.3: Profit despite surfing

|

Updated gold price at the end of the session on March 30: The difference between buying and selling is at a high level, investors still make a profit even if investing in the short term.

The army and police set out to support overcoming the consequences of the earthquake

|

The delegation of officers and soldiers of the Ministry of National Defense and the Ministry of Public Security have set out to support Myanmar in overcoming the consequences of the earthquake.

Waiting for the end of living with wastewater in industrial parks

|

Quang Tri - The lives of people living next to industrial parks have been disrupted by wastewater. Meanwhile, the wastewater treatment plant has not yet come into operation

Preventing encroachment and illegal construction in an urban area project of nearly 220 hectares

Duy Tuấn |

Binh Thuan - Many notice boards have been posted to prevent encroachment and illegal construction in the area of the new Ham Tien - Mui Ne commercial and service urban area project.

Appearance of the 118 billion VND road to Phan Thiet airport just opened to traffic

DUY TUẤN |

Binh Thuan - The Phan Thiet airport access road project (phase 2) has been opened to traffic; vehicles are moving smoothly after nearly 1 year of construction.

Phan Thiet airport civil works expected to start in 2025

Duy Tuấn |

Binh Thuan - The progress of the Phan Thiet Airport project, civil project under BOT contract form, is waiting for the Prime Minister to review and approve the investment policy.