Are clearing land to open a 50m wide central road in Hanoi

HỮU CHÁNH |

Hanoi - Some sections are being cleared to construct the Ring Road 1 project, Hoang Cau - Voi Phuc section, with an investment capital of more than VND 7,200 billion after many years of delay.

According to the reporter of Lao Dong Newspaper on March 15, many houses at the Lang Ha - De La Thanh intersection (Dong Da district, Hanoi) are being demolished by the construction unit, handing over the site for the construction of the Ring Road 1 project, Hoang Cau - Voi Phuc section.

This is a good sign after many years of stagnation in the Hoang Cau - Voi Phuc section of the Ring Road 1 construction project due to many difficulties and problems.

The project was approved by the Government at the end of 2017 with a length of 2.2km. The starting point is at Hoang Cau intersection (Dong Da district), the end point is at Voi Phuc intersection (Ba Dinh district).

The investment level of phase 1 of the Ring Road 1 project, Hoang Cau - Voi Phuc section, is more than VND 7,211 billion. Of which, the construction cost is 627 billion VND; site clearance (GPMB) is more than 5,818 billion VND and some other costs from the city budget.

The Hanoi Civil Works Construction Investment Project Management Board (investor) said that to implement the project, more than 2,000 households in Ba Dinh and Dong Da districts must be cleared of land.

According to the plan, the project is expected to be completed by the end of 2024. However, the site clearance process encountered many difficulties due to people's lack of coordination, failure to confirm land origin, and failure to confirm boundaries. Some households have even received money but have not yet handed over the site, leading to project delays.

Regarding policy mechanisms, problems related to the 2014 Land Law have just been resolved, but now problems arise under the 2024 Land Law.

The Project Management Board said that it has coordinated with the People's Committees of Dong Da District and Ba Dinh District to report to the city and propose solutions.

Up to now, the appraisal of compensation and resettlement plans has made much progress. It is expected that in the first quarter of 2025, Ba Dinh District will complete site clearance and in the second quarter of 2025, Dong Da District will also complete site clearance.

The project investor said that he has directed contractors to always be ready, with the site to start construction immediately. If the site clearance work is as planned, the project will be completed in 2025.

When completed, the road will have a cross-section of 50m, contributing to reducing traffic congestion on La Thanh Street, while enhancing connectivity with the central area of the capital, making traffic more convenient.

Currently, the end point of the project is the Voi Phuc intersection, which has been completed and is ready to connect with the Hoang Cau - Voi Phuc route in the future.

tai nut giao Lang Ha - Giang Vo - La Thanh, may xuc va cong nhan dang thi cong pha do mot so cong trinh, nha dan nam trong dien giai toa, moi duoc ban giao lai cho don vi thi cong.
The Hoang Cau - Voi Phuc route (Dong Da and Ba Dinh districts, Hanoi) has shown signs of demolition and clearance after many years of inactivity. Photo: Huu Chanh
Hon 2 tuan qua, nhieu can nha tai nut giao Lang Ha duoc don vi thi cong pha do, som ban giao mat bang de thi cong du an.
Many houses at Lang Ha intersection were demolished by the construction unit, and the site was handed over soon for project construction. Photo: Huu Chanh
a
A house at the De La Thanh - Giang Vo intersection will be demolished to construct the Hoang Cau - Voi Phuc Ring Road 1 project. Photo: Huu Chanh
z
Some houses outside the project area have been renovated and repaired. Photo: Huu Chanh
Mot cua hang tai nut giao Giang Vo - De La Thanh tra mat bang, thong bao chuyen den dia diem moi. Anh: Huu Chanh
The store at the Giang Vo - De La Thanh intersection has returned the premises and announced a move to a new location. Photo: Huu Chanh
z
To implement the project, it will be necessary to reclaim land from more than 2,000 households in Dong Da and Ba Dinh districts. Photo: Huu Chanh
z
De La Thanh Street has not been expanded for many years, causing constant congestion. Photo: Huu Chanh
z
In the photo is the Voi Phuc intersection, the end point of the project. According to the plan, Ring Road 1 Hoang Cau - Voi Phuc will be completed in 2025. Photo: Huu Chanh

HỮU CHÁNH
TIN LIÊN QUAN

People live with danger waiting for a road opening project in Hanoi

|

Hanoi - People have been crowded with heavy trucks on Provincial Road 70 for many years, while the project was opened in 2020 but has not been completed yet.

Hanoi to enforce land acquisition for road over 1.5km long

|

Hanoi - The People's Committee of Thuong Tin district will enforce land recovery for households that have not complied with the handover of the site to complete the construction of the new route of Provincial Road 427.

Another delay in handing over the site for the Tam Trinh road expansion project

|

Hanoi - Hoang Mai District has postponed the site clearance progress of the Tam Trinh road expansion project until April 2025 due to some remaining difficulties and problems waiting to be resolved.

Newcastle wins first major title in 70 years

|

Newcastle ended a 70-year wait for a major title when defeating Liverpool in the English League Cup final.

Russia is taking the last Ukrainian soldier out of Kursk

|

Russia has stepped up attacks to push the last Ukrainian soldiers out of Kursk Oblast after seven months of Kiev's encroachment on the region.

Hunting for pink laurel wreaths in Soc Trang in the blooming season

|

Soc Trang - The pink flute flower road is becoming an attractive destination every March, attracting a large number of people to admire and take photos.

Gold price update on the morning of March 17: Experts predict a new peak

|

Gold price update on the morning of March 17: remaining at a high level. Experts predict that the precious metal could set a new peak as the market awaits the Fed's interest rate decision.

Mercedes driver hits a series of vehicles waiting for red lights when having alcohol concentration

|

HCMC - On the evening of March 16, the authorities determined that the female Mercedes driver who caused the series of accidents at Thu Duc intersection had alcohol concentration on her body.

People live with danger waiting for a road opening project in Hanoi

HỮU CHÁNH |

Hanoi - People have been crowded with heavy trucks on Provincial Road 70 for many years, while the project was opened in 2020 but has not been completed yet.

Hanoi to enforce land acquisition for road over 1.5km long

HỮU CHÁNH |

Hanoi - The People's Committee of Thuong Tin district will enforce land recovery for households that have not complied with the handover of the site to complete the construction of the new route of Provincial Road 427.

Another delay in handing over the site for the Tam Trinh road expansion project

HỮU CHÁNH |

Hanoi - Hoang Mai District has postponed the site clearance progress of the Tam Trinh road expansion project until April 2025 due to some remaining difficulties and problems waiting to be resolved.