Land clearance problems slow down the progress of Van Thanh bridge in Phan Thiet

Duy Tuấn |

Binh Thuan - After more than 2 years of construction, the progress of the Van Thanh bridge project has only reached about 51% of the contract volume due to land clearance problems.

The Van Thanh Bridge project in Phan Thiet city with a total investment of about 225 billion VND, started in January 2023 and is expected to be completed by the end of December 2024. However, the construction progress to date has only reached about 51% of the contract volume.

According to the design, Van Thanh Bridge is 714m long, including 6 spans, 295m long approach road, 27m wide roadbed, 15m road surface, and 6m sidewalks on each side.

Toan canh cong truong thi cong cau Van Thanh. Anh: Duy Tuan
Overview of the construction site of the Van Thanh bridge project. Photo: Duy Tuan

According to records at the construction site, there are still machinery and construction workers. Currently, the contractor is constructing underwater items near the shore and is still having difficulties in compensation and site clearance. The Phan Thiet City Land Fund Development Center coordinated with relevant units to mobilize the handover of the site in advance of about 10,000m2.

May moc co gioi tai cong truong. Anh: Duy Tuan
Mechanical machinery at the construction site. Photo: Duy Tuan

The implementation of construction at the construction site is facing difficulties due to the need to adjust construction methods to suit actual conditions.

Currently, the Management Board of the Traffic Construction Investment Project of Binh Thuan province is determined, urging the construction unit to speed up the progress to ensure completion according to the requirements.

Tru cau da thi cong. Anh: Duy Tuan
The bridge piers have been constructed according to schedule. Photo: Duy Tuan

The locality also focuses on coordinating to resolve problems related to compensation and site clearance.

Cong nhan thi cong tai cong trinh. Anh: Duy Tuan
Workers at the construction site. Photo: Duy Tuan

The goal of the Van Thanh Bridge Project, Phan Thiet City is to serve the travel needs and exchange goods between Van Thanh residential area and Phan Thiet city center; gradually complete traffic infrastructure, urban beautification, meet the development requirements of a type II urban area and strengthen security and national defense in the locality.

Duy Tuấn
TIN LIÊN QUAN

Speeding up the progress of the Phan Thiet Airport project

|

Binh Thuan speeds up the implementation of the Phan Thiet Airport project, a civil aviation project, striving to start construction in October 2025.

Hanoi builds 3 underpasses for Tu Lien bridge project

|

Hanoi - The implementation of the Tu Lien bridge project will build 3 underpasses (including 2 closed tunnels about 0.16km and 0.1km long; 1 open tunnel about 1.05km long).

Progress of the largest 1,500 billion VND cable-stayed bridge project in Bac Giang province

|

Bac Giang - It is expected that the approach road to Dong Viet bridge will be completed before April 30 this year to connect with Hai Duong province.

The story of ViruSs dating 3 girls, all watching Kung Fu Panda 4

|

The scandal of ViruSs and ex-lover relationships covered social media platforms, causing streamer to be widely criticized.

Special Jelly harvest season for Do Son fishermen, Hai Phong

|

Hai Phong - This year's jellyfish season for Do Son fishermen is special as red jellyfish have appeared a lot after more than 2 decades of almost disappearance.

EU upset because it has been pushed out of Nord Stream negotiations

|

The EU was upset to discover Russia and the US secretly discussing the possibility of restoring Nord Stream without the participation of the European Union.

Approving the latest selling price of clean water for daily use in Hanoi

|

Hanoi - The City People's Committee has just approved the selling price of clean water for daily use of Da River Clean Water Investment Joint Stock Company applicable in the city.

Paying voluntary social insurance for 15 years is entitled to pension

|

From July 1, 2025, employees who only need to participate in voluntary social insurance for 15 years will receive a pension. This policy is supported by many workers.

Speeding up the progress of the Phan Thiet Airport project

Duy Tuấn |

Binh Thuan speeds up the implementation of the Phan Thiet Airport project, a civil aviation project, striving to start construction in October 2025.

Hanoi builds 3 underpasses for Tu Lien bridge project

KHÁNH AN |

Hanoi - The implementation of the Tu Lien bridge project will build 3 underpasses (including 2 closed tunnels about 0.16km and 0.1km long; 1 open tunnel about 1.05km long).

Progress of the largest 1,500 billion VND cable-stayed bridge project in Bac Giang province

Vân Trường |

Bac Giang - It is expected that the approach road to Dong Viet bridge will be completed before April 30 this year to connect with Hai Duong province.