Repairing the Lo Te - Rach Soi route, but how many years can it be guaranteed?

Lê Thanh Phong |

My Thuan Project Management Board informed that the work of patching and repairing the Lo Te - Rach Soi route has been completed, ensuring smooth, safe and stable circulation on the route.

Lao Dong Newspaper has a series of articles reflecting that the Lo Te - Rach Soi Expressway, with a total investment of 6,350 billion VND, has many damaged sections. Lao Dong reporters went to the field and recorded a series of potholes, potholes, deep water holes, and gravel scattered all over the road surface of this route.

The road is too bad, it is difficult for vehicles to move, it is difficult for passengers, and there is a potential risk of traffic accidents. Drivers and passengers complained, some said this was "the worst route in the West".

The expressway invested 6,350 billion VND, was only completed and put into operation for 3 years but is seriously damaged, which is difficult to accept. In October 2023, many damaged sections of this route appeared and were repaired by the construction unit.

Highways that are repaired in the form of patching and patching, the road surface is uneven, unsafe, unstable, and unsustainable. Therefore, just a few months later, many points on the route peeled back, subsided, forming many deep holes, potholes, and elephant holes.

This time it is not a patch, but an upgrade investment project with a total investment of about 750 billion VND, starting point after the intersection between Vam Cong bridge and National Highway 91 bypass in Vinh Thanh district, Can Tho city, The end point connects to the Rach Gia bypass in the southern coastal corridor, Kien Giang province. The investment scale includes asphalt concrete pavement and completion of the traffic safety system in compliance with national technical regulations.

I would like to ask, when building this expressway with a total investment of 6,350 billion VND, did it comply with the National Technical Regulations? If so, why was it damaged after only 3 years and had to be repaired many times?

My Thuan Project Management Board said that according to the signed contract, the completion time of the investment project to upgrade the road surface of Lo Te - Rach Soi route is the end of October 2025. So in more than a year, people will have high-quality expressways for convenient and safe travel.

People in the West have been waiting for the expressway for a long time, another year won't matter. What people are concerned about is this investment in upgrading, will the expressway be of good quality and stable, or will it be damaged again after a while like before.

More than six thousand billion dong was spent on road construction, but every time it was damaged, it had to be repaired, costing more money, and people were very sorry.

Lê Thanh Phong
TIN LIÊN QUAN

Tuyến Lộ Tẻ - Rạch Sỏi đã thi công đại trà hơn 1.000m

Tạ Quang - Yến Phương |

Sau giai đoạn thi công thử nghiệm, đến nay, tuyến Lộ Tẻ - Rạch Sỏi đã bắt đầu thi công đại trà được hơn 1.000m.

Cao tốc trục ngang đặt mục tiêu đạt 20% tiến độ cuối 2024

Tạ Quang |

Cần Thơ - Từ khi có cát, cao tốc Châu Đốc - Cần Thơ - Sóc Trăng đoạn Cần Thơ đã tăng các mũi thi công đẩy nhanh tiến độ, phấn đấu hết 2024 phải đạt 20% tiến độ.

Tiến độ các dự án cao tốc, vành đai kết nối vùng Đông Nam Bộ

MINH QUÂN |

Cao tốc Biên Hòa - Vũng Tàu, Bến Lức - Long Thành, TPHCM - Chơn Thành, Vành đai 3, 4 đang và sắp triển khai giúp tăng kết nối vùng Đông Nam Bộ.

Xe tải bốc cháy ngùn ngụt trên cao tốc Vĩnh Hảo - Phan Thiết

Duy Tuấn |

Bình Thuận - Xe tải đang lưu thông thì bốc cháy ngùn ngụt trên cao tốc Vĩnh Hảo - Phan Thiết.

Tin 20h: Yên Bái kiểm tra nhà hàng "chặt chém" đoàn từ thiện

Nhóm PV |

Tin 20h ngày 19.9: Bà Nguyễn Phương Hằng được ra tù vào hôm nay; Yên Bái kiểm tra nhà hàng bị tố chặt chém đoàn từ thiện...

Phía Miss Universe nói về thông tin Kỳ Duyên chưa tốt nghiệp

Huyền Chi |

Thông tin Hoa hậu Kỳ Duyên chưa tốt nghiệp Trường Đại học Ngoại Thương gây xôn xao mạng xã hội.

Thể Công Tân Cảng bảo vệ thành công chức vô địch giải bóng chuyền U23 Quốc gia 2024

Nhóm PV |

U23 Thể Công Tân Cảng thắng U23 Ninh Bình 3-1 tại chung kết giải bóng chuyền U23 quốc gia vào tối 19.9.

Chậu hoa giấy trên phố đi bộ ở Đà Nẵng đồng loạt "nằm" tránh bão

Nguyễn Linh |

UBND quận Hải Châu, TP Đà Nẵng cho biết đã chủ động đặt nằm các chậu hoa giấy tại phố đi bộ Bạch Đằng để tránh thiệt hại bởi ảnh hưởng của cơn bão số 4.

Highway Axis Cross-Country Sets Target to Achieve 20% Progress by End of 2024

Tạ Quang |

Can Tho - Since there is sand, highway from Châu Đốc to Can Tho to Sóc Trăng section in Can Tho has increased construction points to speed up the progress, striving to achieve 20% progress by 2024.

Progress of High-Speed Highway and Ring Road projects connecting the southeastern region of Vietnam

MINH QUÂN |

Highway Biên Hòa - Vũng Tàu, Bến Lức - Long Thành, Ho Chi Minh City - Chơn Thành, Ring Road 3, 4 is currently and will soon be implemented to increase connectivity in the Southeastern region of Vietnam.