Ho Chi Minh City has a 5-year plan for Metro Line 2, don't lose your promise any more!

Lê Thanh Phong |

Metro Line 2 (Ben Thanh - Tham Luong) of Ho Chi Minh City will start construction on January 15, 2026, applying many specific mechanisms to speed up progress, expected to be completed in 2030.

Ho Chi Minh City residents have been waiting for metro line 2 for a long time, but they only listen to the station and read the newspaper, unfortunately they are all missed reports. People do not have much expectation for the completion time of Metro Line 2 project.

Metro No. 2 project was first approved in October 2010 with a total investment of more than VND 26,000 billion. By 2019, the total investment capital was adjusted to more than VND47,800 billion (about 2.09 billion USD at that time).

But since then, many plans to start Metro Line 2 have failed.

Previously, Metro Line 1 (Ben Thanh - Suoi Tien) with a length of nearly 20km started construction in August 2012, expected to be completed and put into operation in 2018, but will not be operational until the end of 2024. Thus, it will take 12 years from the time the project is started to the finish line.

The unfortunate information that has happened shows that the implementation of Metro Line 2 project requires new breakthroughs to prevent the old story from repeating itself.

The challenging problem for the Ho Chi Minh City government is that Metro Line 2 must be completed within 5 years.

This is also the basis for people to believe in the goal of completing 355km of metro by 2035.

Metro No. 2 is over 11km long, if it reaches the finish line on time, it will only account for a very small part of Ho Chi Minh City's metro system construction plan.

After Metro Line 1 was put into operation, people saw the benefits of using modern means of transport, so they are looking forward to having many other metro lines.

The completion of Metro Line 2 project is to meet the people's expectations, and affirms that from now on, the city government has promised to do it.

Reiterate, speaking at the group discussion within the framework of the 1st Ho Chi Minh City Party Congress, held on October 14, Chairman of the City People's Committee Nguyen Van Duoc pledged that when the belt, expressway and metro network is completed, Ho Chi Minh City will basically have no traffic jams by 2035.

Metro No. 2 project is a route in the expressway network of Ho Chi Minh City. If not completed on schedule, it will not ensure the commitment of Chairman Nguyen Van Duoc to reduce traffic congestion.

Metro No. 2 with 11km not completed on schedule, it is difficult to say that 355km will be completed in the next 10 years.

Lê Thanh Phong
RELATED NEWS

Construction of An Phu, My Thuy intersections, Metro No. 2 HCMC causes damage to roads, traffic jams

|

HCMC - The construction of An Phu intersection, My Thuy intersection, and relocation of Metro 2 infrastructure has caused many degraded and damaged roads, causing traffic congestion.

HCMC finalizes the groundbreaking of Metro Line 2 on January 15, 2026

|

Ho Chi Minh City finalizes the groundbreaking of Metro Line 2 (Ben Thanh - Tham Luong) on January 15, 2026, applying many specific mechanisms to speed up progress.

The Northwest gateway of Ho Chi Minh City is often congested because Metro No. 2 lots occupy the road

|

HCMC - The Northwest gateway of HCMC has been often congested in recent days because the Metro Line 2 lot is located right at the Truong Chinh - Cong Hoa intersection.

Hanoi and Ho Chi Minh City are special provincial-level administrative units

|

The Government has just issued Decree 307/2025/ND-CP regulating the classification of administrative units.

Updated gold price at the end of the session on November 28: Domestic gold increased sharply

|

Updated gold price at the end of the session on November 28: SJC gold bars and plain round gold rings increased in price simultaneously.

Visit to Egypt to expand cooperation between Vietnam - Egypt Trade Union

|

At the invitation of the Egyptian Union of Trade Unions (ETUF), the Vietnam Trade Union Delegation visited and worked in Egypt from November 23 to 26.

HCMC sprints to build a new land price list to be applied from 2026

|

HCMC - Leaders of departments, branches and localities are responsible if there is a delay in developing and announcing the first land price list to be applied from January 1, 2026.

Surprisingly, Vietnamese people were elected as members of the US National Academy of Creative Arts

|

Good news and pride from the United States, when a Vietnamese professor becomes a member of the US National Academy of Inventors ( NAI).

Construction of An Phu, My Thuy intersections, Metro No. 2 HCMC causes damage to roads, traffic jams

MINH QUÂN |

HCMC - The construction of An Phu intersection, My Thuy intersection, and relocation of Metro 2 infrastructure has caused many degraded and damaged roads, causing traffic congestion.

HCMC finalizes the groundbreaking of Metro Line 2 on January 15, 2026

MINH QUÂN |

Ho Chi Minh City finalizes the groundbreaking of Metro Line 2 (Ben Thanh - Tham Luong) on January 15, 2026, applying many specific mechanisms to speed up progress.

The Northwest gateway of Ho Chi Minh City is often congested because Metro No. 2 lots occupy the road

MINH QUÂN |

HCMC - The Northwest gateway of HCMC has been often congested in recent days because the Metro Line 2 lot is located right at the Truong Chinh - Cong Hoa intersection.