More 844,000m3 of soil and sand needed to build the Ho Chi Minh City Ring Road 3 project through Binh Duong

|

Binh Duong province needs 1.516 million m3 of soil and sand to construct the Ho Chi Minh City Ring Road 3 project. Currently, there are 672,000 m3, and an additional 844,000 m3 is needed.

HCMC finalizes the opening of a 47 km strategic road, 4 expressway lanes at the end of this year

|

HCMC - The Ring Road 3 section through HCMC is more than 47 km long, including 4 lanes for high-speed vehicles, and is expected to be technically open to traffic by the end of 2025.

Ho Chi Minh City Ring Road 3 still lacks sand for filling, affecting construction progress

|

The Ho Chi Minh City Ring Road 3 project - a key traffic route that plays a regional linkage role between Ho Chi Minh City and neighboring provinces is facing great difficulties in the supply of sand for filling, affecting the construction progress of the entire route.

76km road through Ho Chi Minh City and 3 provinces at risk of delay due to lack of sand

|

HCMC - The 76-km Ring Road 3 project through HCMC and three provinces is expected to open some sections this year but faces the risk of delays due to a lack of sand for filling.