Ho Chi Minh City Ring Road 3 still lacks sand for filling, affecting construction progress

MINH QUÂN |

The Ho Chi Minh City Ring Road 3 project - a key traffic route that plays a regional linkage role between Ho Chi Minh City and neighboring provinces is facing great difficulties in the supply of sand for filling, affecting the construction progress of the entire route.

Ho Chi Minh City Ring Road 3 is 76km long, passing through 4 localities including Ho Chi Minh City, Binh Duong, Dong Nai and Long An. The project started in mid-2023, with the goal of basically completing in 2025 and completing the entire project in 2026.

According to Mr. Luong Minh Phuc - Director of the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board), the section through Ho Chi Minh City is about 47km long, divided into 14 packages, including 10 main construction packages. To date, the total construction output has reached about 35% of the construction value.

To ensure progress, the Traffic Department has directed contractors and consulting units to review and update detailed construction progress according to each specific milestone. Accordingly, 14.7km of overpass in Thu Duc City is expected to be technically open to traffic before December 31, 2025. By April 30, 2026, 32.6km of the expressway section passing through Cu Chi, Hoc Mon, and Binh Chanh districts will be completed for technical traffic. It is expected that by June 30, 2026, the entire Ring Road 3 route through Ho Chi Minh City and the provinces will be put into operation.

However, one of the biggest challenges at present is the supply of filling materials, especially sand. Contractors have mobilized many sources of river sand from domestic mines, imported sand from Cambodia, and commercial sand from mines that the three localities of Vinh Long, Tien Giang and Ben Tre are committed to providing.

The total volume of sand remaining to be mobilized for the entire project is about 5.05 million cubic meters, of which in 2025 alone, 4.7 million cubic meters are needed and in 2026 it will be 0.35 million cubic meters. Up to now, Vinh Long, Tien Giang and Ben Tre provinces have licensed 10/13 mines (1 mine in Ben Tre, 2 mines in Tien Giang). The progress of sand mobilization to the construction site has not yet met construction requirements.

Mr. Luong Minh Phuc emphasized: In 2025, sand from the three provinces of Vinh Long, Tien Giang, and Ben Tre will play a key role in the project's progress. The remaining volume will have to be compensated from imported and domestic sand sources, but both are very scarce".

To remove obstacles, Mr. Luong Minh Phuc said that localities need to urgently complete licensing procedures for remaining mines, and at the same time consider increasing the exploitation capacity of existing mines to promptly supply materials for the project in accordance with the Government's direction.

MINH QUÂN
TIN LIÊN QUAN

Reasons for 3-storey houses leaning when building Ho Chi Minh City Ring Road 3

|

Binh Duong - The image of a "super thin" 3-storey house tilted attracted the attention of the people. This is a house affected during the construction of the Ho Chi Minh City Ring Road 3 project.

Lack of 6.3 million cubic meters of sand, Ho Chi Minh City Ring Road 3 is at risk of being behind schedule

|

The two sections of the Ho Chi Minh City Ring Road 3 project, over 21km long, are expected to open to traffic by the end of 2025, before the entire 76.34km route is completed on June 30, 2026. However, the construction progress is being hampered by a shortage of sand for embankment.

Image of the largest bridge on Ho Chi Minh City Ring Road 3 about to reach the finish line

|

Ho Chi Minh City - Nhon Trach Bridge, an important item on Ho Chi Minh City Ring Road 3, is about to close the final span on March 9 and is expected to open to traffic on April 30.

Mr. Trump declares he is about to reach a nuclear deal with Iran

|

US President Donald Trump said on May 15 that Washington is getting very close to a nuclear deal with Iran.

Vietnam issues notice of protest against China's ban on fishing in the East Sea

|

The Vietnamese Ministry of Foreign Affairs has interacted with the Chinese Embassy in Hanoi and also issued a document protesting China's ban on fishing in the East Sea.

Number of students who do not take the public 10th grade exam in Hanoi in 2025

|

Hanoi - The number of candidates expected to not take the public 10th grade exam in 2025 is not much different from last year.

Thai Prime Minister begins official visit to Vietnam

|

At noon on May 15, Thai Prime Minister Paetongtarn Shinawatra arrived in Hanoi, starting an official visit to Vietnam.

Reasons for 3-storey houses leaning when building Ho Chi Minh City Ring Road 3

ĐÌNH TRỌNG |

Binh Duong - The image of a "super thin" 3-storey house tilted attracted the attention of the people. This is a house affected during the construction of the Ho Chi Minh City Ring Road 3 project.

Lack of 6.3 million cubic meters of sand, Ho Chi Minh City Ring Road 3 is at risk of being behind schedule

MINH QUÂN |

The two sections of the Ho Chi Minh City Ring Road 3 project, over 21km long, are expected to open to traffic by the end of 2025, before the entire 76.34km route is completed on June 30, 2026. However, the construction progress is being hampered by a shortage of sand for embankment.

Image of the largest bridge on Ho Chi Minh City Ring Road 3 about to reach the finish line

Anh Tú |

Ho Chi Minh City - Nhon Trach Bridge, an important item on Ho Chi Minh City Ring Road 3, is about to close the final span on March 9 and is expected to open to traffic on April 30.