Sand shortage threatens the progress of Ho Chi Minh City Ring Road 3

MINH QUÂN |

The Ho Chi Minh City Ring Road 3 project - a national key transport infrastructure project - is facing the risk of being behind schedule due to a shortage of sand for embankment, especially in the western packages passing through Cu Chi, Hoc Mon and Binh Chanh districts.

Many construction sections are sluggish due to lack of sand

Recorded at the Ring Road 3 construction site in Cu Chi, Hoc Mon and Binh Chanh districts, the construction atmosphere is quite quiet. Although some sections have been formed, the progress of roadbed and technical structure construction is still very slow. The main reason is the lack of sand to treat weak soil.

The Ho Chi Minh City Ring Road 3 project has a total length of more than 76km, passing through Ho Chi Minh City, Binh Duong, Dong Nai and Long An, with a total investment of nearly VND 75,400 billion. The section through Ho Chi Minh City alone is more than 47km long.

According to the latest request of the Government and the People's Committee of Ho Chi Minh City, the 14.7km section of the overpass through Thu Duc City must be completed for technical traffic in 2025 along with the more than 32km section in the West.

As of the end of May 2025, the construction volume of Ring Road 3 through Ho Chi Minh City has only reached nearly 40%. Meanwhile, the demand for sand for embankment in Ho Chi Minh City is estimated at about 6.6 million cubic meters, but so far only about 2.15 million cubic meters have been mobilized. In 2025 alone, the construction site needs about 3.75 million cubic meters of sand.

According to Mr. Luong Minh Phuc - Director of the Management Board of Investment Project Construction of Ho Chi Minh City Transport works, although the three Western provinces including Vinh Long, Tien Giang and Ben Tre have licensed to exploit 14 sand mines for the project, the actual supply progress is slower than the original commitment. This makes the construction progress of western bidding packages significantly affected.

To bring sand from mines in the West to the construction site in Ho Chi Minh City, barges have to go through 8 waterway control stations, border guards and interdisciplinary groups. These stations basically all carry out similar inspection procedures, from material origin records, invoices to vehicle loads. The repeated inspection has caused significant delays.

In order to remove obstacles, the Ho Chi Minh City People's Committee has proposed that relevant units coordinate to establish a separate "green channel" for sand transportation activities to serve the Ring Road 3 project. Each barge is only inspected once per trip, and the inspection results at the starting station will be recognized by the remaining stations.

The city also recommends minimizing repeat inspections by receiving in advance long-term valuable records such as vehicle registration. The list of barges, transportation schedules and related documents will be proactively sent to the authorities in advance for coordination in inspection and supervision in a synchronous and effective manner.

No delay

The remaining workload of the Ring Road 3 project is very large, while the time is less than 8 months. However, according to Mr. Luong Minh Phuc, despite facing many difficulties, the Project Management Board is still steadfast in its goal of completing the project on schedule - from ensuring materials, changing construction plans to speeding up handling weak soil.

Mr. Phuc said that the unit has proposed increasing the exploitation capacity at sand mines in the West to 50%. At the same time, contractors are also proactive in finding sources of commercial sand and importing sand from Cambodia to promptly supplement.

Technically, a series of new solutions are being implemented simultaneously to shorten the time to treat weak ground. The construction units have increased the wick density, adjusting the height of the floor and applying vacuum technology, helping to shorten the processing time from 10 to 12 months to 5-6 months. Some routes, if the monitor meets the requirements, can reach the finishening sooner than expected.

In 5 Western packages with a total length of 32.5km, new technical solutions have been deployed over 25% of the route length. The measure of using cement stakes to treat weak soil is also considered, but due to high costs, it is only applied in areas that are really necessary.

MINH QUÂN
TIN LIÊN QUAN

Nearly 100% of site clearance, Binh Duong speeds up construction of Ho Chi Minh City Ring Road 3

|

Binh Duong - The site clearance work is almost completed, Binh Duong province is speeding up the construction of the Ho Chi Minh City Ring Road 3 project.

Overview of the site for the most complicated intersection construction of the Ho Chi Minh City Ring Road 3 project

|

Binh Duong - The construction site of the Tan Van intersection project of the Ho Chi Minh City Ring Road 3 has been cleared. Units are speeding up the construction progress.

Ho Chi Minh City Ring Road 3 still lacks sand for filling, affecting construction progress

|

The Ho Chi Minh City Ring Road 3 project - a key traffic route that plays a regional linkage role between Ho Chi Minh City and neighboring provinces is facing great difficulties in the supply of sand for filling, affecting the construction progress of the entire route.

Resigned officials and civil servants in Ho Chi Minh City have the opportunity to borrow 300 million VND to start a business

|

HCMC - Cadres, civil servants, public employees and non-professional workers who quit their jobs due to streamlining can get a preferential loan of up to 300 million VND to start a business.

US lawmakers want to control US President's military actions towards Iran

|

While Democrats opposed the new US airstrike on Iran, Republicans said it was a necessary move.

Thanks from the Vietnam Journalists Association

|

Lao Dong Newspaper respectfully introduces the content of the gratitude of the Vietnam Journalists Association on the occasion of the 100th anniversary of the Vietnam Revolutionary Press Day.

Minister of Home Affairs Pham Thi Thanh Tra receives new duties

|

Ms. Pham Thi Thanh Tra - Minister of Home Affairs received a new assignment as Head of the Central gratitude Fund Management Board.

New regulations on spending regimes for sports tournaments are coming

|

Joint Circular No. 200 on financial spending for sports competitions has no longer been suitable for practice after 14 years of application.

Nearly 100% of site clearance, Binh Duong speeds up construction of Ho Chi Minh City Ring Road 3

ĐÌNH TRỌNG |

Binh Duong - The site clearance work is almost completed, Binh Duong province is speeding up the construction of the Ho Chi Minh City Ring Road 3 project.

Overview of the site for the most complicated intersection construction of the Ho Chi Minh City Ring Road 3 project

ĐÌNH TRỌNG |

Binh Duong - The construction site of the Tan Van intersection project of the Ho Chi Minh City Ring Road 3 has been cleared. Units are speeding up the construction progress.

Ho Chi Minh City Ring Road 3 still lacks sand for filling, affecting construction progress

MINH QUÂN |

The Ho Chi Minh City Ring Road 3 project - a key traffic route that plays a regional linkage role between Ho Chi Minh City and neighboring provinces is facing great difficulties in the supply of sand for filling, affecting the construction progress of the entire route.