Complete 5 component projects of the North - South expressway in Ha Tinh, Quang Tri in 2025

PHẠM ĐÔNG |

The Deputy Prime Minister requested ministries, branches and localities to accelerate the implementation of 5 component projects of the North - South expressway in Ha Tinh and Quang Tri provinces.

On September 3, the Government Office issued Official Letter No. 8190/VPCP-CN conveying the direction of Deputy Prime Minister Nguyen Chi Dung on promptly completing the remaining items of the North-South expressway component project in the East through Ha Tinh and Quang Tri.

Official dispatch No. 8190/VPCP-CN stated: According to the report of the Ministry of Construction, up to now, all 5 component projects of Bai Vot - Ham Nghi, Ham Nghi - Vung Ang, Vung Ang - Bung, Bung - Van Ninh, Van Ninh - Cam Lo sections in the two provinces of Ha Tinh and Quang Tri under the North - South expressway construction project in the Eastern phase of 2021-2025 have basically completed the main expressway.

Of which, 259.2 km of expressway has been opened to traffic and put into operation, meeting the Government's requirements (the Ham Nghi - Vung Ang project alone has been completely completed).

To complete the remaining items of component projects, Deputy Prime Minister Nguyen Chi Dung requested the People's Committee of Quang Tri province to mobilize the entire political system to resolutely direct the completion of site clearance for the remaining areas (reservoir roads, rest stops...) of the 3 component projects Vung Ang - Bung, Bung - Van Ninh, Van Ninh - Cam Lo before September 15.

The People's Committee of Quang Tri province has solutions to protect construction (at some locations where people obstruct construction) so that contractors can organize the completion of projects according to the required schedule.

The Ministry of Construction urgently directs investors and contractors to focus all resources, continue to promote the spirit of "overcoming the sun to overcome the rain, not losing to storms and winds", "working day, working night, working extra days off", "eating and sleeping quickly during holidays, during Tet", "working 3 shifts, 4 teams"... to construct, striving to complete the 2 component projects of Vung Ang - Bung, Bung - Van Ninh in September 2025, completing the Van Ninh - Cam Lo component project in October 2025.

At the same time, the Ministry of Construction urgently directs investors and the Vietnam Road Administration to actively speed up the implementation of traffic control and operation monitoring items and rest stop items, striving to complete before December 31, 2025.

The 5 expressway component projects are 259.16 km long, with a total investment of 49,206 billion VND, in Ha Tinh and Quang Tri provinces.

In which, the Bai Vot - Ham Nghi section (35.28km long), Ham Nghi - Vung Ang section (54.2km long), Vung Ang - Bung section (55.34km long), Bung - Van Ninh section (48.84km long), Van Ninh - Cam Lo section (65.5km long) of the North - South axis expressway in the East has an investment scale of 4 lanes, roadbed width of 17m.

PHẠM ĐÔNG
RELATED NEWS

Agree to expand the entire North-South expressway in the East under the PPP method

|

The Deputy Prime Minister agreed to the plan to expand the entire North-South expressway in the East; requested that before August 4, the Prime Minister be informed of the expansion plan.

20 inspections by the Prime Minister and Deputy Prime Minister to accelerate the progress of 3,000 km of expressway

|

The Prime Minister requested to continue accelerating, making a breakthrough to strive to have 2,476 km of expressway by August 19 and exceed the target of 3,000 km of expressway by the end of 2025.

Racing against time, resolutely completing the target of 3,000km of highway

|

The Prime Minister emphasized the spirit of racing against time, only discussing work, not retreating, and resolutely completing the goal of having at least 3,000km of expressway by the end of 2025.

Ukrainian President publicly abandons NATO membership goal for first time

|

Ukrainian President Volodymyr Zelensky said Kiev had accepted giving up its ambition to join NATO to find a way out of the conflict with Russia.

Nguyen Thi Thanh Phuc is exhausted, must give up in the 33rd SEA Games walking event

|

On the evening of December 14, Nguyen Thi Thanh Phuc was forced to give up the women's walking event at the 33rd SEA Games due to a recurring and exhausted injury.

Workers in Quang Ngai worry when the arranging unit still owes billions in wages

|

Quang Ngai - The Transport Technical Training Center - is operating stably but is worried if the project to reorganize the apparatus is implemented.

The beach party suddenly involved a tragic shooting incident, killing 10 people

|

The two were detained after reports of a shooting that left many people dead or injured at Bondi Beach, Sydney, on December 14.

My Tien burst into tears after winning the silver medal, the Vietnamese sports delegation took part

|

The leaders of the Vietnamese sports delegation worked with the Water Sports Association after the incident of swimmer Vo Thi My Tien burst into tears on the podium to receive the 33rd SEA Games medal.

Agree to expand the entire North-South expressway in the East under the PPP method

PHẠM ĐÔNG |

The Deputy Prime Minister agreed to the plan to expand the entire North-South expressway in the East; requested that before August 4, the Prime Minister be informed of the expansion plan.

20 inspections by the Prime Minister and Deputy Prime Minister to accelerate the progress of 3,000 km of expressway

PHẠM ĐÔNG |

The Prime Minister requested to continue accelerating, making a breakthrough to strive to have 2,476 km of expressway by August 19 and exceed the target of 3,000 km of expressway by the end of 2025.

Racing against time, resolutely completing the target of 3,000km of highway

PHẠM ĐÔNG |

The Prime Minister emphasized the spirit of racing against time, only discussing work, not retreating, and resolutely completing the goal of having at least 3,000km of expressway by the end of 2025.