Banks do not approve loans for Bach Mai Hospital, Viet Duc facility 2 project

PHẠM ĐÔNG |

The Deputy Minister of Health said that contractors are facing difficulties when banks do not approve loans for the Bach Mai and Viet Duc Hospitals project, facility 2.

On the afternoon of May 4, at the regular government press conference in April 2026, Deputy Minister of Health Le Duc Luan informed the press about the progress of putting Bach Mai Hospital and Viet Duc Hospital facility 2 into operation.

Bach Mai Hospital facility 2 project has a total investment of 4,990 billion VND, a total land area of 20.07 ha, a total construction floor area of 118,941m2. Viet Duc Hospital facility 2 project has a total investment of 4,968 billion VND, a total land area of 21.44 ha, a total floor area of 117,714 m2.

According to the Deputy Minister of Health, implementing the direction of the Prime Minister, the Ministry of Health has been and is focusing on directing the Project Management Board, investors, contractors and related units, with the goal of striving to put both Bach Mai Hospital and Viet Duc Hospital facility 2 into operation in the second quarter of 2026.

Deputy Minister Le Duc Luan said that currently, in the process of implementation, there are still some difficulties and major obstacles, directly affecting the project completion progress such as: construction of fire prevention and fighting systems; construction of wastewater and waste treatment systems to serve the issuance of environmental permits.

In addition, contractors are facing financial difficulties when banks do not approve loans for the facility 2 project of Bach Mai Hospital and Viet Duc Hospital.

Thứ trưởng Bộ Y tế Lê Đức Luận. Ảnh: VGP
Deputy Minister of Health Le Duc Luan. Photo: VGP

Providing more information, Deputy Minister Le Duc Luan said that to remove the above-mentioned difficulties and obstacles, the Ministry of Health is implementing many synchronous solutions.

The Ministry of Health has proactively coordinated and worked with the Ministry of Construction to remove difficulties and obstacles in the work of preparing and appraising bid estimates for bidding packages; as a basis for paying completed volumes to contractors.

The Ministry of Health continues to regularly grasp and promptly handle difficulties and obstacles under its authority; continue to coordinate with the Ministry of National Defense and the Ministry of Construction to direct contractors to focus resources on completing the main bidding packages of the project, especially fire prevention and fighting items.

The Ministry of Health has directed the investor to temporarily pay up to 90% of the value of the completed work volume to the contractor according to the provisions of Decree No. 37/2015/ND-CP. For arising work, the Ministry of Health has directed the investor to immediately advance 50% of the value to the construction contractor.

Previously, on April 10, at the group discussion session of the National Assembly on socio-economic issues, Minister of Health Dao Hong Lan said that the Bach Mai Hospital and Viet Duc Hospital facility 2 projects have completed the rough construction but cannot yet operate.

The Minister said that the backlog project has lasted for up to 10 years, in which violations have arisen right from the contract signing stage.

Minister Dao Hong Lan also further analyzed that although it has been working very actively, even throughout Tet, the project has not yet been put into operation. The reason is that when handling each specific project, especially the hospital project, many subsequent procedures still arise that need to be completed.

Regarding construction, the project has been basically completed, the facilities are very good, it can be said that it is no different from a 5-star hotel, spacious, clean and beautiful. However, to achieve this result, it took 10 years and 10 months with many efforts of ministries, branches and contractors," Minister Dao Hong Lan informed.

PHẠM ĐÔNG
RELATED NEWS

Prime Minister directs deadline for operation of Bach Mai and Viet Duc Hospitals, facility 2

|

Prime Minister Le Minh Hung decisively directed the operation of Bach Mai and Viet Duc Hospitals, facility 2, in the second quarter of 2026.

Prime Minister chairs meeting on Viet Duc and Bach Mai Hospital project, facility 2

|

Prime Minister Le Minh Hung chairs the Government Standing Committee meeting with the Ministry of Health on 2 projects: Viet Duc Friendship Hospital and Bach Mai Hospital facility 2.

The State Bank continues to maintain the operating interest rates

|

The State Bank of Vietnam maintains the operating interest rates to create conditions for credit institutions to access capital sources.

Banks do not approve loans for Bach Mai Hospital, Viet Duc facility 2 project

|

The Deputy Minister of Health said that contractors are facing difficulties when banks do not approve loans for the Bach Mai and Viet Duc Hospitals project, facility 2.

Forecast of upcoming cold air and areas at risk of extreme thunderstorms

|

According to a representative of the meteorological agency, the phenomenon of hail appearing concentratedly in both mountainous, midland and delta areas is rare.

Boat carrying 14 tourists crashes into an anchored buoy and sinks in Ha Long Bay

|

Quang Ninh - At about 12:40 pm on May 4, in the Hang Luon area, Ha Long Bay, an accident occurred with a tourist transfer boat.

There will be 1,138 official delegates attending the 11th National Congress of the Vietnam Fatherland Front

|

On the afternoon of May 4, the Central Committee of the Vietnam Fatherland Front held a press conference to inform about the 11th National Congress of the Vietnam Fatherland Front, term 2026-2031.

Public non-business units proposed for ranking to reform salaries

|

The Ministry of Home Affairs proposes ranking public non-business units on a 100-point scale, divided into 5 levels.

Prime Minister directs deadline for operation of Bach Mai and Viet Duc Hospitals, facility 2

PHẠM ĐÔNG |

Prime Minister Le Minh Hung decisively directed the operation of Bach Mai and Viet Duc Hospitals, facility 2, in the second quarter of 2026.

Prime Minister chairs meeting on Viet Duc and Bach Mai Hospital project, facility 2

PHẠM ĐÔNG |

Prime Minister Le Minh Hung chairs the Government Standing Committee meeting with the Ministry of Health on 2 projects: Viet Duc Friendship Hospital and Bach Mai Hospital facility 2.

The State Bank continues to maintain the operating interest rates

PHẠM ĐÔNG |

The State Bank of Vietnam maintains the operating interest rates to create conditions for credit institutions to access capital sources.