Strive to shorten the progress of the Bach Mai and Viet Duc 2 Hospital projects by at least 1 month

PHẠM ĐÔNG |

Inspecting the Bach Mai and Viet Duc Hospital project, facility 2, Deputy Prime Minister Le Thanh Long requested to strive to shorten the progress by at least 1 month.

On the afternoon of February 19, Party Central Committee member, Deputy Prime Minister Le Thanh Long and the working delegation inspected and had a meeting on mechanisms and solutions to handle difficulties and problems in the investment project to build the second facility of Bach Mai Hospital and the investment project to build the second facility of Viet Duc Friendship Hospital.

On February 13, 2025, the Government issued Resolution No. 34/NQ-CP on mechanisms and solutions to handle difficulties and problems in these two hospital projects.

According to the Government Office, at the meeting, the representative of the Project Management Board said that the unit had coordinated with general contractors to ensure the progress of the Bach Mai Hospital project, which is expected to be completed and equipped by August 15, 2025; the contractor of Viet Duc Hospital committed to completing the construction on October 15, 2025.

The project management board will review to submit to the Ministry of Health in March to adjust the equipment list; conduct bidding.

Representatives of contractors for the Bach Mai Hospital and Viet Duc Hospital, branch 2 projects said that it is necessary to soon shorten procedures and time for approving contract adjustments ( progress, value, equipment portfolio) and hope to pay a part of the completed volume to have resources to continue implementation.

The contractor for the construction of facility 2 of Viet Duc Hospital is determined to complete the construction on October 15. The contractor of the Bach Mai Hospital project, Facility 2, committed to completing the remaining work in the next 6 months.

Pho Thu tuong Chinh phu Le Thanh Long kiem tra co so 2 Benh vien Viet Duc. Anh: Duc Tuan
Deputy Prime Minister Le Thanh Long inspected the second facility of Viet Duc Hospital. Photo: Duc Tuan

Concluding the meeting, Deputy Prime Minister Le Thanh Long stated that the number of patients coming to Bach Mai Hospital for examination and treatment shows that the completion of this project is extremely urgent.

Recalling the direction of General Secretary To Lam on combating waste, the Deputy Prime Minister noted that relevant ministries, branches, investors, and contractors are determined to put the project into operation as soon as possible.

The Deputy Prime Minister said that we have issued Resolution 34 but that is not everything, only to help us have some major mechanisms and principles to implement, but to put the two projects into operation, there is still a lot of work ahead.

"We cannot say that the work is done but must be organized and implemented," said the Deputy Prime Minister. The opinions of ministries, branches, investors, and contractors at today's meeting clearly demonstrated their determination, now it is necessary to organize implementation.

Accordingly, the Ministry of Health has issued a plan to implement Resolution 34. The Deputy Prime Minister stated that we are determined to shorten the progress by at least 1 month.

There is still a lot of work, so don't let one thing wait for another, try to do everything at the same time.

According to the Deputy Prime Minister, documentary documents are also important, but the way of working is to work directly with each other. The investor and the project management board will promptly complete the contract adjustment dossier to submit to the Ministry of Construction for appraisal.

For the project management board, it is necessary to closely follow the plan, focus on human resources, time, intelligence, enthusiasm, and work side by side with contractors to implement the work.

The Ministry of Construction guides and accelerates processes and procedures to resolve contractor's proposals; the Ministry of Finance ensures funding for the project.

The two hospitals need to be proactive in human resources, so that when they receive them, they can operate well. Request to report to the Prime Minister on the project implementation progress once a month.

PHẠM ĐÔNG
RELATED NEWS

Auditing the two projects of Bach Mai Hospital and Viet Duc Hospital, Facility 2

|

The Government requests the State Audit to conduct an audit of the settlement report of Bach Mai and Viet Duc Hospitals, Facility 2, to complete it according to regulations.

In 2025, hand over Central Hospital 74 to Vinh Phuc province

|

By the end of 2025, the Ministry of Health will hand over the Central Hospital 74 to the Vinh Phuc Provincial People's Committee for management.

Bach Mai Hospital's machinery is innocent, why is it left unused

|

From the case at Bach Mai Hospital, National Assembly delegates said that the machine system was not guilty of anything but was stopped and not used.

House fire in a deep alley in Ho Chi Minh City suspected of being caused by electrical short circuit

|

Ho Chi Minh City - A house in a deep alley on Le Van Luong street, Tan Hung ward suddenly caught fire, with flames billowing. The initial cause of the fire is suspected to be an electrical short circuit.

Toyota Long Bien whistled for bidding violation

|

Toyota Long Bien has just been notified by Thai Nguyen C Hospital of handling violations in bidding activities.

Dismantling houses to expand key roads at the eastern gateway of Ho Chi Minh City

|

Ho Chi Minh City - People are urgently dismantling houses and works to hand over land to serve the Do Xuan Hop road expansion project (section intersecting with Nguyen Duy Trinh).

Reasons why the Ministry of Education and Training proposes "reverse linkage" from universities to colleges and intermediate schools

|

The proposal to articulate from university to college and intermediate level is not to lower training standards but to protect the rights of learners and reduce waste in training.

Auditing the two projects of Bach Mai Hospital and Viet Duc Hospital, Facility 2

PHẠM ĐÔNG |

The Government requests the State Audit to conduct an audit of the settlement report of Bach Mai and Viet Duc Hospitals, Facility 2, to complete it according to regulations.

In 2025, hand over Central Hospital 74 to Vinh Phuc province

PHẠM ĐÔNG |

By the end of 2025, the Ministry of Health will hand over the Central Hospital 74 to the Vinh Phuc Provincial People's Committee for management.

Bach Mai Hospital's machinery is innocent, why is it left unused

PHẠM ĐÔNG |

From the case at Bach Mai Hospital, National Assembly delegates said that the machine system was not guilty of anything but was stopped and not used.