400 billion VND emergency traffic project in Da Nang is slow due to a series of bottlenecks

Nhóm PV |

Da Nang - Sluggish construction contractors, loose management, and continuous changes in focal points have caused the nearly 400 billion VND traffic reconstruction project in Da Nang mountainous area to be delayed for a long time.

7 contractors are behind schedule, some construction units are under 10%

Real-world records at the project site in Phuoc Thanh commune, Da Nang city at the beginning of 2026, in a sunny and dry time - favorable for construction in mountainous areas, but along the nearly 30km length of the Da Nang mountainous disaster emergency reconstruction project, there are only a few motorized vehicles.

The construction atmosphere is quiet, many locations have almost no significant movement, contrary to the "urgentness" of the project. For some bidding packages, after more than 4 years, the implemented volume is still less than 10% of the contract.

According to information from functional agencies, all 7 contractors participating in the project are behind schedule. Many construction units are holding back, lacking machinery, manpower, and materials. In particular, some contractors have withdrawn from the construction site when the actual volume is still very low.

Thiên tai qua lâu, nhưng dự án đường tái thiết vẫn dang dở,
Sunny season, but the construction site of a nearly 400 billion VND transportation project in mountainous Da Nang is only constructed sparingly, with rain, muddy roads, and the risk of further landslides. Photo: PV Group

When asked about the reasons for the slow progress, Mr. Tran Van Duong, managing the construction of the DH1 project of Thai Duong Construction Co., Ltd., admitted that the slow progress was due to prolonged rain and high material prices. But for an urgent project in mountainous areas, with a total value of nearly 400 billion VND, the factors of rain, floods, and complex geology should have been calculated right from the project preparation stage, technical solutions selection and construction organization because mountainous areas are not new to rain. Fluctuations in material prices are not entirely unexpected in the context of prolonged construction.

It is even more noteworthy that according to assessments from functional agencies, construction units do not have clear plans to deploy the remaining items; the gathering of materials, equipment, machinery, and manpower does not meet requirements. In other words, many contractors reveal signs of weakness in construction organization capacity, not simply encountering objective obstacles.

Dự án có đến 7 nhà thầu, trong đó, có đơn vị chỉ thi công dưới 10% khối lượng trong suốt hơn 4 năm qua. Ảnh: Nhóm PV
After more than 4 years, 7 contractors participating in the Da Nang mountainous traffic reconstruction project are all behind schedule, with some units only constructing less than 10% of the volume. Photo: PV Group

The names of some units specifically mentioned include: Thai Duong Construction Co., Ltd. on DH1 route; 168 Da Nang Infrastructure Construction Investment Joint Stock Company on DH2 and DH5 routes; Thanh Son Construction and Development Joint Stock Company on DH5 route.

However, weak contractors are only part of the problem. The rest lies in the selection, supervision and handling of weak contractors.

Mr. Do Hoai Xoan, Chairman of Phuoc Thanh Commune People's Committee, said frankly: "This responsibility belongs to the Project Management Board of the old Phuoc Son area".

Transfer like "empty paper

More complicatedly, this project takes place in the context of a constantly fluctuating management apparatus. After being assigned by the old Phuoc Son District People's Committee as the investor from 2021, traffic reconstruction projects then underwent many changes of focal points. The Phuoc Son Area Project Management Board disbanded. The director of the board received a new assignment in another locality. The project was received by the Quang Nam Provincial Construction Investment Project Management Board. Then this unit continued to merge into the Da Nang Civil, Industrial and Technical Infrastructure Construction Investment Project Management Board at the beginning of this year.

A project that is unfinished, and has gone through many transfers like that, is very likely to fall into a state of lack of continuity in monitoring and operation. And in fact, it has happened exactly like that.

Giao thông miền núi Đà Nẵng vẫn ngổn ngang sau 4 năm dự án tái thiết gần 400 tỉ đồng được triển khai. Ảnh: Nhóm PV
Mountainous traffic in Da Nang is still messy after 4 years of the nearly 400 billion VND reconstruction project being implemented. Photo: PV Group

Mr. Do Thanh Lam, Deputy Director of the Da Nang Civil, Industrial and Technical Infrastructure Construction Investment Project Management Board, admitted that the responsibility belongs to the managing management board of the project in the past. He said that the process of receiving the project faced many difficulties because it was almost "just a blank sheet of paper", without sufficient information to continue implementation; while some contractors have applied for withdrawal due to poor capacity.

It can be seen that the problem of the project is not only in the road surface outside the field, but also in the dossier system and management apparatus itself. A project worth nearly 400 billion VND cannot be allowed to be handed over in a state of broken information, incomplete data, and unclear personnel. If that actually happened, this is a serious sign of lax management in public investment projects.

Hàng trăm tỉ đồng ngân sách đổ vào dự án tái thiết giao thông miền núi Đà Nẵng, nhưng đường vẫn hư hỏng, nham nhỏ. Ảnh: Nhóm PV.
Hundreds of billions of VND of budget poured into the Da Nang mountainous traffic reconstruction project, but the road is still damaged and jagged. Photo: PV Group

An emergency traffic project invested nearly 400 billion VND for less than 30km – an average of more than 13 billion VND/km – but the effectiveness brought about to date is not commensurate.

The longer it is delayed, the greater the social cost. The slower it is, the more people's trust decreases. And it is even more dangerous if that delay is not pursued to the end of responsibility, not only to push the project to the finish line, but also to prevent the risk of wasting hundreds of billions of dong of the budget.

Nhóm PV
RELATED NEWS

400 billion VND for reconstruction, emergency traffic projects in Da Nang are still messy

|

Da Nang - After more than 4 years of construction, the nearly 400 billion VND emergency traffic project in the mountainous disaster area is still unfinished, bumpy as if it has never been rebuilt.

Project of over 31,200 billion VND in Can Tho lacks millions of cubic meters of sand

|

Can Tho - The Chau Doc - Can Tho - Soc Trang expressway project is facing a shortage of materials as the amount of sand brought to the construction site does not meet construction needs.

Da Nang removes obstacles to site clearance for more than 400 projects in 2026

|

The entire Da Nang City has more than 400 projects to be implemented, with nearly 47,000 dossiers not yet handed over.

466 projects and works in Hai Phong are backlogged and behind schedule

|

Hai Phong - Vice Chairman of the City People's Committee Le Trung Kien chaired a meeting to handle projects and works that are backlogged, suspended, and behind schedule in the area.

Academic transcripts, degrees integrated on VNeID: Progress in building education data

|

From May 15, 2026, transcripts and diplomas, certificates will be integrated on the VNeID application, serving for lookup and use in many administrative procedures.

Thailand announces initial results of mysterious missing 57 million tons of fuel

|

Huge amount of fuel mysteriously disappeared, Thai authorities suspect involvement in illegal fuel transit and storage activities.

Israel declares defeat of Major General in charge of Iranian Guard intelligence forces

|

Israel claims to have killed the head of intelligence of the Iranian Islamic Revolutionary Guard Corps (IRGC).

Gold prices plummet, trading is smooth

|

On April 6, gold prices adjusted down, gold stores continued to be bustling in the buying direction.

400 billion VND for reconstruction, emergency traffic projects in Da Nang are still messy

Nhóm PV |

Da Nang - After more than 4 years of construction, the nearly 400 billion VND emergency traffic project in the mountainous disaster area is still unfinished, bumpy as if it has never been rebuilt.

Project of over 31,200 billion VND in Can Tho lacks millions of cubic meters of sand

Tạ Quang |

Can Tho - The Chau Doc - Can Tho - Soc Trang expressway project is facing a shortage of materials as the amount of sand brought to the construction site does not meet construction needs.

Da Nang removes obstacles to site clearance for more than 400 projects in 2026

An Thượng |

The entire Da Nang City has more than 400 projects to be implemented, with nearly 47,000 dossiers not yet handed over.

466 projects and works in Hai Phong are backlogged and behind schedule

Hoàng Khôi |

Hai Phong - Vice Chairman of the City People's Committee Le Trung Kien chaired a meeting to handle projects and works that are backlogged, suspended, and behind schedule in the area.