Provincial roads in Can Tho lack sand, expressways face difficulties in filling material sources

Tạ Quang |

Can Tho - Many provincial road projects in Can Tho lack filling sand, while the horizontal axis expressway project, even with sufficient reserves, still faces difficulties in exploitation.

Tạ Quang
RELATED NEWS

Road 917, 918 projects in Can Tho are being constructed halfway due to lack of land

|

Can Tho - Many traffic projects in Can Tho are behind schedule due to site clearance, lack of resettlement land and unsynchronized handover of land.

Ground clearance not yet cleared, a series of Can Tho traffic projects are slow to construct

|

Can Tho - Many traffic projects in Can Tho are under construction at a slow pace due to site clearance problems, slow arrangement of resettlement foundations, affecting progress and investment efficiency.

Black spots of accidents on National Highway 61C - Provincial Road 929 in Can Tho removed

|

Can Tho - Approaching Lunar New Year, the intersection of National Highway 61C - Provincial Road 929, Can Tho City is being repaired, eliminating traffic accident black spots.

Ho Chi Minh City changes investment form to Thu Thiem Symphony Orchestra

|

Ho Chi Minh City changes the investment form of the Thu Thiem Symphony Orchestra, Music and Ballet Theater project from budget capital to public-private partnership (PPP) method.

The rainy and storm season is approaching, the Bac Khe Hydropower dam breach incident has not been resolved

|

Lang Son - Although it is close to the rainy and storm season, the Bac Khe 1 Hydropower dam breach has not been repaired.

Lao Cai stops operation of 13 sand and gravel mines that do not meet conditions

|

Lao Cai - 13 sand and gravel mines in the province do not meet the conditions, forcing them to stop operating until procedures are completed.

Vietnamese actors tell dangerous memories of filming with 300 buffaloes

|

The scene with the appearance of 300 buffaloes becomes special for the cast when acting in "Buffalo Harvest".

Opening of Vietnam Book and Reading Culture Day 2026

|

Hanoi - Vietnam Book and Reading Culture Day 2026 with the theme "Knowledge Chain - From Book Pages to Digital Space" has been officially organized.

Road 917, 918 projects in Can Tho are being constructed halfway due to lack of land

Tạ Quang |

Can Tho - Many traffic projects in Can Tho are behind schedule due to site clearance, lack of resettlement land and unsynchronized handover of land.

Ground clearance not yet cleared, a series of Can Tho traffic projects are slow to construct

Tạ Quang |

Can Tho - Many traffic projects in Can Tho are under construction at a slow pace due to site clearance problems, slow arrangement of resettlement foundations, affecting progress and investment efficiency.

Black spots of accidents on National Highway 61C - Provincial Road 929 in Can Tho removed

Tạ Quang |

Can Tho - Approaching Lunar New Year, the intersection of National Highway 61C - Provincial Road 929, Can Tho City is being repaired, eliminating traffic accident black spots.