Ground clearance not yet cleared, a series of Can Tho traffic projects are slow to construct

Tạ Quang |

Can Tho - Many traffic projects in Can Tho are under construction at a slow pace due to site clearance problems, slow arrangement of resettlement foundations, affecting progress and investment efficiency.

Many key transport projects in Can Tho are being implemented, expected to create a boost for socio-economic development. However, reality shows that the progress of some projects is still slow due to problems in compensation, support and site clearance.

Tiến độ một số dự án vẫn ì ạch do vướng mắc trong công tác bồi thường, hỗ trợ và giải phóng mặt bằng. Ảnh: Tạ Quang
The progress of some projects is still slow due to problems in compensation, support and site clearance. Photo: Ta Quang

At the 917 road project, more than 1km of the route has not been handed over land; dozens of households are still waiting for resettlement land. Many new packages have reached less than 15% of the volume, causing construction to be cut off and interrupted. Machinery and labor are gathered but have to "stand still" just because of land issues for a few households.

Mr. Le Thanh Thang - Technical Officer of Mien Nam Company said that the lack of construction site costs are high. "Equipment and machinery have been gathered but cannot be deployed, labor and mechanical costs still have to be maintained," Mr. Thang said.

Ông Lê Thành Thắng – Cán bộ kỹ thuật Công ty Miền Nam. Ảnh: Tạ Quang
Mr. Le Thanh Thang – Technical Officer of Southern Company. Photo: Ta Quang

Similarly, in the 918 road phase 2 project, more than 65% of the contract value has not been implemented. Dozens of cases have not handed over land; many resettlement plots have only stopped at the dossier approval stage. Some bidding packages such as the lighting system are almost unable to be implemented.

Mr. Nguyen Phi Hung - Supervision Consultant of Song Hong Company said that the unit has brought machinery and equipment to the construction site and partially constructed, but had to temporarily stop due to lack of land for the next items.

Thiết bị, máy móc đã tập kết nhưng không triển khai được. Ảnh: Tạ Quang
Equipment and machinery have been gathered but cannot be deployed. Photo: Ta Quang

Not only the above two projects, the situation of slow site handover also occurs at many other projects such as the National Highway 91 expansion project and provincial road 921. Non-synchronous handover of land, lack of resettlement ground, slow relocation of technical infrastructure... are "bottlenecks" that cause construction progress to be pushed back, and many bidding packages do not meet the plan.

Mr. Le Nhut Thu - Deputy Head of Project Management Unit 2, Project Management Unit for Investment and Construction of Transport and Agricultural Works of Can Tho City informed that the unit hopes that city leaders, Land Fund Development Center and local authorities will soon remove obstacles in site clearance work.

Ông Lê Nhựt Thủ - Phó Trưởng phòng Ban QLDA 2, Ban QLDA đầu tư xây dựng công trình giao thông và nông nghiệp TP Cần Thơ. Ảnh: Tạ Quang
Mr. Le Nhut Thu - Deputy Head of Project Management Board 2, Project Management Board for Investment and Construction of Transport and Agricultural Works of Can Tho City. Photo: Ta Quang

According to Mr. Le Nhut Thu, not only projects under construction but also projects about to be implemented need to be handed over land in a timely manner to ensure progress.

Early clearing the "bottleneck" of site clearance is expected to help traffic projects accelerate, avoid wasting resources and promote investment efficiency, meeting people's expectations.

Tạ Quang
RELATED NEWS

Transport infrastructure accelerates, Can Tho creates momentum for breakthrough in 2026

|

Can Tho - A series of transport infrastructure projects in Can Tho are being accelerated, aiming to complete important milestones in 2026.

Can Tho - Ca Mau expressway puts 2 rest stops into operation during Tet

|

Can Tho - During Tet, 2 rest stops on the Can Tho - Ca Mau expressway are put into temporary operation, serving people and drivers.

Mr. Trump declares Iran is developing missiles capable of reaching the US

|

Mr. Trump's State of the Union address sparked debate about Tehran's missile capabilities.

Restricting aspirations, candidates are forced to carefully calculate when registering

|

Ho Chi Minh City - The 2026 enrollment regulations will limit candidates registering to a maximum of 15 aspirations, forcing candidates to carefully consider when choosing majors and schools.

Collision on the highway, car blocks the road

|

Ha Tinh - After a collision on the Ham Nghi - Vung Ang highway, a car blocked a lane, causing traffic obstruction.

Clean water sometimes available, sometimes not, people stay up all night waiting for each drop

|

Hundreds of households in Bung Triet hamlet, Lieu Tu commune (Can Tho City) are living in a situation of clean water shortage, especially serious in the dry season and during Tet.

Iran is about to finalize agreement to buy China's hypersonic anti-ship missiles

|

Iran is approaching an agreement with China to buy hypersonic anti-ship cruise missiles, according to 6 well-informed sources.

Tiến độ giải phóng mặt bằng làm quảng trường phía Đông hồ Hoàn Kiếm

HOÀI ANH |

Hà Nội - Phường Hoàn Kiếm đã tiếp nhận mặt bằng của 12/17 tổ chức, 38/43 hộ dân và đang phá dỡ để làm quảng trường phía Đông hồ Hoàn Kiếm.

Transport infrastructure accelerates, Can Tho creates momentum for breakthrough in 2026

Tạ Quang |

Can Tho - A series of transport infrastructure projects in Can Tho are being accelerated, aiming to complete important milestones in 2026.

Can Tho - Ca Mau expressway puts 2 rest stops into operation during Tet

Tạ Quang |

Can Tho - During Tet, 2 rest stops on the Can Tho - Ca Mau expressway are put into temporary operation, serving people and drivers.