14 green trees "hold" a 150 billion VND project in Can Tho for 1 year after commencement

Tạ Quang |

Can Tho - After more than 1 year of construction, the nearly 150 billion VND library project in Can Tho is behind schedule due to 14 green trees.

The Can Tho City Library project has a total investment of nearly 150 billion VND, started at the end of February 2025, but after more than a year of implementation, it is still facing many difficulties, including not being able to handle 14 green trees located within the project premises.

Phối cảnh Thư viện TP Cần Thơ. Ảnh: Ban Quản lý dự án
Perspective of Can Tho City Library. Photo: Project Management Board

According to the Can Tho City Traffic and Agricultural Construction Investment Project Management Board, the project is built at land plot No. 1 Phan Dinh Phung street, Ninh Kieu ward, with an area of more than 2,424m2, expected to be completed in February 2027. However, so far, the construction value has only reached about 6% of the contract, and the acceptance value has reached 4.5%.

One of the main reasons is the obstacle of 14 ancient trees located along Phan Dinh Phung and Ngo Gia Tu streets. These trees have a large diameter, are decades old, and are located right at the pile driving position, so the foundation construction cannot be deployed yet. According to the plan of specialized agencies, all the trees will be relocated instead of being cut down.

However, the relocation cannot be carried out due to the lack of suitable transportation roads. It is expected that by March 2026, the road serving the relocation of new green trees will be completed, causing site clearance work to continue to be prolonged.

Những cây lâu năm sẽ được di dời sang nơi khác. Ảnh: Tạ Quang
Long-standing green trees will be moved to another place. Photo: Ta Quang

Mr. Nguyen Van Tinh - Project Commander said that the green trees are directly entangled in the pile pressing position, so the construction unit has not been able to deploy the necessary items. After more than a year of construction, the green tree ground has not been completely treated, greatly affecting the overall progress of the project.

During the construction process, the unit also discovered many underground items not in the initial design documents such as old reinforced concrete foundations, stone walls, old piles and underground water tanks. These items must be dismantled before pile pressing, causing additional time and affecting progress.

In addition, the transportation of materials is difficult because the project is located in the central area, only allowed to be carried out at night to ensure traffic safety, causing the construction process to be interrupted.

According to the design, the project includes 1 basement, 1 technical floor and 6 above-ground floors, with a total floor area of about 8,647m2, with a capacity of about 800 people. While waiting for completion, the library is currently temporarily operating at another location in Ninh Kieu ward. Top of Form

Tạ Quang
RELATED NEWS

Can Tho voters satisfied with quick, concise, and thoughtful election work

|

Can Tho - Voters said that the effective and quick election process has added confidence in a renewed and drastic term.

Police in Can Tho patrol overnight to ensure security and order during elections

|

Can Tho - Police forces in Can Tho increased night patrols, 100% of troops on duty, ensuring security and order in polling areas.

Account of the victim who had an accident in the cargo train tunnel in Khanh Hoa

|

Khanh Hoa - When the incident was discovered, the victims went down to the cargo train's hold to check and encountered an oxygen-deficiency environment, causing shock.

More than 100 billion VND bridge in Hue opens to traffic but is still unfinished, posing a risk of accidents

|

HUE - Although traffic has been cleared, the bridge over the Nhu Y River still lacks railings, lighting and pedestrian walkways, posing a risk of traffic accidents.

Politburo transfers Mr. Nguyen Manh Hung to hold the position of Deputy Secretary of Da Nang City Party Committee

|

Da Nang - Mr. Nguyen Manh Hung - Deputy Chairman of the Central Inspection Committee was transferred and appointed to hold the position of Deputy Secretary of the Da Nang City Party Committee.

Scene of 3 deaths in cargo train tunnel in Khanh Hoa

|

Khanh Hoa - On the morning of March 17, at the scene of the 3 deaths suspected of being due to gas poisoning, the victim's body still trapped in the cargo train's hold was taken out.

President Trump: The US should not be present in the Strait of Hormuz

|

President Trump faced fierce criticism after unexpectedly declaring that the US protection of the Strait of Hormuz was unnecessary and should not have been present here.

Can Tho voters satisfied with quick, concise, and thoughtful election work

Tạ Quang - Phong Linh |

Can Tho - Voters said that the effective and quick election process has added confidence in a renewed and drastic term.

Police in Can Tho patrol overnight to ensure security and order during elections

Tạ Quang |

Can Tho - Police forces in Can Tho increased night patrols, 100% of troops on duty, ensuring security and order in polling areas.

Truy nã Chủ tịch Tổng Công ty Cây xanh Công Minh

Việt Dũng |

Cơ quan An ninh điều tra Bộ Công an, trong bản kết luận đã đề nghị truy tố Chủ tịch Tổng Công ty Cây xanh Công Minh và truy nã với bị can này.