Two routes to relieve traffic jams in Ho Chi Minh City are only half open to traffic

MINH QUÂN |

HCMC - The road connecting Tran Quoc Hoan - Cong Hoa (Tan Binh district) and Duong Quang Ham street (Go Vap district) is only partially open to traffic due to land clearance and electricity poles.

Tran Quoc Hoan - Cong Hoa connecting road

Construction started at the end of 2022, the Tran Quoc Hoan - Cong Hoa connecting road project aims to connect Tan Son Nhat airport's T3 terminal, breaking the monopoly of the only airport entrance on Truong Son street.

The entire route is 4 km long, starting at the Tran Quoc Hoan - Phan Thuc Duyen intersection; ending at the intersection of C12 - Cong Hoa - Truong Chinh streets.

Ho Chi Minh City had set a target of opening the entire route to traffic by December 31, 2024. However, to date, only the Tran Quoc Hoan - Phan Thuc Duyen intersection tunnel and the section from this intersection to 18E Street, which is more than 600 m long, and about 500 m from 18E Street leading to Cong Hoa Street, have been completed and opened to traffic.

Ham chui duong Tran Quoc Hoan - Phan Thuc Duyen thong xe tu thang 10.2024. Anh: Minh Quan
The Tran Quoc Hoan - Phan Thuc Duyen underpass will open to traffic from October 2024. Photo: Minh Quan

According to the Management Board of Investment and Construction of Traffic Works in Ho Chi Minh City, on January 20, 2025, the section from 18E Street to Hoang Hoa Tham Street will be opened to traffic.

The remaining section (from Hoang Hoa Tham to the end of the route) will be open to traffic before April 30, 2025 due to site clearance issues, provided the site is handed over before February 20, 2025.

Duong va cau vuot truoc nha ga T3 san bay Tan Son Nhat se thong xe ngay 20.1. Anh: Minh Quan
The road and overpass in front of Tan Son Nhat Airport's T3 terminal will open to traffic on January 20. Photo: Minh Quan

This section is currently stuck with 68 households. A representative of Tan Binh District People's Committee said that there are currently 22 cases that are partially affected and have not agreed to the compensation plan. According to the plan, before Tet, Tan Binh District will complete the demolition and hand over the site of 46 cases that have agreed to the compensation and resettlement support plan to implement the construction.

For the remaining 22 cases on the frontage and alleys 111, 119, 116 Tran Van Du street, the district will increase contact and mobilize households to hand over the premises to the Traffic Department by the end of February 2025.

Duong Quang Ham Street

The project to expand Duong Quang Ham Street (Go Vap District) is nearly 2.5 km long, connecting Go Vap Cultural Park to the railway adjacent to Binh Thanh District.

The road was widened from 6m to 32m, with 6 traffic lanes. The total investment is over 2,300 billion VND, of which the cost of site clearance accounts for over 1,926 billion VND.

Started in April 2020, the project had to be suspended after only 4 months due to incomplete site clearance. It was not until September 2023 that the project was restarted when Go Vap district handed over part of the site.

Nhieu tru dien van an ngu giua duong Duong Quang Ham (Go Vap, TPHCM). Ảnh: Anh Tu
Many electric poles still block the middle of Duong Quang Ham Street (Go Vap, HCMC). Photo: Anh Tu

According to the Traffic Department, the project is still facing difficulties because many electric poles and telecommunication cables have not been relocated.

The section from Nguyen Viet Xuan Primary School to An Nhon Cultural House has been paved and is temporarily open to traffic. However, because the electric poles are still located between the existing road and the extension, the Traffic Department has installed barriers, painted warning signs and arranged flashing lights to ensure traffic safety.

Duong Duong Quang Ham se cho xe luu thong truoc, di doi tru dien sau.  Anh: Anh Tu
Duong Quang Ham Street will be open to traffic first, then the electric pole will be relocated. Photo: Anh Tu

The two sections from Luong Ngoc Quyen Street to Nguyen Viet Xuan Primary School (520 m) and the section from An Nhon Cultural House to Nguyen Van Luong Street (295 m) are still new routes and not yet open to traffic.

The Traffic Department said that to reduce traffic pressure and facilitate people during the 2025 Lunar New Year, these sections will be temporarily opened to traffic on January 20, 2025. The lighting system and steel dividers will be fully installed to ensure safety.

The project is expected to complete phase 2 (entire cross-section) on April 30, 2025, on condition that the electricity industry must withdraw all electricity poles before March 30, 2025.

MINH QUÂN
TIN LIÊN QUAN

Trillion-dollar road surface to ease traffic jams in Go Vap

|

HCMC - The Duong Quang Ham Street expansion project (Go Vap) is speeding up construction progress, with the goal of completing the expansion to 6 lanes in 2025.

4,800 billion VND road to "rescue" Tan Son Nhat traffic jam reaches 88% of volume

|

HCMC - The Tran Quoc Hoan - Cong Hoa connecting road, costing over VND4,800 billion, has reached 88% completion, and is expected to open the entire route by the end of February 2025, reducing traffic congestion at Tan Son Nhat airport.

Ho Chi Minh City opens 9-year-old unfinished road in Thu Duc

|

HCMC - After 9 years of implementation, Luong Dinh Cua Street (from Nguyen Hoang Street to Tran Nao intersection, Thu Duc City) will open to traffic before Lunar New Year 2025.

Expressway in operation for 6 years still lacks "input" and has no "output"

|

After more than 6 years of collecting tolls, the 139km Da Nang - Quang Ngai expressway still faces many problems, especially a serious shortage of essential logistics services.

Police invite Mercedes driver who crashed into the sea to come in for questioning

|

Khanh Hoa - The police have sent a letter inviting the Mercedes driver to come in for questioning. Previously, this driver was carrying 4 women and crashed into the Nha Trang beach.

Colonel Nguyen Duc Hai was elected as a member of Dong Nai People's Committee

|

Dong Nai Provincial People's Council elected Colonel Nguyen Duc Hai - Director of Dong Nai Provincial Police to be an additional member of Dong Nai Provincial People's Committee.

Permanent Deputy Prime Minister Nguyen Hoa Binh presents Tet gifts in Quang Ngai

|

On January 14, the Quang Ngai Provincial Federation of Labor organized the program Tet Sum Vay - Xuan Ung Deng. Deputy Prime Minister Nguyen Hoa Binh attended.

Michelin Pho Restaurant Owner Reveals 80-Year-Old Family Secret

|

The owner of Pho Tu Lun restaurant in Hanoi's Old Quarter revealed a simple recipe for making pho that retains its delicious flavor, winning over diners for decades.

Trillion-dollar road surface to ease traffic jams in Go Vap

Anh Tú |

HCMC - The Duong Quang Ham Street expansion project (Go Vap) is speeding up construction progress, with the goal of completing the expansion to 6 lanes in 2025.

4,800 billion VND road to "rescue" Tan Son Nhat traffic jam reaches 88% of volume

MINH QUÂN |

HCMC - The Tran Quoc Hoan - Cong Hoa connecting road, costing over VND4,800 billion, has reached 88% completion, and is expected to open the entire route by the end of February 2025, reducing traffic congestion at Tan Son Nhat airport.

Ho Chi Minh City opens 9-year-old unfinished road in Thu Duc

TÚ QUÂN |

HCMC - After 9 years of implementation, Luong Dinh Cua Street (from Nguyen Hoang Street to Tran Nao intersection, Thu Duc City) will open to traffic before Lunar New Year 2025.