On January 9, Lam Dong Provincial People's Committee assigned Da Lat City People's Committee to urge and speed up the progress of site clearance for the road to Xuan Huong Lake.
This is a project to build a traffic route connecting Lu Gia Street to the upstream of Xuan Huong Lake, the embankment of settling lake No. 1 (Ward 9, Da Lat City).
The project started in September 2021, but has not yet been completed.
The project has a total initial investment of 138 billion VND, invested by the Da Lat City Land Fund Development and Investment Project Management Board.
The contractor is Construction One Member Co., Ltd. 470.
In this project, the traffic route connecting Lu Gia Street to the upstream of Xuan Huong Lake has a total length of 1.7km.
Due to difficulties in site clearance, the construction unit has only been able to build more than 700m.
In September 2024, Lam Dong Provincial People's Committee decided to adjust the total investment of the project from 138 billion VND to more than 261 billion VND.
Of which, land clearance costs were adjusted from 67 billion VND to more than 163 billion VND (an increase of about 96 billion VND).