500 workers divided into 3 shifts of 4 teams constructing Rach Mieu 2 bridge

Thành Nhân |

Ben Tre - 500 workers divided into 3 shifts of 4 teams to construct Rach Mieu 2 bridge project. They worked tirelessly to bring the project to the finish line.

According to the reporter of Lao Dong Newspaper on January 24, at the Rach Mieu 2 Bridge project, many workers are still working hard on construction items.

Working at the Rach Mieu 2 Bridge project site, Mr. Le Minh Thao said that during the time approaching the Lunar New Year 2025, at the construction site, workers were still working enthusiastically, taking advantage of a quick meal to complete the construction on time, bringing the project to the finish line early and handing it over as committed to the investor.

Hon 500 cong nhan lao dong thi cong tren cong truong du an cau Rach Mieu 2. Anh: Thanh Nhan
500 workers working in 3 shifts, 4 shifts at the Rach Mieu 2 bridge project site. Photo: Thanh Nhan

Mr. Nguyen Nam Phong - Director of the Rach Mieu 2 Bridge Project Management Board - said that the Rach Mieu 2 Bridge project has been completed over 79%, ahead of the general schedule by more than 4%. The main bridge - Rach Mieu 2 Bridge in particular is ahead of schedule by more than 24%.

The road section under construction on the entire route is about 14 km, 100% complete of the embankment work to treat weak soil (in the consolidation stage). Currently, 10/14 km of the load is being unloaded, and about 4 km of asphalt concrete has been laid in each segment. It is expected that the entire route (including roads and bridges on the route) on the Ben Tre side will be completed before June 30, 2025.

Regarding the bridge section, 4/6 bridges have been completed (Xoai Hot bridge, My Tho bridge, Tam Son bridge and Ba Lai bridge), the remaining 2 bridges are under construction (Rach Mieu 2 main bridge and Song Ma bridge), of which Song Ma bridge is expected to be completed before June 2025.

As for the main bridge section of Rach Mieu 2 Bridge, as of October 24, 2024, 100% of the towers of P19 and P20 have been completed. The bridge deck has completed the beam block up to K10 (block K10/13 blocks) at the cable-stayed piers P19 and P20, the SK11 beam block on the anchor piers P18 and P21 has been completed. Currently, workers are installing and tensioning the cable-stayed cable bundle No. 88/112 cable-stayed cable bundles. The plan is to close the edge in April 2025, close the middle in August 2025, open the technical traffic on September 2, 2025, and complete the entire project before October 30, 2025.

Mr. Nguyen Nam Phong also said that currently, at the construction site, the units are continuing to maintain the implementation of 3 shifts, 4 teams (with a total of about 30 construction heads and about 150 construction equipment, 500 workers and 83 technical staff). During the Tet At Ty 2025, the units have proactively arranged and organized the construction of the main items until the last day of the old year. In addition, during the Tet holidays, auxiliary works, concrete maintenance, road surface maintenance, ensuring safety work, etc. are still being carried out. The units organize rotation of teams and groups to work at the construction site, ensuring that workers and engineers have Tet with their families and also complete the common tasks of the Rach Mieu 2 bridge project in parallel.

The Rach Mieu 2 Bridge project connects Tien Giang and Ben Tre provinces, with a route length of about 17.6km. This project has a total investment of more than 6,810 billion VND, and was started at the end of March 2022. The scale is 4 lanes, the design speed is 80km/h, and is expected to be completed in 2025. When completed, the project will contribute to reducing traffic congestion at the existing Rach Mieu Bridge.

Thành Nhân
RELATED NEWS

Workers work through Tet on Rach Mieu 2 Bridge project

|

Ben Tre - On the morning of January 1, at the Rach Mieu 2 bridge project, many workers and engineers were working on items such as leveling the ground, bundling cable-stayed cables, etc.

Visiting Rach Mieu Bridge construction workers on the first 2 days of the new year

|

Ben Tre - On the morning of January 1, although it was New Year's Day, at the construction site of the Rach Mieu 2 bridge project, workers and engineers were still working non-stop.

Workers quickly ate a bowl of rice, determined to bring Rach Mieu 2 bridge to the finish line

|

Ben Tre - As of December 9, the overall progress of the Rach Mieu 2 bridge project has reached more than 71%, 0.49% faster than planned.

Unexpected risks of holding many "winter- sleeping" accounts

|

The fee is from 5,000 VND - 22,000 VND/month if the account is only "opened".

VinFuture main prize is the project with a large-scale influence on the global population

|

On the evening of December 5, the VinFuture 2025 Award Ceremony - the focal event of VinFuture Science and Technology Week 2025, will take place.

Ho Chi Minh City plans to build Can Gio Bridge worth over VND13,200 billion, starting construction in 2027

|

HCMC - The Can Gio bridge project has a total length of 6.3 km, a total of more than 13,200 billion VND under the BT contract, expected to start construction in 2027, replacing Binh Khanh ferry.

Ambulances transferred to the hospital hit a passenger bus, the patient died on the way to Ho Chi Minh City

|

Lam Dong - An ambulance took a patient to Ho Chi Minh City when he had an accident on the highway. The patient was transferred to another hospital by another vehicle but died.

Resuming search for MH370, data reveals unusual scenario

|

On December 4, Malaysia announced that marine survey company Ocean Infinity will begin searching for MH370 from December 30, with a non-continuous 55-day period.

Workers work through Tet on Rach Mieu 2 Bridge project

Thành Nhân |

Ben Tre - On the morning of January 1, at the Rach Mieu 2 bridge project, many workers and engineers were working on items such as leveling the ground, bundling cable-stayed cables, etc.

Visiting Rach Mieu Bridge construction workers on the first 2 days of the new year

Thành Nhân |

Ben Tre - On the morning of January 1, although it was New Year's Day, at the construction site of the Rach Mieu 2 bridge project, workers and engineers were still working non-stop.

Workers quickly ate a bowl of rice, determined to bring Rach Mieu 2 bridge to the finish line

Thành Nhân |

Ben Tre - As of December 9, the overall progress of the Rach Mieu 2 bridge project has reached more than 71%, 0.49% faster than planned.