Bac Ninh Provincial People's Committee has just issued a decision approving the adjustment of the implementation time of the DT.292 connecting road project through An Ha Industrial Park, Tien Luc commune to the Northeast ring road, Bac Giang ward.
This project was approved by the Chairman of Bac Giang Provincial People's Committee (old) in the decision dated December 25, 2020, and approved for adjustment in the decision dated July 6, 2022 with the implementation period being 2022-2025.
The project was started on December 31, 2023. However, up to now, due to difficulties and obstacles in site clearance (the newly cleared project reached 7.78km/14.98km, total construction length reached 4.4km/15.33km). Therefore, it is necessary to extend the project implementation time so that investors and localities have enough time to carry out project tasks according to regulations.
Adjustment content: Adjusting the project implementation time to the end of 2026.
Bac Ninh Provincial Traffic and Agriculture Project Management Board No. 1 organizes the implementation of the next steps according to regulations.
Heads of agencies: Office of the Provincial People's Committee; Departments: Finance, Construction, Agriculture and Environment; State Treasury of Region VI; Director of Bac Ninh Provincial Traffic and Agriculture Project Management Board No. 1; Chairmen of People's Committees of communes: Kep, Lang Giang, My Thai and related agencies and units based on the decision to implement.
It is known that the DT.292 connecting road project through An Ha Industrial Park, Tien Luc commune to the Northeast Ring Road, Bac Giang ward is invested by the Bac Ninh Provincial Traffic and Agriculture Project Management Board No. 1.
The road is 15.3km long, the road surface is 11m wide. The total investment is nearly 410 billion VND from the state budget.