Disagreement between contractors threatens progress of Metro Line 1 in Ho Chi Minh City

MINH QUÂN |

HCMC - Metro Line 1 is facing difficulties due to internal disagreements among contractors in the CP1a package consortium (underground section from Ben Thanh to City Theater).

This information was presented by the Ho Chi Minh City Department of Transport in a report sent to the Ministry of Transport, updating the implementation status of key transport projects in the city.

According to the report, Metro Line 1 project (Ben Thanh - Suoi Tien) has achieved about 98.81% of the workload.

In which, the system safety certification assessment is being completed with 10 out of 13 reports completed, equivalent to about 80% of the volume.

The trial operation process on the entire Metro Line No. 1, carried out by the Urban Railway Company No. 1, began on October 1 and is expected to last until November 30. This is the final inspection step to ensure system safety before the project officially goes into operation.

Nha ga ngam Ben Thanh thuoc goi thau CP1a do Lien danh Sumitomo Mitsui - CIENCO4 lam tong thau.  Anh: Anh Tu
Ben Thanh underground station belongs to CP1a package with Sumitomo Mitsui - CIENCO4 joint venture as general contractor. Photo: Anh Tu

However, the project is facing difficulties and obstacles due to internal disagreements between contractors in the CP1a consortium (construction of the underground section from Ben Thanh station to City Theater station).

SMC4 Joint Venture (Sumitomo Mitsui - CIENCO4 Joint Venture is the general contractor of CP1a package) has not yet reached an agreement on signing the project documents.

For example, the signature of the consortium member CIENCO4 Group Joint Stock Company is missing in the contract appendices (contract appendix adjusting the contract implementation time, appendices related to payment and disbursement, providing VAT invoices for payment, etc.).

Faced with this situation, the Management Board of Ho Chi Minh City Urban Railways (MAUR - the investor) has conducted many working sessions with both members of the consortium, listening to the opinions and proposals of Sumitomo Mitsui and CIENCO4.

MAUR suggested that both sides make efforts to discuss and compromise to agree on solutions and thoroughly resolve internal problems within the consortium in the spirit of cooperation and support, avoiding affecting the progress of Metro Line 1 project.

To ensure progress and disbursement, on October 24, MAUR sent a document requesting the consortium SMC4 and CIENCO4 Group Corporation to urgently complete related documents and submit them to MAUR in October.

MAUR also emphasized that if these documents are not provided on time, the unit will report to the Ho Chi Minh City People's Committee and the Ministry of Transport, and even report to the Prime Minister for direction, in order to have strong, thorough and decisive handling measures.

Gieng troi cao 6 m, duong kinh 21,6 m o ga ngam Ben Thanh.  Anh: Anh Tu
6 m high, 21.6 m diameter skylight at Ben Thanh underground station. Photo: Anh Tu

To date, this issue has not been resolved by the parties involved.

Faced with this situation, the Ho Chi Minh City Department of Transport has proposed the State Steering Committee for important national projects and key transport sector works and projects and the Ministry of Transport to direct CIENCO4 Group Joint Stock Company to urgently complete the above documents in November 2024 to ensure the project's completion progress.

In case of non-compliance, the Ho Chi Minh City Department of Transport proposes to take measures to deal with other transportation projects that CIENCO4 Group Joint Stock Company is participating in, including measures to limit bidding for a limited period in Ho Chi Minh City.

According to the Ho Chi Minh City Department of Transport, this year Metro Line 1 must disburse more than VND4,467 billion, but by the end of October, it had only disbursed more than VND962 billion, reaching 21.54% of the plan.

Ho Chi Minh City aims to officially operate Metro Line 1 from December 22, 2024.

MINH QUÂN
TIN LIÊN QUAN

Metro Line 1 enters decisive test week before operation

|

HCMC - Metro Line No. 1 (Ben Thanh - Suoi Tien) enters a testing week at maximum capacity, marking an important milestone before officially entering commercial operation.

Appearance of Ba Son underground station, Metro line 1, just handed over

|

HCMC - Ba Son underground station of Metro line 1 (Ben Thanh - Suoi Tien) has completed acceptance and handover, marking an important step before official operation.

Metro line 1 will run commercially from December 22, what are the conditions?

|

Ho Chi Minh City aims to put Metro Line 1 (Ben Thanh - Suoi Tien) into commercial operation on December 22. So what is the current progress of Metro Line 1?

Clarifying responsibility for issuing wrong red books on prison land

|

Lam Dong - Provincial inspectors determined that 4.29 hectares of land of Dai Binh Prison had been illegally granted red books by local authorities to 7 households.

Inadequate treatment of officials and workers

|

National Assembly delegates said that the treatment of officials and employees working at drug rehabilitation facilities is not commensurate with the requirements and tasks of the job.

Nam Dinh has a new Provincial Party Secretary

|

Nam Dinh - Mr. Dang Khanh Toan was mobilized and appointed by the Politburo to hold the position of Secretary of Nam Dinh Provincial Party Committee.

Go Cong sea dike "fluctuates" before monsoon season

|

Tien Giang - Some sections of the Go Cong sea dike are degraded, local authorities in Go Cong Dong district have proposed investing in wave-reducing dikes.

Sad news

|

Mr. Ignatius Do Van Luan, born in 1956, father of comrade Do Thi Yen Phuong, father-in-law of comrade Nguyen Van Quang - reporter of Lao Dong Newspaper working at the Representative Office in the Mekong Delta, passed away at 2:00 p.m. on November 13, 2024, October 13, Giap Thin year. He was 68 years old.

Metro Line 1 enters decisive test week before operation

MINH QUÂN |

HCMC - Metro Line No. 1 (Ben Thanh - Suoi Tien) enters a testing week at maximum capacity, marking an important milestone before officially entering commercial operation.

Appearance of Ba Son underground station, Metro line 1, just handed over

MINH QUÂN - ANH TÚ |

HCMC - Ba Son underground station of Metro line 1 (Ben Thanh - Suoi Tien) has completed acceptance and handover, marking an important step before official operation.

Metro line 1 will run commercially from December 22, what are the conditions?

MINH QUÂN |

Ho Chi Minh City aims to put Metro Line 1 (Ben Thanh - Suoi Tien) into commercial operation on December 22. So what is the current progress of Metro Line 1?