Binh Dinh has made many requests, but the project to upgrade National Highway 19 is still slow

Hoài Luân |

Regarding the problem of inadequacies in the construction of the National Highway 19 upgrade project, the leader of Binh Dinh province said that he will direct the authorities to investigate and handle the matter.

On October 8, chairing a press conference on the socio-economic situation in the first 9 months, Mr. Lam Hai Giang - Vice Chairman of Binh Dinh Provincial People's Committee informed about some contents that the press has reflected in the past time. Among them, the construction of the project to enhance traffic connectivity in the Central Highlands region (project to renovate and upgrade National Highway 19) caused dust and cracked houses.

According to Mr. Lam Hai Giang, the press has reported a lot about the slow progress of the project to renovate and upgrade National Highway 19. The province has seen this problem and has repeatedly made recommendations to the central government, even working with the project investor. However, the solution is still very slow.

s
Mr. Lam Hai Giang informed at the press conference. Photo: Hoai Luan

"In the near future, we will invite the units related to the project to work directly. If the units do not do it, the Department of Transport Inspectorate will come down to inspect and if violations are found, they must be handled. This situation cannot happen again."

The day before, the delegation of Deputy Prime Minister Ho Duc Phoc of the Government went to Binh Dinh, traveling on National Highway 19, but the project construction unit caused dust all over the road. The authorities requested that water be sprayed during construction, but they gave the excuse that they were not there, so they did not do it," said Mr. Lam Hai Giang.

s
Many sections of National Highway 19 have not been paved, causing dust when vehicles pass by (photo taken on May 15). Photo: Hoai Luan

The project to renovate and upgrade National Highway 19 has a total length of more than 143km (passing through Tay Son district, Binh Dinh province 17km; Gia Lai province 126.34km), with a total investment of more than 3,650 billion VND, invested by Project Management Board 2 (Ministry of Transport).

It is expected that by the end of October 2024, the construction unit will complete the XL-01 package of this project. However, currently, site clearance work at some locations on the route is still "not yet completed" and compensation and support for houses that have been cracked due to project construction have not been completely resolved.

s
More than 1,200 houses and structures of households were cracked due to the construction of the National Highway 19 upgrade project. Photo: Hoai Luan

According to the People's Committee of Tay Son district, up to now, the progress of the land acquisition and clearance project to renovate and upgrade National Highway 19 still has some electric poles on the frontage road that need to be relocated. The capital plan for compensation work by the project in 2024 is 57,594 billion VND, but currently the investor has only transferred nearly 34 billion VND to the locality.

As of September 16, the total number of households whose houses and structures were cracked due to project construction was 1,201 (781 households in Tay Giang commune and 420 households in Tay Thuan commune), the number of households whose damages had been assessed was 1,054 (113 households had not agreed with the assessment results). Of which, the investor had paid compensation to 138 households, with an amount of more than 690 million VND; the number of households that had agreed to receive the money was 150 households, with a compensation amount of more than 1 billion VND.

Speaking with Lao Dong, Mr. Nguyen Van Khanh - Vice Chairman of Tay Son District People's Committee - said that the locality is urging the investor and project unit to compensate the remaining households with cracked houses.

Hoài Luân
RELATED NEWS

The US maintains a counterpart tax of 20%, opening up opportunities to reduce to 0% for Vietnamese goods

|

Maintaining the counterpart tax rate of 20% and the possibility of expanding the scope of tax reduction for some groups of goods to 0% will open up new opportunities for Vietnam.

Metro No. 1 reaches 14 million passengers, stops selling paper tickets at 11 stations

|

HCMC - From November 1, Metro Line 1 (Ben Thanh - Suoi Tien) will stop selling paper tickets at 5 more stations, bringing the total number of stations that have stopped selling tickets to 11/14.

Conflict of inexorable accounts over investment capital contribution of Hanoi University of Business and Technology

|

Not only in legal crisis, Hanoi University of Business and Technology was also accused of "abandoning" hundreds of investors, "losing" more than 117 billion VND in capital contributions.

sandbags are used all day and night to block the water of Tra Khuc river from overflowing into the inner city of Quang Ngai

|

Quang Ngai - The authorities are keeping their mouths closed day and night at the pumping station at the embankment project to prevent landslides on the southern bank, preventing the Tra Khuc River from flowing back into the inner city.

Floodwaters rise again, the center of Hue City becomes a chaotic traffic "river"

|

HUE - On the afternoon of October 29, floodwaters on rivers rose rapidly, causing many central streets of Hue City to be deeply flooded, vehicles stalled, and traffic paralyzed.

Allocated 3 phases with a total budget of 428 billion VND to support people affected by storms and floods

|

The Central Relief Mobilization Committee has allocated 3 phases with a total budget of 428 billion VND to support 17 provinces and cities to overcome the consequences of storms and floods.

National Assembly deputies surprised when people had to provide copies of their red books

|

National Assembly delegates said that cleaning up land data is very necessary, but there needs to be solutions that are well implemented so as not to cause trouble for people.

Binh Dinh requires ensuring the quality of key road projects

Hoài Phương |

For key national and provincial transport projects, the Chairman of Binh Dinh province requires ensuring construction quality, especially when constructing during the rainy season.

Binh Dinh fishing boat sunk by another ship at sea

Hoài Phương |

Binh Dinh - While fishing at sea, a fishing boat of fishermen from Hoai Nhon town was sunk by a ship of unknown origin.

Binh Dinh requests to end the situation of "your rights, my rights"

Hoài Phương |

Binh Dinh - According to the Secretary of Binh Dinh Provincial Party Committee, the current procedures for applying for mineral mines are very complicated, causing difficulties in departments and offices.