Binh Dinh speeds up progress, starts construction of new runway at Phu Cat airport in August

Hoài Luân |

Binh Dinh requested the Traffic and Civil Project Management Board to complete the work, procedures... to be ready to start construction of the new runway in August.

On May 15, Vice Chairman of Binh Dinh Provincial People's Committee Nguyen Tu Cong Hoang directed the implementation of the Investment project to build runway No. 2 and synchronous works at Phu Cat Airport area.

In recent times, the Traffic and Civil Project Management Board of Binh Dinh province has actively coordinated with ministries, central and local branches to implement the project and basically meet the set plan.

However, the remaining workload is currently very large, especially tasks related to appraisal of documents, handover of defense land, selection of contractors, relocation of technical infrastructure, site clearance for resettlement areas and burial areas...

Therefore, Mr. Nguyen Tu Cong Hoang requested the Provincial Traffic and Civil Project Management Board to urgently complete the DTM dossier (environmental impact assessment report) of the project and the land mine serving the project to submit to the competent authority for appraisal and approval.

At the same time, speed up the completion of dossiers on conversion of forest, forest land, and rice land use purposes to meet the conditions for submission to the Provincial People's Council for consideration at the thematic session in May 2025.

Focus on implementing steps, documents, procedures, and developing compensation and support plans for site clearance in the runway area No. 2. These documents must be completed and submitted to the appraisal agency for approval in May to pay compensation in June 2025. The site clearance for resettlement areas and burial areas must be completed in July, to be ready to start construction from August 2025.

In addition, the Vice Chairman of Binh Dinh Provincial People's Committee requested the Project Management Board to work with Vietnam Airports Corporation (ACV) to promptly give opinions on the feasibility study report, serving the work of project appraisal and approval according to regulations.

At the same time, regularly coordinate with relevant ministries and branches to promptly handle problems in the implementation process, especially the issue of handing over National Defense land. In case of arising content beyond the authority, it is necessary to urgently report to the Provincial People's Committee for direction on handling.

Proactively coordinate closely with military units in the area such as Regiment 940, Regiment 925, ... to agree on a plan to prepare compensation and support records for site clearance for items in the affected military region. These plans must be submitted for appraisal and approval early to transfer funding to military units to carry out the relocation and construction of returned works to serve national security and defense work.

Hoài Luân
TIN LIÊN QUAN

Binh Dinh displays more than 1,500 documents commemorating the 70th anniversary of the Northward gathering

|

Binh Dinh displays more than 1,500 valuable documents and images, recreating the heroic historical period when tens of thousands of people from the South gathered in the North.

Phanh phui illegal stone mining activities on Hon Cha Mountain

|

Binh Dinh - After many days of following the traces of stone bandits, Lao Dong Newspaper reporters recorded the entire illegal stone mining process taking place on Hon Cha Mountain.

Binh Dinh will soon complete the program to eliminate temporary and dilapidated houses

|

Binh Dinh - After more than 3 months of implementing the elimination of temporary and dilapidated houses, the province has completed the construction and repair of 4,200 houses and put them into use, reaching 95.3%.

HCMC supports electricity prices, students and workers are excited to wait for application

|

HCMC - Rental renters are happy when HCMC supports electricity and water prices and expect landlords to soon apply them to reduce the living burden for students and workers.

Roadmap for handling more than 100 redundant headquarters after restructuring and streamlining in Hai Phong

|

Hai Phong - According to the project to reorganize commune-level administrative units, Hai Phong City plans to have 101 surplus headquarters.

Many contents in the Land Law need to be reviewed to amend in accordance with the 2-level model

|

Many contents of the 2024 Land Law need to be amended to comply with the 2-level local government model.

Sunscreen distributed by singer Doan Di Bang's husband was revoked due to incorrect SPF index

|

Hanayuki sunscreen distributed by singer Doan Di Bang's husband's company was revoked by the Ministry of Health for incorrect sunscreen index.

The last song Uncle Ho listened to before going far away

|

"The words of Uncle Ho before going far" is a song composed by musician Tran Hoan in 1989 - 20 years after Uncle Ho passed away.

Binh Dinh displays more than 1,500 documents commemorating the 70th anniversary of the Northward gathering

Thảo Phương |

Binh Dinh displays more than 1,500 valuable documents and images, recreating the heroic historical period when tens of thousands of people from the South gathered in the North.

Phanh phui illegal stone mining activities on Hon Cha Mountain

Hoài Phương |

Binh Dinh - After many days of following the traces of stone bandits, Lao Dong Newspaper reporters recorded the entire illegal stone mining process taking place on Hon Cha Mountain.

Binh Dinh will soon complete the program to eliminate temporary and dilapidated houses

Hoài Luân |

Binh Dinh - After more than 3 months of implementing the elimination of temporary and dilapidated houses, the province has completed the construction and repair of 4,200 houses and put them into use, reaching 95.3%.