Ministry of Construction guides determining the cost of monitoring and installing equipment in the project

Xuyên Đông |

The Ministry of Construction has just responded to citizens' instructions to determine the cost of monitoring and installing equipment into the project.

On the Government Information Portal, Mr. N.L reflected that Clause 39, Article 3 of the Construction Law stipulates that equipment installed on works includes construction equipment and technology equipment.

Construction equipment is equipment installed in a construction work according to a construction design. Technology equipment is equipment located in a technology line installed in a construction work according to a technology design.

According to Circular No. 12/2021/TT-BXD of the Minister of Construction promulgating construction norms, the cost of monitoring and installing equipment is determined according to the percentage norm (%) (issued in Table 2.22 attached to this Circular) multiplied by the cost of equipment (excluding value-added tax) in the equipment bidding package estimate.

In Mr. N.L's locality, some construction investment projects include items for purchasing ordinary equipment (tables, chairs, cabinets, computers, washing machines, shelves, shelves, cabinets, counters, air conditioners, fans, trash cans...) or equipment in the fields of health, education, sports... (breaters, syringes, operating knives, hospital beds, student tables and chairs, experimental equipment, sports equipment...) approved by the investor for the estimate (not approving construction design or technology design.

In which there is a section on supervision costs for these equipment items determined according to the percentage norm of equipment installation supervision costs issued in Table 2.22 attached to Circular No. 12/2021/TT-BXD mentioned above.

Mr. L asked, is the investor's determination of monitoring costs for equipment as above consistent with regulations?

In case it is not in accordance with regulations, he proposed that the Ministry of Construction soon provide guidance on how to determine the estimate for the supervision of these equipment so that localities have a basis to implement the management of construction investment costs to ensure current regulations.

The Ministry of Construction answers this question as follows:

According to Clause 39, Article 3 of the 2014 Construction Law:

Equipment installed on a construction site includes construction equipment and technology equipment. Construction equipment is equipment installed on a construction site according to a construction design. Technology equipment is equipment located in a technology line installed on a construction site according to a technology design.

Thus, for construction investment projects with parts of equipment installed on the project according to the design, the cost of monitoring and installing equipment is determined according to the provisions at point 8.3, item 8, chapter II, part II, Appendix No. VIII of Circular No. 12/2021/TT-BXD of the Minister of Construction on promulgating construction norms.

Xuyên Đông
RELATED NEWS

Ministry of Construction answers about the scope of operation of construction practice certificates

|

On the Government Information Portal, the Ministry of Construction answers citizens about the scope of operation of construction practice certificates.

The Ministry of Construction answers the time of site clearance for the high-speed railway project

|

The Ministry of Construction said it will advise the Government on site clearance for the high-speed railway project in January 2026.

The Ministry of Construction responds to cases of current construction permit exemption

|

On December 18, on the Government Information Portal, the Ministry of Construction responded to citizens about the current construction permit exemption regulations.

Greenland and cost calculation that divides NATO

|

The former NATO Deputy Secretary General said that deploying more US troops to Greenland is unrealistic.

Hanoi pilots Kham Thien street traffic organization for 3 months

|

Hanoi will pilot traffic organization adjustments on Kham Thien street for 3 months, including banning taxis and contract cars under 8 seats during peak hours to reduce congestion.

Russia ignores US tariffs, declares it still sends oil to save Cuba

|

Russia is actively discussing measures to help Cuba overcome the fuel crisis, while underestimating US tax threats.

Ministry of Industry and Trade postpones gasoline and oil price management to the 4th day of Tet 2026

|

The gasoline and oil price adjustment period on February 19, 2026 will be moved by the Ministry of Industry and Trade to February 20, 2026 (4th day of Tet).

Northern peach blossoms enter Ho Chi Minh City, garden owners are excited because of fast consumption

|

Peach blossoms from northern garden villages have just entered Ho Chi Minh City and have attracted buyers. Many garden owners said that more than half of the goods have been sold in just a few days.

Ministry of Construction answers about the scope of operation of construction practice certificates

Xuyên Đông |

On the Government Information Portal, the Ministry of Construction answers citizens about the scope of operation of construction practice certificates.

The Ministry of Construction answers the time of site clearance for the high-speed railway project

Xuyên Đông |

The Ministry of Construction said it will advise the Government on site clearance for the high-speed railway project in January 2026.

The Ministry of Construction responds to cases of current construction permit exemption

Xuyên Đông |

On December 18, on the Government Information Portal, the Ministry of Construction responded to citizens about the current construction permit exemption regulations.