The Ministry of Construction answers the time of site clearance for the high-speed railway project

Xuyên Đông |

The Ministry of Construction said it will advise the Government on site clearance for the high-speed railway project in January 2026.

Ninh Binh voters recommend that the Ministry of Construction promptly inform and hand over the site clearance markers of the North-South high-speed railway project so that the locality can be proactive in land management, thereby avoiding violations arising during the project implementation.

After studying, the Ministry of Construction would like to respond as follows: The high-speed railway project on the North-South axis was approved by the National Assembly in Resolution No. 172/2024/QH15 dated November 30, 2024, the Government issued Resolution No. 106/NQ-CP dated April 23, 2025 to implement Resolution No. 172/2024/QH15 of the National Assembly.

In the past time, to speed up the project's progress, the Ministry of Construction has directed the Railway Project Management Board (investor) to work with localities and Vietnam Electricity Group to coordinate in compensation, support and resettlement.

Recently, 12/15 localities have started construction of resettlement areas on August 19, 2025; Vietnam Power Corporation has directed 15/15 local power companies; 4/4 regional power transmission companies have conducted a review, counting, and statistics of intersections with the project, and made preliminary plans to relocate affected power projects.

In parallel with the work with localities, the Railway Project Management Board is simultaneously conducting consultation selection work for packages such as project management consultation; bomb and mine clearance; environmental impact assessment...

Currently, the Government submitted to the National Assembly at the 10th Session a proposal to supplement the mechanism and policies applied to the high-speed railway project on the North-South axis and has been approved by the National Assembly to supplement the policy of "Allowing the separation of compensation, support and resettlement content of the North-South high-speed railway project into independent projects, capital allocated from the central budget and local budget.

Localities, relevant agencies, competent authorities, organizations that establish, decide on investment, and implement compensation, support, and resettlement projects in the area and the investment in items related to this content do not have to establish an investment policy. Based on the actual situation, the Government is assigned to provide detailed instructions on this regulation".

After having a Resolution of the National Assembly, the Ministry of Construction will advise the Government on instructions for implementation in January 2026.

In addition, the Prime Minister - Head of the Steering Committee for key projects and important national projects in the railway sector regularly meets with the Steering Committee to direct, urge progress, and resolve problems for key and important national railway projects.

Currently, the Railway Project Management Board is carrying out consultation selection procedures to serve the work of preparing the Project Feasibility Study Report.

Based on the research results of the consultant in preparing a feasibility study report and the decision of the competent authority on the route plan, station location, and depot area, the investor will immediately deploy the work of preparing boundary documents for site clearance, organizing deposits and handing them over to the locality according to regulations.

Xuyên Đông
RELATED NEWS

The Prime Minister requested to choose the investment method for the North-South high-speed railway in January 2026

|

Prime Minister Pham Minh Chinh emphasized that it is necessary to choose the investment method for the North-South high-speed railway project in January 2026.

No losses in compensation and resettlement for the High-speed Railway project in Khanh Hoa

|

Khanh Hoa province is reviewing the application of specific mechanisms and policies in compensation and resettlement for the North-South High-Speed Railway Project.

Proposing a specific mechanism for compensation, support, and resettlement to implement the high-speed railway project

|

The Ministry of Construction is drafting a specific mechanism for the North-South high-speed railway project, including a compensation, support and resettlement policy.

Securities continue to set a new peak to welcome Christmas

|

Despite strong differentiation in the pillar stocks group, the stock market still set a new peak approaching the historical threshold of 1,800 points.

Cambodia - Thailand ceasefire negotiations last 4 days

|

The Thai military said that ceasefire negotiations with Cambodia began on the afternoon of December 24 and will end on December 27.

Ring Road 3 is about to limit a series of vehicles during rush hour, people hope to escape congestion

|

Hanoi - The Department of Construction will pilot the limitation of cars with a load capacity of over 10 tons from Thang Long Avenue, National Highway 32 to the elevated Ring Road 3 from January 1, 2026.

Ministry of Education and Training: Many localities are in a hurry to arrange and merge mechanical schools

|

Some localities merging " mechanisms" schools cause imbalances in the scale of classes and school scores, potentially overloading facilities, affecting teaching quality.

Bac Me Hydropower Plant refuses to coordinate with other sectors to inspect 3 times

|

After National Highway 34 suffered a serious landslide, Tuyen Quang province repeatedly inspected and requested the Bac Me hydropower investor to work, but this unit did not cooperate.

The Prime Minister requested to choose the investment method for the North-South high-speed railway in January 2026

Xuyên Đông |

Prime Minister Pham Minh Chinh emphasized that it is necessary to choose the investment method for the North-South high-speed railway project in January 2026.

No losses in compensation and resettlement for the High-speed Railway project in Khanh Hoa

Hữu Long |

Khanh Hoa province is reviewing the application of specific mechanisms and policies in compensation and resettlement for the North-South High-Speed Railway Project.

Proposing a specific mechanism for compensation, support, and resettlement to implement the high-speed railway project

Xuyên Đông |

The Ministry of Construction is drafting a specific mechanism for the North-South high-speed railway project, including a compensation, support and resettlement policy.